Open Workbench By Wilmer Arellano Spring 2008
This is just an example, you can customize as you like.
In Favorites Gantt Charts, double-click the little square and enter: A new Phase with: Name Category And ID Make sure to select phase
The first phase has been created
In Favorites Gantt Charts, double-click the little square and enter: The Tasks with: Names Category And ID Duration Make sure to select task
The first task has been entered
This is how it would look after all tasks for the first phase have been entered
To indicate task’s dependencies drag from the end of one task to the beginning of the next one
Click here to auto- schedule
This is how it would look like Red Color indicates the Critical Path
Project with two phases included It is a coincidence that the two phases have same duration
Click to see the PERT The zoom commands were used to fit the chart in the window
On planning, Resource assignment, double click the little square to enter the resources and their costs
Do the same for non labor resources Use Equipment for Space
You can add the cost of components as “material”
Right click on the tasks and select assignment to assign resources to the tasks
Right click on the tasks and select assignment to assign resources to the tasks. Enter estimated hours in Estimate
As components were entered with a rate of $100, 1.5 will represent $150
The yellow color indicates that the task is low in resources, more hours or space or equipment, etc are needed If you need to add a new task or phase in between tasks or phases, right click the square and select insert task
There will be a problem if you click schedule again
As the Audio Interface Module and the Mixer Module were using the same resources, they were converted to sequential. You would need to add more resources to keep the tasks in parallel The zoom commands were used to fit the chart in the window
Another Low Frequency Engineer was included Two more Lab Spaces were included It was not necessary to increase the project duration
Click on controlling and then Revise Schedule to see the budget
Set The base Line Updating The Project Status
The task bar changes colour to reflect status (Red / Blue – Not Started) (Purple – Started) (Grey – Progress completed) The task name changes colour to reflect status (Red – Not Started) (Purple – Started) (Green – Completed)
Updating The Project Status If the task is completed enter 0 in Estimate
Updating The Project Status We reduced 20 hours but because of the weekend it appears to be a longer time
Milestones
Drag the milestone to the desired location
Milestones
Copy and Paste Table cells can be copied and pasted into excel By the way, this is a representation of the WBS
The Budget Even the Components are included here
& & Q uestions A nswers