BA6 newsRF power Cable list being worked out. BA6 newsLLRF Cable list done, pending check and confirmation.

Slides:



Advertisements
Similar presentations
Backwards Compatibility L4 – L2 W. Weterings LBCC - 14.
Advertisements

Marion M. White Undulator System 07 April 2005 LCLSLCLSLCLSLCLS Undulator System Tests Marion M. White ANL-ASD-LCLS.
Vacuum, Surfaces & Coatings Group Technology Department 04/12/2014 R. Salemme – COLDEX results during SPS Scrubbing Run I Electron Cloud Meeting #18,
Session 8 - Long Shutdown 2 Strategy and Preparation LIU Planned Activities Reference : RLIUP Oct.2013 (indico) “Work Effort in the LHC Injector Complex,
QRL Leak Tests the story so far………. Paul Cruikshank on behalf of TE-VSC colleagues & AL4030 Consortium (S133) 1 Paul Cruikshank TE/VSC - QRL Leak Tests.
HLTC 15 th April 2014 EDMS: Y. Muttoni EN-MEF-INT with the contribution of P. Fessia.
HIE-ISOLDE (High Intensity and Energy) project Protection of superconducting solenoids MPE work shop – December 14, 2010 G.J. Coelingh TE-MPE-CP.
RADWG 6 TH TH OCTOBER 2012 G. Spiezia (EN/STI/ECE)
HIE-ISOLDE contribution packages M. Pasini BE/RF.
09/28/07Shutdown’07 Week 8 F.G. Garcia1 MTA beam line installation Weekly Report September 28, 2007 Period covered: September 24 th September 28 th (Week.
LIU-IONS Linac3 meeting LIU Project – Planning and Installation Julie Coupard EN/MEF-OSS.
WP3 Required interfaces for cryostat design / integration Patxi DUTHIL SPL 3 rd Collaboration Meeting, CERN, Geneva November 12 th 2009.
Global Design Effort Beam Delivery System => EDR LCWS07 June 2, 2007 at DESY Andrei Seryi for BDS Area leaders Deepa Angal-Kalinin, A.S., Hitoshi Yamamoto.
1 1. Some recent views ( ) 2 Linac tunnel
HIE-ISOLDE Project Status Report
9 th AWAKE Technical Board 11 March Actions from Last Technical Board WP laser and MPP: decide until March 2015 which compressor design will be.
CMS Muon detectors for the GIF++ DRAFT Needs discussion within CMS Muon community A. Sharma.
ISOLDE Activities for LS2 Richard Catherall EN-STI ISOLDE Technical Coordinator.
Consolidation activities for GS-SE Luigi Scibile GS-SE Accelerator Consolidation Workshop, EDMS:
2. Linac Systems 3. Booster Systems 4. Installation commiss. 5. Building, Infrastruct. 2.1 Ion Source and LEBT, R. Scrivens, BE/ABP 2.2 Radio Frequency.
TE-CRG Interfaces Fair S-FRS magnets - CERN cryogenics Control interface CERN-GSI for B.180 cryogenics Control interface CERN-GSI for B.180 cryogenics.
Cryogenics for crab cavities – SPS/LHC 2 nd HiLumi LHC meeting – Frascati (Italy) 15 November 2012 K. Brodzinski and L. Tavian on behalf of cryogenic team.
Floor plans, Infrastructure & Logistics Hie-Isolde Spectrometer Workshop Physics Department, Lund University 10 March, 2011 Hie-Isolde Erwin Siesling.
HIE-ISOLDE Project: Planning & Resources Y. Kadi (EN-HDO) and the HIE-ISOLDE Project team.
Survey activities during LS1 Dominique Missiaen On behalf of the SU section.
PS-EA Update RadWG August 23 rd 2012 Radiation 2 Electronics (R2E) LHC Activities RadWG August 23 rd 2012 PS East Area Update M. Brugger on behalf of the.
Interface of FP420 to LHC FP420 meeting 28-Sep-2006.
Krzysztof Radwan, PJAS, TE/VSC/ICM Interlocks, Controls and Monitoring Section HIE-ISOLDE Vacuum Controls INSTALLATION.
TE-CRG Activities D. Delikaris, TE-CRG.
SPSU – May 19, 2009 – Resources needed for SPS coating project– J. Bauche 1 Coating of the SPS Main Dipoles Vacuum Chambers: Resources Needed for Project.
R2E relocation & shielding LS1 preparation Anne Laure Perrot EN/MEF- LE Discussion with OP colleagues, 5 th July 2012.
Each converter 3 racks (fighting for 2?) Access from front and rear of each rack! 56 racks total + 6 racks Ethernet/control Existing RF equipment to be.
D.Macina TS/LEATOTEM Meeting25/02/2004 Roman Pot test at the SPS Test of the Roman Pot prototype in the SPS proposed in December 2003 (CERN/LHCC ):
SPS movable table Joanna Swieszek, Kurt Artoos (EN-MME) 14/04/2016.
Scope of CERN SC RF Activities Status Report for A&T Sector Meeting 18 Nov’13 BE, TE, EN Departments Summarized by José Miguel JIMENEZ 1 BE-RF (E. Jensen*,
HiRadMat status report Adrian Fabich HiRadMat EAM, 4. March 2016 EuCARD-2 is co-funded by the partners and the European Commission under Capacities 7th.
Crab cavity test installation in SPS
February 4 th, Quality assurance plan: production, installation and commissioning N.Vauthier TE-CRG Technical Review on Beam Screen Heater Electronics.
LIU-PSB Working Group meeting: 25/06/2015, Markus Zerlauth Consolidation of magnet interlocks in the PS complex – Warm magnet Interlock System (WIC) R.Mompo,
Laser Line work package (WP6) AWAKE Technical Board meeting 19 May 2014.
LIU Configuration Management EDMS Documentation, Layout and ECRs This presentation follows the LIU-PSB specific presentation done on 9 th October 2014.
Cost and schedule for ELENA Beam Transfer Systems W. Bartmann, J. Borburgh, E. Carlier, L. Ducimetiere, T. Fowler, M. Hourican, R. Ostojic, L. Sermeus.
LIU and TE/VSC activities LIU-SPS aC coating & flange impedance reduction Paul Cruikshank LIU & TE/VSC activities, 23/6/2016 Paul Cruikshank.
LIU and TE/VSC activities Status September 2016 LIU-SPS aC coating & flange impedance reduction Paul Cruikshank on behalf of TE-VSC LIU & TE-VSC, 19/9/2016.
Collimation Activities during EYETS
Cryomodule test stand at ESS site
Crab cavities Cryogenics progress for the SPS
Schedule CM SPS G.Vandoni.
IT-4189 Supply and installation of a cryogenic distribution system
BE-ICS Activities during the LS2 Period (15 min)
Equipment simplified model SMR UR safety
ELENA installation and commissioning status
BA6 – crab cavity activities in EYETS
Installation of an Instrument on a CERN machine
Feasibility and implication of installation of the string test in SM18 with a slope M. Bajko WP16.
BE/RF-IS Contribution to LIU C. Rossi and M. Paoluzzi
Hollow e- lens, Cryogenic aspects
SPS CC: Final plan for interlocking of crab cavities in SPS
XFEL Vacuum System Commissioning
WPs concerned by L4 connection:
SPS East Extraction bump inhibit during COLDEX operation
SPS activities during LS2 TE-EPC (Power Converter Group)
Status with crucial LSS5 kicker transmission line cables
Cryogenic C&C Scope of work
BE-ICS work for SPS Safety Systems
Linac4-PSB 160 MeV connection readiness review ( TE/VSC )
HIE-ISOLDE Project: Planning & Resources
HIE-ISOLDE Status & Summary of HIE-ISOLDE SC
Project management Ray Veness.
ThomX – Commissioning Meeting – 25/01/2018
Presentation transcript:

BA6 newsRF power Cable list being worked out

BA6 newsLLRF Cable list done, pending check and confirmation

Interlocks Machine protection Safety & Functional, equipment protection Inspired by the Linac4 test stand, HIE-Isolde SC linac, plus meetings with BE/OP, Coldex, TE/MPE, BE/ICS DRAFT for discussion

plan.cern.ch PREPARATION TeamRequired actionsDonePending BE/RFDefinition of beam instrumentation requirementsTo complete BE/BInew BPM integrationPending requirement from BE/RF BE/ICSIntegration study with the new SPS-fire-safety systemSpec definedInventory of all equipment for crabs in TA6: cryo, vac, table BE/ICSStudy of access conditions and ODHStrategy definedCryogenic safety analysis EN/ACEPlanning; integration; scans; reinforcementScans, tunnel studyInfo on BA6, TA6: cryo. Master plan EN/ACESurvey and alignment EN/CVStudy infrastructure for water and ventilationStrategy definedDetailed power needs EN/ELUncabling; cable purchaseStrategy definedDetailed purchase breakdown, DIC EN/MME Design of componentsTable specification TE/ABTClear BA6; support uncabling, integration of new TPSGdoneCommon SRR TE/CRGProcurement of mobile cold-box, transfer-line, infrastructure Specifications, integration models, cabling strategy, installation strategy TE/MPEPreparation of CIBU, DIC for the related cable, for SPS-ring and EXTR1 Strategy definedWrap-up with all systems TE/VSCProduction of Y chamber, new sectorization and other chambers In workInsulation vacuum integration models HSE/SEEAssessment of support structuresContact missing, Pending information for cryogenic heavy equipment.

Main missing items TeamWhatProgressOpen BE/RFBeam instrumentationSee WP4 CoordinationDoes BE/BI have a clear specs for development? BE/RF (GV) Supporting structuresInventory being doneWho designs and produces? PB for advice Interlock: functional, beam, safety Draft prepared for discussion Is any essential system missing? Dedicated meeting TE/VSC EN/MME TE/CRG Electronics in the tunnel (TA6) Dose estimate, BatMons for SEE Detailed inventory, type of electronics, to present to RadWG EN/MME TE/CRG Motorized table, transfer line, cold-box, ancillaries Specifications for purchase HSE, CRG, ICS Safety analysisInput data knownCalculation

Documents

AGENDA SPS Installation Space Reservation Request, coupling crab-cavity and TPSGIn work (90%) Conceptual Specification, based on the existing DRAFTIn work (50%) Engineering Specification, to be used as a basis for ECR and Safety fileJune DICDuring fall, but cable orders have to be placed before June ECRAt latest in November for EYETS preparation (but it can follow the ES) Safety review of the SPS Installation, on the model of the HIE-Isolde one. After September 15th, well before EYETS