CSN1, Roma, 18 Luglio 2014 Catia Milardi on behalf of the DA  NE Team DAΦNE status.

Slides:



Advertisements
Similar presentations
1 Group 1 Meeting, Catania, Sept,16, 2002 STATUS REPORT ON DAFNE P. Raimondi for the DAFNE team.
Advertisements

DA  NEUpgrade Status DA  NE Upgrade Status David Alesini, LNF-INFN For the DA  NE Upgrade and Commissioning Team (*) (*) David Alesini, Maria Enrica.
Towards an extremely-flat beam optics with large crossing angle for the LHC José L. Abelleira, PhD candidate EPFL, CERN Beams dep. Supervised by F. Zimmermann,
Crab-Waist experiment results The 40th ICFA Advanced Beam Dynamics Workshop on High Luminosity e + e – Factories, April 14–16, 2008 Budker Institute of.
Recent observations of collective effects at KEKB H. Fukuma, J. W. Flanagan, S. Hiramatsu, T. Ieiri, H. Ikeda, T. Kawamoto, T. Mitsuhashi, M. Tobiyama,
Super B-Factory Workshop, Hawaii, April 20-22, 2005 Lattice studies for low momentum compaction in LER M.E. Biagini LNF-INFN, Frascati.
PEP-II B Factory Machine Status and Upgrades John T. Seeman for the PEP-II Staff SLAC DOE Site Review April 9, 2003.
June 2-4, 2004 DOE HEP Program Review 1 M. Sullivan for the PEP-II Team DOE High Energy Physics Program Review June 2-4, 2004 PEP-II Status and Plans.
SLAC Accelerator Department The PEP-II Accelerator John T. Seeman Assistant Director of the Technical Division Head of the Accelerator Department SLUO.
January 15, 2005D. Rubin - Cornell1 CESR-c Status -Operations/Luminosity December/January vs September/October -Machine studies and instrumentation -Simulation.
 An h=4 (30 MHz) RF system will be used for electron operation. For protons, this would correspond to h=56, and the 1 kV maximum gap voltage would only.
Progress towards nanometre-level beam stabilisation at ATF2 N. Blaskovic, D. R. Bett, P. N. Burrows, G. B. Christian, C. Perry John Adams Institute, University.
Future Very High Luminosity Options for PEP-II John T. Seeman For the PEP-II Team e+e- Factories Workshop October 13-16, 2003.
STRIPLINE KICKER STATUS. PRESENTATION OUTLINE 1.Design of a stripline kicker for beam injection in DAFNE storage rings. 2.HV tests and RF measurements.
March 7, 2007 LET Issues (Cai/Kubo/Zisman) Global Design Effort 1 Low-Emittance Tuning Issues and Plans Yunhai Cai, Kiyoshi Kubo and Michael S. Zisman.
January 13, 2004D. Rubin - Cornell1 CESR-c BESIII/CLEO-c Workshop, IHEP January 13, 2004 D.Rubin for the CESR operations group.
October 4-5, Electron Lens Beam Physics Overview Yun Luo for RHIC e-lens team October 4-5, 2010 Electron Lens.
Energy Spectrometer for the ILC Alexey Lyapin University College London.
CASA Collider Design Review Retreat HERA The Only Lepton-Hadron Collider Ever Been Built Worldwide Yuhong Zhang February 24, 2010.
CesrTA Experimental Plan M. Palmer for the CesrTA Collaboration November 17, 2008.
1 BROOKHAVEN SCIENCE ASSOCIATES Storage Ring Commissioning Samuel Krinsky-Accelerator Physics Group Leader NSLS-II ASAC Meeting October 14-15, 2010.
DA  NE Status Report C. Milardi, D. Alesini, M.E. Biagini, C. Biscari, R. Boni, M. Boscolo, B. Buonomo, A. Clozza, G. Delle Monache, E. Di Pasquale, G.
1 Proposal for a CESR Damping Ring Test Facility M. Palmer & D.Rubin November 8, 2005.
Beam-Beam and e-Cloud in RHIC Oct. 6, 2015 Haixin Huang, Xiaofeng Gu, Yun Luo.
Fast feedback, studies and possible collaborations Alessandro Drago INFN-LNF ILCDR07 Damping Rings R&D Meeting 5-7 March 2007.
Flat-beam IR optics José L. Abelleira, PhD candidate EPFL, CERN BE-ABP Supervised by F. Zimmermann, CERN Beams dep. Thanks to: O.Domínguez. S Russenchuck,
Vertical Emittance Tuning at the Australian Synchrotron Light Source Rohan Dowd Presented by Eugene Tan.
Damping Ring Parameters and Interface to Sources S. Guiducci BTR, LNF 7 July 2011.
RHIC Run11 Summary May 6, 2011 RSC Meeting Haixin Huang Luminosity Availability Polarization RHIC setup issues.
1 BINP Tau-Charm Project 3 February 2010, KEK, Tsukuba E.Levichev For the BINP C-Tau team.
14th ESLS RF Workshop ELETTRA / Trieste, Italy / 2010 September The Elettra Storage Ring and Top-Up Operation Emanuel Karantzoulis.
02/04/2009 AS-TAGL Mtg Global Design Effort 1 CesrTA Update Mark Palmer CLASSE.
February 5, 2005D. Rubin - Cornell1 CESR-c Status -Operations/Luminosity -Machine studies -Simulation and modeling -4.1GeV.
Beam Physics Issue in BEPCII Commisionning Xu Gang Accelerator physics group.
CESR Test Accelerator Optics Correction and Tuning Tools David Sagan Cornell University.
DA  NE Status Report P. Raimondi Scientific Committee Nov-2005.
Global Design Effort ILC Damping Rings: R&D Plan and Organisation in the Technical Design Phase Andy Wolski University of Liverpool and the Cockcroft Institute,
Pushing the space charge limit in the CERN LHC injectors H. Bartosik for the CERN space charge team with contributions from S. Gilardoni, A. Huschauer,
LIU-Ions overall status and outlook: LEIR H. Bartosik for the LIU-IONS LEIR team* with lots of material from “Beam dynamics studies on LEIR”, H. Bartosik,
Haixin Huang AGS Cold Snake: Status and Plans.
DA  NE: status report M. Preger on behalf of the DA  NE team 22/11/2010.
Workshop on Accelerator R&D for Ultimate Storage Rings – Oct Nov.1 – Huairou, Beijing, China A compact low emittance lattice with superbends for.
Introduction of Accelerators for Circular Colliders 高亮度 TAU-CHARM 工厂 & 先进光源, 2014/09.
Electron Cloud Studies at DAFNE Theo Demma INFN-LNF Frascati.
The machine status and operating mechanism of BEPCII CAO, Jianshe Institute of High Energy Physics, CAS April 16, 2013 The 4th Accelerator.
TDR and R&D Plans J. Seeman and M. Biagini For Super-B Staff.
44 th LNF Scientific Committee, Frascati, 4-5 June 2012 DA  NE Status Catia Milardi (on behalf of the DA  NE Team)
Crabbed Waist Scheme at DA  NE M. Zobov for DA  NE Upgrade Team SuperB IV, November 2006 Monte Porzio Catone - Italy.
Jørgen S. Nielsen Center for Storage Ring Facilities (ISA) Aarhus University Denmark ESLS XXIII (24-25/ ), ASTRID2 facility 1.
WP15.4 Status March 2017.
Operating IP8 at high luminosity in the HL-LHC era
Riunione CSN1 del 29 settembre - 3 ottobre 2014, Catania
Operating Experience with Electron Cloud Clearing Electrodes at DAFNE
For Discussion Possible Beam Dynamics Issues in ILC downstream of Damping Ring LCWS2015 K. Kubo.
(on behalf of the DAFNE team)
Beam-beam effects in eRHIC and MeRHIC
BE/RF-IS Contribution to LIU C. Rossi and M. Paoluzzi
10 MHz amplifier status G. Favia
DAFNE experience with compensating wires
Coupling Correction at the Australian Synchrotron
Multiturn extraction for PS2
Status of the VEPP-2000 Collider Project at Novosibirsk
BINP Tau-Charm Project
The Proposed Conversion of CESR to an ILC Damping Ring Test Facility
Electron Rings Eduard Pozdeyev.
SLHC-PP kick-off meeting, CERN 9 April 2008
The Lepton colliders Data Base
Proposal for a CESR Damping Ring Test Facility
SuperB Accelerator Overview
Crab Crossing Named #1 common technical risk (p. 6 of the report)
Presentation transcript:

CSN1, Roma, 18 Luglio 2014 Catia Milardi on behalf of the DA  NE Team DAΦNE status

The DA  NE Team C. Milardi, D. Alesini, M.E. Biagini, S. Bini, M. Boscolo, B. Buonomo, S. Guiducci, S. Cantarella, A. De Santis, G. Di Pirro, G. Delle Monache, A. Drago, L. Foggetta, O. Frasciello, A. Gallo, A. Ghigo, F. Guatieri, F. Iungo, C. Ligi, G. Mazzitelli, L. Pellegrino, R. Ricci, U. Rotundo, C. Sanelli, G. Sensolini, M. Serio, A. Stella, A. Stecchi, M. Zobov, LNF-INFN, Frascati, Italy; R. Gargana, A Michelotti, Cabibbo-Lab, Rome, Italy; D. Shatilov, BINP SB RAS, Novosibirsk, Russia; A. Valishev, Fermilab, Batavia, USA; M. Tobyiama, KEK, Tsukuba, Japan. Other Contributors

Outline overview on DA  NE DA  NE c ommissioning How the upgrade improved operations Latest luminosity results Pushing luminosity even further Conclusions

BTF X-ray eV X-ray eV IR 1.24 meV eV UV eV The DA  NE Accelerator Complex LNF are also part of the European synchrotron light Infrastructures

DA  NE and KLOE

3 unscheduled interruptions due to external circumstances causing two and half months of inactivity STOP scheduled accidental fault SKEW CHV PS installed CRYO plant Vacuum opened in ¼ MRp Water Electric power Cooling System maintanence – CRYO plant PS cabling - Linac Commissioning

IR Structural Modifications A pair of carbon fiber composite legs have been added to the existing ones some rubber pads previously inserted below the cradle support have been removed, thus strengthening the structure and increasing its rigidity. The spectrum of a previously observed vertical beam oscillation got modified. The main harmonic was shifted toward higher frequencies, ~15 HZ, and its amplitude reduced by a factor four MRp

vertical orbit oscillation vertical orbit oscillation recent measurements on e- beam compared with 2012 time domainFFT analysis natural beam oscillation around the reference orbit as recorded at BPBEL202 lower harmonic reduced in amplitude and increased in frequency with respect to 2012 reduced peak to peak oscillation in 2013

Spherical Vacuum chamber Heating problem affecting the low-  defocusing quadrupole downstream the e- beam has been fixed working point stability in operations New BPMs allow more accurate beams overlap and transverse betatron coupling studies

A new supervision and control system, based on an industrial SCADA MOVICON, performs a smarter management of the installation The renewed PLC’s and previous devices are under control of an unique supervision system. Efficient and user friendly tools give access to subsystem information (data, alarm, faults) allowing a very useful data analysis Stability of the power supplies temperatures has been improved Ancillary plants Control System

The Control System architecture has been deeply modified: Most of the VME bus platform have been dismissed The whole data flow has been redirected to the network An Obiect Caching service (Memcached) hosts the live data Large part of the front-end boards (serial, DAQs, ADCs, etc.) replaced by network devices, which allowed for the porting of many control programs to remote Linux virtual machines. Using serial device servers instead of serial communication boards, permitted to increment the number of daisy chain lines (RS-422) employed in connecting the magnets' power supplies. Almost all distributed front-end VME processors (forty-five custom boards) with Intel boards, run Linux. New Linux servers for the core services (NFS, DHCP, diskless boot, MySQL, memcached) and for the SunRay™ thin-clients employed as consoles. DCS is now more performable, reliable and its overall uptime significantly increased commutation of the injection system between the e + and the e - operating modes is now considerably faster thanks to the increased number of daisy chain connecting the relative power supplies Computing and memory resources available for the virtual machines Control System

Commissioning Commissioning started mainly by the end of January 2014, but it has been severely slowed down by 3 main interruptions due to external circumstances causing, in total, two and half months of inactivity. Transverse betatatron coupling all skew QUADs off :  +  ~ 0.4%  -  not yet optimal Tuning the skew QUADs: 0.2% <   0.3% (both beams) working points adopted x - = y - =  x + = y + = according LIFETRAC simulations should provide good luminosity e - ring optics

Beam Dynamics Highest currents stored, so far, in 98 bunches spaced by 2.7 ns are: I - = 1.85 A I + = 1.15 A These currents are the highest ever achieved after installing the new IR for the KLOE-2 detector, based on the Crab-Waist collision scheme. The three independent bunch-by-bunch feedback systems installed on each ring are essential for high current multi-bunch operations. The e + vertical feedback is now using a new ultra-low noise front-end module, designed in collaboration with the SuperKEKB feedback team, aimed at reducing the noise contribution to the transverse vertical beam size in collision.

Beam dynamics in the e + ring is clearly dominated by the e-cloud induced instabilities which are kept under control by: powerful bunch-by-bunch transverse feedback systems solenoids wound all around the straight sections electrodes installed inside dipole and wiggler vacuum chambers. Electrodes effectiveness has been already proved in 2012 polarizing the stripline with a positive voltage in the range 0÷250 V Simulations indicate that a factor two higher voltage is required to completely neutralize the e-cloud density due to a e + current of the order of 1 A e + Beam Dynamics

The electrode power supplies have been replaced with devices providing a maximum negative voltage of 500 V, the change of polarity was intended to limit the current delivered by the power supplies New setup test: I + =  700  mA in 90 contiguous bunches e-cloud induced effects have been mitigated also by: Moving  x  y to higher positive values lengthening the bunch by reducing the RF cavity voltage e-cloud Mitigation

KLOE CW-IR preliminary test Vertical beam-beam scan Comparison Among DAΦNE Best Runs with and without Crab-Waist Peak Luminosity (100 bunches) 2012 achievements

DA  NE CW upgrade SIDDHARTA (2009) DA  NE KLOE (2005) DA  NE (CW) KLOE (2012) DA  NE (CW) KLOE-2 (2014) L peak [cm -2 s -1 ] I - [A] I + [A] N bunches L peak exceeds by a 13% the best luminosity ever achieved, at DA  NE, during operations for an experimental apparatus including high field detector solenoid. Peak Luminosity Background presently has been reduced to levels almost compatible with the detector data-taking 100 bunches L ∫1 hour = 0.4 pb -1 moderate injection regime

Vertical beam-beam Luminosity scan  meas y is still considerably high since the transverse betatron coupling in the e - ring is not yet properly corrected

Crab-Waist Sextupoles Crab-Waist Sextupoles effectiveness has been tested on the e + ring I CS = 210 A I CS = 150 A DA  NE luminosity monitor Crab-Waist Sextupoles strengths are 30% and 50% lower than the nominal ones for e + and e - respectively.

10 Bunches Luminosity L peak ~ cm -2 s -1 might be achieved by using 100 bunches Beam-beam is not a limiting factor Crab-Waist Sextupoles work (even at lower strength) This result can be improved by: optimizing dynamical vacuum perfecting colliding beams parameters tuning multi-bunch and high current operations Aiming at minimizing the impact of collective effects on L

KLOE-2 data taking test L ∫12 hour = 3.7 pb -1

Pushing luminosity further A considerably higher luminosity might be attained by: Improving the transverse betatron coupling correction in the e - ring optimizing the present rings optics and working point Setting the CW-Sextupoles to the nominal values improving dynamic vacuum Increasing stored currents and number of colliding bunches Further contributions might come also from exploring new optics configuration with higher  c and from extensive beam dynamics studies.

Conclusions The DA  NE collider is operational again. Despite the adverse circumstances several clear results have been achieved: the instantaneous luminosity and the maximum stored beam currents are now the highest ever achieved in operations with an experimental apparatus including high field detector solenoid. Limiting factors have been well understood and still many parameters can be ameliorated to further improve the collider performances Some criticalities affecting specific subsystems will be cured during the summer shut-down

Thank you for your attention