DDBA magnets Chris Bailey Low emittance rings Sept 17-19 2014 Frascati.

Slides:



Advertisements
Similar presentations
Simona Bettoni and Remo Maccaferri, CERN Wiggler modeling Double-helix like option.
Advertisements

EMMA Magnet Design Ben Shepherd Magnetics and Radiation Sources Group ASTeC STFC Daresbury Laboratory.
CIEMAT technological contributions to linear colliders Fernando ToralGandía, 3/12/2005.
Field measurements of QEA magnets at KEK Mika Masuzawa May 30, 2006.
Magnets for the ESRF upgrade phase II
Ultra Low Vertical Emittance at the Australian Light Source Mark Boland on behalf of Rohan Dowd 1.
Zachary Wolf Undulator Tuning June 17, 2008 Undulator Tuning Status Z. Wolf, S. Anderson, R. Colon, S. Jansson, S.Kaplunenko,
LCLS Undulators October 14, 2004 Heinz-Dieter Nuhn, SLAC / SSRL MMF Review Introduction to the LCLS Undulators Heinz-Dieter Nuhn,
Magnet designs for the ESRF-SR2
Engineering Integration of the Double- Double Bend Achromat (DDBA) into the Diamond storage ring Jim Kay Diamond Light Source Low emittance ring 2013 workshop.
BROOKHAVEN SCIENCE ASSOCIATES Abstract Magnetic Specifications and Tolerances Weiming Guo, NSLS-II Project In this presentation I briefly introduced the.
1 BROOKHAVEN SCIENCE ASSOCIATES Storage Ring Magnet Production Status Satoshi Ozaki, Manager, SR Magnet Production 9 th ASAC Meeting for the NSLS-II Project.
BROOKHAVEN SCIENCE ASSOCIATES Abstract Magnet Design Workshop: Magnet Design and Analysis Charles Spataro, NSLS-II Project NSLS-II is a new 3Gev synchrotron.
1 / 19 M. Gateau CERN – Geneva – CH 14th International Magnetic Measurement Workshop September 2005, Geneva, Switzerland.
Magnet designs for Super-FRS and CR
Hall C Meeting SHMS Magnets and Support Structure Design and Procurement Status Paul Brindza January 26, 2009.
Daniel Schoerling TE-MSC-MNC 1 Magnets Daniel Schoerling on behalf of WP 2.2 and WP 2.16 ELENA Project Review 14 th – 15 th October IT.
1 BROOKHAVEN SCIENCE ASSOCIATES Abstract Magnet and Girder Integration Lewis Doom, NSLS-II Project National Synchrotron Light Source II (NSLS-II) will.
Permanent Magnet Quadrupoles for the CLIC Drive Beam Jim Clarke, Norbert Collomb, Neil Marks, James Richmond, and Ben Shepherd STFC Daresbury Laboratory,
ASTeC Report for CLIC-UK Jim Clarke on behalf of all ASTeC & Technology Department staff contributing to CLIC-UK STFC Daresbury Laboratory, UK CERN-UK.
BROOKHAVEN SCIENCE ASSOCIATES 0 Top-Off Safety Yongjun Li ASAC Meeting October 22, 2009.
ERHIC: an Efficient Multi-Pass ERL based on FFAG Return Arcs June 9, 2015Stephen Brooks, ERL On behalf of the eRHIC design team.
1 J.DiMarco 16Nov2010 LQS01b Magnetic Measurements Results ( preliminary ) J. DiMarco 16Nov2010.
ATF2 Magnets ATF2 Magnets 27/28 Feb 2007Cherrill Spencer, SLAC. Info for QC3 machining discussion 1 Information for discussion about how to enlarge the.
Optimization of Field Error Tolerances for Triplet Quadrupoles of the HL-LHC Lattice V3.01 Option 4444 Yuri Nosochkov Y. Cai, M-H. Wang (SLAC) S. Fartoukh,
Magnet Design & Construction for EMMA
MBA Magnets MultiBend Achromat Magnets 9/27/2013 Review By Mark Jaski.
Vertical Emittance Tuning at the Australian Synchrotron Light Source Rohan Dowd Presented by Eugene Tan.
Analysis of Multipole and Position Tolerances for the ATF2 Final Focus Line James Jones ASTeC, Daresbury Laboratory.
High Resolution Separator
Magnetic Metrology of SOLEIL Synchrotron S.R. Multipoles IMMW 14, A. Madur Magnetic Metrology of SOLEIL Synchrotron Storage Ring Multipoles A. Dael, P.
Emittance Tuning Simulations in the ILC Damping Rings James Jones ASTeC, Daresbury Laboratory.
CLIC requirements on Warm Magnets (for CLIC Modules mainly) 1 M. Modena, CERN TE-MSC 13 April 2011 CERN-UK Collaboration Kick-off Meeting.
Principals of fast injection and extraction R. Apsimon.
Correctors magnets V. Zubko, IHEP, Protvino SIS 300 Pre-consortium Meeting Thursday 19 March 2009, Protvino.
MEIC Detector and IR Integration Vasiliy Morozov, Charles Hyde, Pawel Nadel-Turonski MEIC Detector and IR Design Mini-Workshop, October 31, 2011.
Warm-Cold Changes in the Sextupole Harmonic in the Quadrupole Magnets for the BEPC-II Luminosity Upgrade Animesh Jain Brookhaven National Laboratory Upton,
Practical aspects of small aperture quadrupoles Dr Ben Leigh Tesla Engineering Ltd.
1 BROOKHAVEN SCIENCE ASSOCIATES 12th International Workshop on Accelerator Alignment September 10-14, 2012 Fermilab, Batavia, Illinois, U.S.A NSLS-II Girder.
1 Magnetic measurements of the Super-FRS magnets 1 Overview: - Measurement systems for dipoles - requirements - Measurement systems review - Open points.
CERN –GSI/CEA MM preparation meeting, Magnetic Measurements WP.
Design of the magnets for the MAX IV project Martin Johansson, Beam Dynamics meets Magnets-II workshop, Bad Zurzach, Dec
Plans for Diamond-II ESLSXX Workshop, Bessy II, 19 November 2012 R. Bartolini Diamond Light Source and John Adams Institute for Accelerator Science University.
September 27, 2007 ILC Main Linac - KOF 1 ILC Main Linac Superconducting Quadrupole V. Kashikhin for Magnet group.
Yingshun Zhu Design of Small Aperture Quadrupole Magnet for HEPS-TF
GSI Helmholtzzentrum für Schwerionenforschung GmbH Super-FRS multiplet field.
Ultra-low Emittance Coupling, method and results from the Australian Synchrotron Light Source Rohan Dowd Accelerator Physicist Australian Synchrotron.
Part 2: NbTi Magnet Performance Yury Ivanyushenkov for the APS SCU Team: S. Bettenhausen, C. Doose, M. Kasa, Q. Hasse, I. Kesgin, D. Jensen, S. Kim, G.
Diamond-II upgrade toward ultra-low emittance T. Pulampong University of Oxford Octoberfest October 2014 Royal Holloway, London.
Cherrill Spencer, SLAC Member of ATF2 Magnet Team
Yingshun Zhu Accelerator Center, Magnet Group
Some Design Considerations and R &D of CEPCB Dipole Magnet
High Gradient Magnet Design for SPring-8 Upgrade Plan
Page Headline CBETA Splitter.
Procurement, Measurement and Installation of 2 Octupoles for ATF
Advanced Photon Source Upgrade Project:
Halbach Magnets: Design, Prototypes & Results
Arc magnet designs Attilio Milanese 13 Oct. 2016
Coupling Correction at the Australian Synchrotron
CHEN, Fusan KANG, Wen November 5, 2017
Magnets for the ESRF upgrade phase II
Magnet developments for the ESRF-EBS
Yingshun Zhu Accelerator Center, Magnet Group
On the accuracy of port assembly at Wendelstein 7-X
PERMANENT MAGNET QUADRUPOLE FOR THE LINAC 4 CCDTL
Beam-Based Alignment Results
IR Lattice with Detector Solenoid
CEPC Collider Magnets CHEN, Fusan November 13, 2018.
CEPC Booster Ring Magnets
Electron Collider Ring Magnets Preliminary Summary
Presentation transcript:

DDBA magnets Chris Bailey Low emittance rings Sept Frascati

Outline DDBA What and why Where have we got to Choices affected by single cell Tolerances Each of the magnets Mountings Measurements Alignment and final setup

What is DDBA and Why Double Double Bend Achromat is a single cell upgrade based on the early Diamond II studies. Central part of modified cell emptied to give additional Insertion device space in ring. Is being used to provided additional beamline with more powerful Insertion Device than would be otherwise possible. Also gives experience and understanding of some of the issues involved in the design and build of low emittance lattice upgrade

Project status Cell 2 in progress. Magnet contract placed Vacuum vessels contract placed ? New girders ordered ? Temporary wiring for existing cell to make space for new wiring install in progress ? 2 nd cell (11), approved awaiting funding confirmation, target 2 years after first cell. Beam dynamics work in progress, price for additional set of magnets included in contract

Schedule MilestoneDate Magnet contract placedJun 14 Vacuum vessel contract placed Sep 14 Girders orderedNov 14 Existing installation moved to temporary cabling Sep 15 Vacuum vessels DeliveredSep 15 Magnets DeliveredNov 15 Girders AssembledApr 16 New cabling installedJun 16 Front end for new beamline installed (partial) Jun 16 DDBA Cell installed and commissioned Aug / Sep 16 First Light to new beamline Jan 17 MilestoneDLS (Specific ation) Current Schedu le Preliminary Design review Aug 14Sep 14 Final Design reviewFeb 15End Oct 14 DLS familiarisation with Measurement system ----Oct-Dec 14 Prototype magnet testing Jun 15Mar 15 Delivery of Series magnets Nov 15Sep 15 Re-measure magnets installed on girder (Final alignment) Nov-Dec 15 Girders Ready for install Apr 16

What are the implications of only changing a single cell… Single variation of quadrupole and sextupole, only 2 variations of dipole. Match to existing power supply designs and cooling system. Choice of windings in Dipole. Some of the tolerance requirements are relaxed, compared to full ring. There will not be spare girders so needs to be possible to swap magnets. Length of Shutdown for install very short :- preparatory cabling

Lattice and Magnets Dipole 0.67 and m Tm T Central Quadrupole 0.25 m 70 Tm -1 Sextupole m 2000 Tm -2

Errors and tolerances Request in specification Surface tolerances 20µm Assembly tolerances ±15µm Surface on dipole will only be possible to verify to 40µm due to distances to reference points. Modelling work on full geometry models with errors is ongoing (slowly) and suggests there may be scope to relax tolerances slightly. Problems with models mean confidence is not high enough. Alignment system resolution and errors. Resolution 5µm Accuracy 10µm

Dipole Dipole parameters Nominal Field0.8 T Gradient Tm -1 Length0.670 & m Minimum Gap19.8 mm Good field region ± 10 mm X ± 4mm Y Long Dipole with trim at 65A Integrated field components / nominal length Dipole0.800 T Quadrupole Tm -1 Sextupole0.2 parts 10^4 Octopole All others<0.1 Offset825 µm

Dipole : practical comments Manufacturing accuracy achieved by wire erosion of pole in place on main structure. All mating surfaces are flat. Poles are curved but back leg is straight. There are feature surfaces that should be parallel for measurement. The field is optimised by adjusting the length and depth of the pole noses. The strength of the integrated sextupole has been minimised by adjusting the angle of rotation of the end chamfers Lateral position is used to match field and gradient. ±2mm adjustment. Longitudindal space is very limited Using 2 coils: 7-turns per pole on existing dipole circuit, & 12 turns 200A trim coil to adjust field. Advantage taken of smaller conductor for trim winding to mount inside the primary conductor. Probably requires separate manifolds Early designs had winding on back leg. This has been abandoned to improve structural rigidity of magnet.

Quadrupole Quadrupole parameters Gradient70 Tm -1 Bore diameter30 mm Effective length0.250 m Max length0.322 m Gap between coils for extracted beam pipe 17 mm Model fieldsParts in 10^4 integrated field quadrupole70 Tm -1 Octupole-4 20 Pole2 All others<1

Quadrupole: Practical comments Made from solid steel not laminations Will be finished by wire erosion of fully assembled yoke. Needs to be dismantled to fit coils. Pole flats to give measureable gaps Space constraints for coil significant issue, both at ends of magnet and clearance for photon beam pipe. Power in magnet, the quadupole circuit becomes the defining cooling circuit on each girder The poles are highly saturated

Sextupole Sextupole parameters Effective length0.175 m Physical length0.232 m Bore radius15 mm Strength2000 Tm -2 Integrated Corrector strength Horizontal8 mTm Vertical8 mTm Skew quad0.1 T Integrated harmonics parts in 10^4 Octupole

Sextupole: Practical comments Corrector windings included Horizontal, Vertical and Skew quadrupole. Laminated magnet: Fast Feedback Laminated poles to be oversized when assembled Final profiles achieved by wire erosion on fully assembled yoke Profiles give parallel surface to check assembly This magnet has reduced strength compared to sextupole required for full ring upgrade. Coils intended to use existing power supply modules. But small primary coils have lower than ideal resistance. We have chosen to maintain the conductor cross section as these windings also provide the cooling for the correctors Space to clear extracted photon pipe not so tight as in quadrupole, but the yoke is also limited on the outside, currently checking rigidity.

Mounting Still on girders. 2 Dipoles on each girder drives change from existing arrangement. Accuracy Range ±1mm for multipoles, horizontal and vertical Ability to remove magnets once vessel is in place. Dipole adjustment, given greater range of transverse adjustment to allow correct setting of both field and gradient. Separate motion system to remove.

Measurement program. Multipoles:- ESRF-Stretched wire (alignment and higher multipoles) On 10 mm radius. 0 – full current 10 steps. Offsets, rolls and Harmonics Measurements required in spec … Dipoles Hall probe field scan (1mm intervals and interpolate) 2mm transverse lines on 0, ±2mm, ±4mm Vertically. On axis over range from 0.8 to 1.1 times operating point.

Alignment and final setup Initial alignment of multipoles, using measurements at works. Then check with same stretched wire system but mounted on final girder all multipoles present, adjust as required. Compensating masses for missing dipoles. Initial alignment of dipoles based on at works measurements, but radial adjustment to set correct field when gradient correct, using Beam based measurements during commissioning.

Conclusions Magnets on order at Danfysik, Final design review in October. There are still some mechanical design issues to be resolved, space is very tight. Schedule for delivery, of magnets, ahead of that required for install in Measurement and alignment program being developed. Cabling works to enable optimised shutdown already in progress.