Infrastructure EHN1 extension Lau Gatignon, 7 March 2016
News Lau Gatignon, WA105 meeting2 Handover date civil engineering shifted to 16 September. A two-week period in July offered as compensation. Not obvious how to profit from this in view of legal and safety related constraints. Working on new planning and looking into the legal and safety aspects Impact on crane, protectionb of pits, access, …. MNP22 magnet can be removed when needed. Discussions under way on where to put it. Cryo has promised presentation for next week Specification of racks urgently needed. Chilled water cooling would be a major issue Cooling capacity issue for beam line magnets solved
Lau Gatignon, WA105 meeting3
Civil engineering status Lau Gatignon, WA105 meeting4
Lau Gatignon, WA105 meeting5