1 NCSX VV Assembly Joint Issue B. Nelson 17 Mar 2005.

Slides:



Advertisements
Similar presentations
Fabricating Techniques and Practices
Advertisements

3 rd Harmonic He Vessel Welding Helium Vessel-to-Cavity No June 2008.
ATLAS Pixel Detector February 2003 N. Hartman LBNL 1 Pixel Support Tube PRR: Assembly, Production, Schedule February 2003.
Vacuum Vessel Production Readiness Review
1 MC Assembly via Test Cell Crane FPA Stage 3 Peer Review August 12, 2005 T. Brown.
Status of the LARP Phase II Secondary Collimator Prototype 30 September 2013 LHC Collimation WG Meeting Tom Markiewicz/SLAC BNL - FNAL- LBNL - SLAC US.
NCSX Vacuum Vessel Overview Paul Goranson WBS 12 Manager Vacuum Vessel Manufacturing Study Kickoff meeting April 29, 2003.
Integration of Cavities and Coupling Coil Modules Steve Virostek Lawrence Berkeley National Laboratory MICE Collaboration Meeting March 28 – April 1, 2004.
Update of the ARIES-CS Power Core Configuration and Maintenance Presented by X.R. Wang Contributors: S. Malang, A.R. Raffray and the ARIES Team ARIES.
MICE Collaboration Meeting March 29 - April 1, CERN MICE alignment, tolerances and supports Tuesday March 30 Room Edgar Black/IIT March17-
Joint fit up and alignment
Status of the LARP Phase II Secondary Collimator Prototype 14 October 2013 LHC Collimation WG Meeting Tom Markiewicz/SLAC BNL - FNAL- LBNL - SLAC US LHC.
Jigs and Fixtures.
ILC Main Linac Superconducting Cryogen Free Splittable Quadrupole Progress Report V. Kashikhin for Superconducting Magnet Team.
Muons, Inc. AAC Feb. 4, 2009 V. Kashikhin 1 Fermilab AAC  V. Kashikhin for Superconducting Magnet Team Superconducting Helical Solenoids.
1 Stage 3 Peer Review October 26, 2006 T. Brown. 2 Field Period Assembly (FPA) 1.Make sure the requirements for the tooling is well defined (including.
NCSX Vacuum Vessel Joint Design Mike Viola PPPL July 1 st, 2003.
1 Dimensional Control for the National Compact Stellarator Experiment R. Ellis, A. Brooks, T. Brown, W. Reiersen, S. Raftopoulos, B. Stratton Presented.
1 NCSX Modular coil winding pack To shim or not to shim? NCSX WBS 1 Engineering Meeting July 7, 2004 What is requirement? What is baseline winding pack.
Trip Report from CERN and Wendelstein W7-X October 6 – 13, 2007 Michael Viola; Steve Raftopoulos; Bill Sands October 6-10 CERN Geneva, Switzerland October.
1 WBS 1 Design Analysis Status NCSX Analysis Meeting Dec 3, 2003.
Defining the Vacuum Vessel Geometry NCSX Project Meeting November 27, 2002 Art Brooks.
NCSX A. Brooks, P. Fogarty, G. Lovett, D. Williamson June 3, 2005 Modular Coil Type-C Final Design Review – Part II.
10/31/2007Mike Viola1 NCSX Field Period Assembly + + = October 31, 2007 Mike Viola Field Period Assembly Manager.
NCSX VACUUM VESSEL PL Goranson Thermal Insulation Final Design Review July 31, 2006 WBS12 NCSX.
Conceptual design of JPARC Horn 2 assembly L. Bartoszek Bartoszek Engineering/CU 5/5/04.
10/31/2007Mike Viola1 NCSX Field Period Assembly + + = October 31, 2007 Mike Viola Field Period Assembly Manager.
1Page # Machine Assembly WBS 700 By: James H. Chrzanowski January 24, 2001.
NCSX VACUUM VESSEL HEATING/COOLING PL Goranson Preliminary Results February 17, 2006 MDL Testing of Coolant Tracing NCSX.
11/2/2005Mike Viola1 November Lehman Review November 2, 2005 NCSX VVSA NCSX Vacuum Vessel Fabrication Major Tool and Machine – S F 3 120° segments.
ARIES-CS Power Core Configuration Presented by X.R. Wang Contributors: Laila A. Ei-Guebaly, S. Malang, T.K. Mau, Richard Peiperty, A.R. Raffray and L.
NCSX B. Nelson for the NCSX Engineering Team NCSX modular coil cooling workshop June 10-11, 2004 PPPL NCSX Modular Coil Cooling Requirements and Initial.
1 Field Period Assembly Office of Science Project Review Princeton Plasma Physics Laboratory Princeton, NJ November 2, 2005 T. Brown Princeton Plasma Physics.
NCSX NCSX Vacuum Vessel R&D, Risk Management and Manufacture NCSX Preliminary Design Review October 7-9, 2003 Princeton, NJ Mike Viola, Phil Heitzenroeder,
10/31/2007Mike Viola1 NCSX Field Period Assembly + + = October 31, 2007 Mike Viola Field Period Assembly Manager.
SC Project Review of NCSX, April 8-10, 2008 NCSX Field Period Assembly Mike Viola NCSX Field Period Assembly Manager NCSX Project Review April 8-10, 2008.
SC Project Review of NCSX, April 8-10, 2008 NCSX Machine Assembly E. D. Perry.
LMQXFA Cold Mass Assembly Antonios Vouris Fermilab February 3, 2016.
NCSX November 18-20, 2003NCSX Performance Baseline ReviewMichael Viola 1 NCSX Vacuum Vessel R&D, Risk Management and Manufacture Mike Viola, Phil Heitzenroeder,
MICE Prototype Coupling Coil Fabrication Update Allan DeMello Lawrence Berkeley National Laboratory MICE CM38 - Napa California February 25, 2014 February.
1 Stellarator Core Metrology issues NCSX WBS-1 Meeting April 2, 2003 What are we measuring? When? How do we take the measurements? How do we correlate.
1 Assembly Tooling PU Workshop on NCSX Cost & Schedule Princeton Plasma Physics Laboratory Princeton, NJ Mar 1-4, 2007 T. Brown Princeton Plasma Physics.
NEDM Collaboration Meeting, May 19, 2008 Valve Progress Steve Williamson.
LARP Collaboration Meeting Racetrack Coil Fabrication
NCSX VACUUM VESSEL PL Goranson Final Design Review November 17, 2005 Man Access Port /Lateral Supports NCSX.
Field Period Assembly Wayne Reiersen SC Project Review PPPL May 2006.
The Design: Totally bolted, electrically isolated 6 top and 6 bottom inboard flange holes, with tapped holes in one flange and a thru holes in mating flange.
MICE RFCC Module Update Allan DeMello Lawrence Berkeley National Lab MICE CM25 at RAL, UK November 6, 2009.
NCSX 21 March 2003 Reiersen - 1 PDR Preparations Wayne Reiersen NCSX Engineering Meeting 21 March 2003.
1 Modular Coil Assembly Fixture (MCAF) Information Meeting February 23, 2005.
9/28/20051 Mike Viola 1, T. Brown 1, P. Heitzenroeder 1, F. Malinowski 1, W. Reiersen 1, L. Sutton 1, P. Goranson 2, B. Nelson 2, M. Cole 2, M. Manuel.
10/31/2007Mike Viola1 NCSX Field Period Assembly + + = October 31, 2007 Mike Viola Field Period Assembly Manager.
Preparations for working on Station 1 November 22, 2005.
SEPT 20, 2006 T. Brown, M. Cole, P. Fogarty, P. Goranson, K. Freudenberg, D. Williamson NCSX STAGE 2 COIL TO COIL ASSY.
8/15/2007Mike Viola1 NCSX Field Period Assembly + + = August 15, 2007 Mike Viola Field Period Assembly Manager.
12/19/2006Mike Viola1 December Lehman Review December 19, 2006 Mike Viola Field Period Assembly Manager NCSX Field Period Assembly + + =
Stellarator Core Machine Configuration NCSX Project Meeting Dec 19-20, 2000 B. Nelson, M. Cole, P. Fogarty P. Goranson, G. Jones, D. Williamson O AK R.
1 WBS 1 Preparation for FDRs NCSX WBS 1 Engineering Meeting March 17, 2003 What establishes the plan? What are near term deliverables? How will we status.
EMC BWE Proto18 - Orsay Meeting 1 PANDA EMC BWE Proto18 Mikel Catania Goikoetxea, Javier Navarro Medrano, David Rodríguez Piñeiro, Yue Ma, Frank.
Cold Mass and Assembly Tooling Design, Procurement Status and Assembly Plan Igor Novitski Fermilab 15 T Dipole Design Review April 2016 April 28-29,
1 VV Support Fixture FPA Stage 1 PDR Review August 10, 2005 T. Brown.
1 NCSX radial build NCSX Project Meeting December 18, Modular coil build assumptions 2.Vessel build assumptions 3.FW/internal build assumptions.
Cryomodule Interconnect Installation Issues A Comparison of XFEL to LCLSII Karen Fant 7/29/2015.
NCSX Major Procurement Status July 20, Steady Progress on C1 and C2 The C1 was transferred to the 5 axis machine last Saturday; finish machining.
NCSX Vacuum Vessel Fabrication
Superconducting Helical Solenoids
Design of Distribution Feedbox at LHC P7
On the accuracy of port assembly at Wendelstein 7-X
SNS PPU Cryomodule Vacuum Vessel
SNS PPU Cryomodule Space Frame
Presentation transcript:

1 NCSX VV Assembly Joint Issue B. Nelson 17 Mar 2005

2 Presentation Outline Purpose of spacer and baseline design overview Alternate design Design comparison Discussion Recommendation

3 Purpose of spacer End flanges of field periods may distort due to port extension welding Spacer provided for fit-up of field periods at final assembly Assembly welds Spacer Spacer between field periods

4 Baseline spacer design Barn door (open) Facility interior Assembly welds Spacer Vessel Oversized spacer flanges are machined to match vessel profile for final assembly Weld Prep VACUUM SIDE Backing Gas VACUUM SIDE Clamp Mount holes Spacer Flex Seal with glass rope gasket* * Seal is welded to spacer. Each spacer has two, continuous, poloidal welds, as well as flex seal for backing gas and leak checking

5 Baseline spacer design requires precise measurement and machining End flanges of vessel field periods are measured after field periods are assembled, port extensions welded, and vessel locked in place relative to mod coils “Virtual” fitup is accomplished by knowing relationship between vessel flanges and mod coil positions. Mod coils dictate assembled position TF Coil Vacuum Vessel Modular Coil Coil Support Structure Vessel Port Extensions Vessel Support

6 Baseline spacer design requires special assembly motion At assembly, spacer must be rotated about radial axis and moved in radially to clear mod coil wings Simulation (courtesy of Tom Brown) predicts 1.5 inches of clearance

7 We are buying three VVSA kits from Major Tool consistent with the baseline spacer design Spacer Field Period Assembly Port extensions End Cap for leak check

8 Issues with baseline design Lack of confidence in ability to measure vessel field periods accurately enough to machine the spacer to fit within 1/8 inch J-groove weld is harder to weld than double bevel weld, welders prefer double bevel Major Tool thinks alternate design is cheaper for them to supply Special spacer assembly / manipulation fixture could be expensive Etc.

9 Alternate Design Spacer is fabricated as 5 or more splice plates, supplied by Major Tool At final assembly, splice plates are trimmed and fit into position from inside the vessel Welds are made with v-groove prep and backing rings / backing plates Cover gas is all supplied from front side Splice plates 6 inches 3/8 in max mismatch Splice plate VV period shell weld Backing ring / plate

10 Design Comparison 1800 hours, MTM est. Baseline DesignAlternate design Feature/requirementDescription cost impact critical path schedule impact Description cost impact critical path schedule impact 1Spacer configurationcomplete spool with machined flanges baseline 5 or more formed pieces -$250k 2field period assembly end configuration machined flanges weld backing ring around od incl in 1. 3measurement / modelinglaser scan of vessel & flanges $38k no- prior to asm. Same as baseline $38k0 4intermediate leak checkingblankoff flanges seal welded to gas seal rings same individual seals for each port or weld blankoff flanges to backing ring same 5spacer fitup and accommodation of misalignment spacer flanges machined, based on field period measurements $30k prior to assy, 4-6 wks. (MTM est.) individual pieces measured and trimmed and/or re- formed to fit, assume 10 pcs. $41k total of 30 plates; 1 day/plate 2 man crew 6weld prepmachined into spacer flanges (j-groove), part of 4 above edges ground to provide v- groove bevel $10k 7welding6 poloidal locations $20k 30 pcs. 16" perimeter each CONCERN: SHRINKAGE OF POL. WELDS. $20k assumed the same 8positioning at assembly3 special assembly fixtures synchronized with field period radial motion, $60k TB guessfitting & tacking pieces by hand $10k 3 wks could be reduced by teams

11 Design Comparison (2) Baseline DesignAlternate design Feature/requirementDescription cost impact critical path schedule impact Description cost impac t critical path schedule impact 9gas seal for weldingflex seal behind weld joint $1k stuff ceramic rope into flange gap at asm backing ring welded to field period assembly for poloidal welds $12kprior to asm cross backing bars for toroidal welds (?) $30k 30 10helium leak checkingsame as gas seal $4k after welding same as gas seal $0k no leak checking 11thermal insulationinsulation pre-applied to spacer $0k 0insulation pre-positioned prior to fitup of pieces $10k Pull draw string to position insul. 12coil protection during welding gas seals and thermal insulation (microtherm) same weld backing rings and thermal insulation (microtherm) same 13integration of radial portpart of spacer port of outboard spacer segment 14Drawing modificationsNone required0 Need to delete flanges, show segmentation, verify pieces can be inserted,etc. $50k2 mm ? 15Add rigidizing fixtures for alignment of VV (note: 4" from turrett to flange weld) same $18k same $18k

12 Design Comparison – Summary BaselineAlternate Technical Can’t measure Mod coils require 10 times VV accuracy Worst case requires trial fit-up Poloidal weld shrinkage not quantified? R&D could quantify J-groove not preferred weld joint Weld tests say either joint will work Vessel moves during fit-up operations Splice plates must be pre-formed to fit, not forced to fit in place Screw up the spacer machining? Must fix with weld repair Re-forming plates to fit requires on-site press and expertise or off-site forming R&D could quantify Schedule Potentially less time needed during final assembly More time needed for custom fit-up during final assembly (+4 weeks?) Cost Current baseline budget: $75k Estimated cost per chart: $171k Delta: add $96k Current baseline budget: $75k Est. cost with MTM rebate: $-18k Delta: save $93k Current baseline budget: $75k Est. cost w/o MTM rebate: $239k Delta: add $164k

13 Design Comparison – Recommendation Baseline design is feasible even if alternate has certain advantages Measurement issue must be solved for mod coil assembly Alternate will require design changes, may require additional R&D We do not want to slow down nor distract MTM Cost rebate from MTM for alternate design may not be realized Better is the enemy of good enough at this stage of project Therefore: Keep the baseline design

14 Major Tool estimates 1800 hours for splice plate fitup and welding 600 hours for each VVSA joint – 1800 hours to do all three “spacers”: 7-8 weeks Start with the panel that has the port hole. Work the way around, tacking in each panel. Then have three welders in – one at each joint simultaneously

15 Major Tool estimates $40-50k for splice plate R&D mockup From MTM to Mike Viola: 40-50K for a test spool piece same as before except without the flanges. He could have the material next week to provide. 34.5”-36” diameter ~24” wide will give enough material for 1 – 6” spool piece, 2 – 12” 8” end pieces, 2 – 1” backing strips