Research on Single-phase Ground Fault Locating for Non-effectively Grounded System in Shanghai Weibin Wang Shanghai Municipal Electric Power Company, China Weibin Wang – China – Session 3 – 0084
Frankfurt (Germany), 6-9 June 2011 Contents Weibin Wang – China – Session 3 – 0084 Introduction 1 Traditional Ways to Find the Fault Spot 2 Fault Locating System 3 4 Conclusions 5 Actual Application
Frankfurt (Germany), 6-9 June 2011 Several neutral point grounding modes for 10kV grids in Shanghai Low resistance (urban & Pudong districts) Arc suppression coil (west district) Ungrounded system (some small area) Fault locating system is used in the west district Weibin Wang – China – Session 3 – 0084 Introduction
Frankfurt (Germany), 6-9 June 2011 Recently, parallel resistance has been added nearby the arc suppression coil to increase the selection accuracy of ground fault feeder Weibin Wang – China – Session 3 – 0084 Introduction
Frankfurt (Germany), 6-9 June 2011 Manual search method - time-consuming, laborious Fault feeder selector - can’t locate the fault spot Old fault indicator - can only locate the short-circuit faults, it can’t locate the ground faults Weibin Wang – China – Session 3 – 0084 Traditional Ways to Find the Fault Spot
Frankfurt (Germany), 6-9 June 2011 Traditional ways to find the fault spot What is the key? - single-phase ground faults are the most frequent type of faults - traditional ways are not valid for locating single-phase ground faults - people’s requirement is rising, the demand of reliability is also rising So, it is necessary to find a valid way to locate the ground fault quickly Weibin Wang – China – Session 3 – 0084
Frankfurt (Germany), 6-9 June 2011 Fault Locating System Principle : signal injection method - first select the fault feeder - inform the master station - the parallel resistance will be put in and ablate it for 6 times - a characteristic current will be produced - indicators before the fault spot will detect the characteristic current, the indicators after the fault spot will not. - send data to the master station - the fault spot can be determined
Frankfurt (Germany), 6-9 June 2011 Action series: the duration time is 100ms, the interval time is 10s Judgment : fault indicators capture the characteristics current ≥ 5 times Factors: - In order to distinguish the characteristic current from the grid disturbance, put in and ablate the parallel resistance for several times - Considering the cooling of parallel resistance, the interval time should be enough Weibin Wang – China – Session 3 – 0084 Fault Locating System put in the parallel resistance ablate the parallel resistance t Ia 100ms 10s
Frankfurt (Germany), 6-9 June 2011 size :120*190*50mm Installation - they are always installed evenly on trunk lines, and on each branch joints - hang it on the line, then rotate it 90 degree clockwise to close - rotate it counterclockwise to release, then take it down Weibin Wang – China – Session 3 – 0084 Fault indicators
Frankfurt (Germany), 6-9 June 2011 Functions - communication with the arc suppression coil controller - analyze and locate the fault spot, and flash it in GIS - management of fault indicators - display fault current wave - history data storage Weibin Wang – China – Session 3 – 0084 Master station
Frankfurt (Germany), 6-9 June 2011 GPRS: operation cost is high (so many indicators), RF technology: cheaper indicators—repeater—transfer one by one--master station 433Hz, it is free self-checking periodically Weibin Wang – China – Session 3 – 0084 Communication
Frankfurt (Germany), 6-9 June 2011 Actual Application The system was tested strictly for many times in the lab Applied to two 10 kV over-head lines - 54 fault indicators, 20 wireless repeaters - installation was ended in January Result - so far, so good - part of the performance has been optimized Weibin Wang – China – Session 3 – 0084
Frankfurt (Germany), 6-9 June 2011 The fault locating system can locate single- phase ground faults, short-circuit faults, disconnection, etc It takes full use of the existing parallel resistance, thus reduces the investment A communication interface should be set up between the arc suppression coil controller and the master station of fault locating In the future, we will still improve its performance, and use more widely in 10kV grids Weibin Wang – China – Session 3 – 0084 Conclusions
Frankfurt (Germany), 6-9 June 2011 Thank You! Weibin Wang – China – Session 3 – 0084