PRELIMINARY VERSION Mechanical integration in the ESS Accelerator tunnel HENRY PRZYBILSKI.

Slides:



Advertisements
Similar presentations
Safety Absolutes Green Lake
Advertisements

F&T Inc. OVERHEAD CRANE SAFETY.
Chapter 6 Cranes Crane Operation • Industrial Cranes • Mobile Cranes • Crane Inspections.
Optical Manufacturing Solutions 1 Probe Assembly.
SPL Intercavity support Conceptual design review 04/11/ A. Vande Craen TE/MSC-CMI.
CMS ZDC Crane Emergency Payload Removal Procedures This document proposes the viability of using a portable hydraulic actuator Hand crane (Davit crane)
MODULE TRANSPORT CLIC Module Working Group 27 September 2010 Keith Kershaw CERN EN-HE.
EditablePowerPoint Slides for Lecturers By Phil Hughes MBE and Ed Ferrett By Phil Hughes MBE and Ed Ferrett.
FHM TRAINING TOOLS This training presentation is part of FHM’s commitment to creating and keeping safe workplaces. Be sure to check out all the training.
Copyright  Business & Legal Reports, Inc.
Copyright  Business & Legal Reports, Inc. BLR’s Safety Training Presentations Cranes and Slings 29 CFR and 184.
MICE Collaboration Meeting at Frascati, Jun 26~29, 2005 Iron Shield Mounting Design Stephanie Yang.
EA meeting, Wednesday 6 Dec 2006 TT installation, Jeroen van Tilburg 1 TT installation Installation of the TT station.
Outcome 5 Safety requirements for using access equipment Unit 201: Health and safety in building services engineering.
1 Cryostat assembly, integration and commissioning procedures M.Olcese Version: 07 May 2008.
Alain FRANCE for the ESS RFQ Team at CEA Saclay
ZDC/Dummy Absorber Exchange Crane Proposal Paul Debbins Ianos Schmidt Univ. of Iowa - Nov. 5, 2007.
Status of vacuum & interconnections of the CLIC main linac modules C. Garion TE/VSC TBMWG, 9 th November 2009.
This presentation is for illustrative and general educational purposes only and is not intended to substitute for the official MSHA Investigation Report.
Assembly Scenarios Draft 1 MODEL simulation based on CXUO-CRY-AP-001.
Lifting Operations & Lifting Equipment. LOLER 98  Lifting Equipment must be of adequate strength & stability, as must the load itself  Lifting equipment.
LATLAT Beam Test Workshop 20th March GLAST Program Beam Test Workshop CU Outer Shipping Container Michele Pinchera
2.5.5 Student Book © 2004 Propane Education & Research CouncilPage Coordinating Loading and Unloading of ASME Tanks Using Contractor- Operated.
Cranes and Slings 29 CFR and 184
CMS ZDC Remote Handling Status LTEX Meeting - Sept. 13, 2012 The Crane Testing and Development has moved from SX5 to ISR: Crane #2 has been fully assembled,
Framed Canopy Fitting Instructions Contents – 6- Angled frame fixing brackets 1 x handle pack 6 x self drilling tech screws 3 keys 1x door 6 x coach screws.
Transport and handling at CERN for FAIR
ZDC Remote Handling Tool Structure and Force Analysis P. Debbins University of Iowa December 10, 2009.
Manufacturing process, validation and factory test
RICH1 Gas Enclosure Installation. Experimental Area Meeting at CERN on 21st June 2006 Bill Cameron (Imperial College London) on behalf of the RICH1 team.
Transport & Handling of Detectors TAN Workshop S. Prodon –
Sling Safety (Level 1 Rigger). Objectives Be familiar with regulations regarding slings. Be familiar with regulations regarding slings. Understand safe.
Additional muon stations for the Upgrade of the Elevator Regions in the ATLAS Muon Spectrometer. Installation scenario, status on the installation tools.
ICARUS Collaboration Meeting Dec A. Scaramelli.
Baby Mind C OIL DESIGN AND ASSEMBLY SCENARIOS Helder Silva Phillipe Benoit Alexey Dudarev Gabriela Rolando Herman ten Kate Etam Messomo Laurent Nicola.
Procedure for erection and use of mobile tower scaffolds (Revision 1 – 5 th April 2011) Toolbox talk.
CDR2 – Coupler Mechanical Design NICOLAS MISIARA.
SPS movable table Joanna Swieszek, Kurt Artoos (EN-MME) 14/04/2016.
Accelerator Tunnel Layout (G01) Nick Gazis Senior Mechanical Engineer Review of ESS Accelerator Conventional Facility Design.
How selected hoist overload limiter. How should hoist overload limiter Selection Electric hoist is a motor, reducer and rope reel (or chain) as one of.
ESS RFQ INTERFACES | Didier CHIRPAZ-CERBAT CEA-ESS INTERFACES.
PXIE RFQ Engineering Design Steve Virostek Engineering Division Lawrence Berkeley National Laboratory April 10, 2012 Project X Collaboration
SAFE DIE HANDLING FOR STAMPING PRODUCTION OPERATIONS UAW-GM SAFE DIE HANDLING FOR STAMPING PRODUCTION OPERATIONS Copyright © UAW-GM Health & Safety.
Introduction to the Accelerator layout February 2016 Nick Gazis Mechanical Integration Lead Engineer.
SuperB Experimental hall General considerations on the Babar experimental area Preliminary space requirements hall proposal. A floor plan. Specification.
Adjustable tuner HENRY PRZYBILSKI / PIERRE-ALAIN LEROY.
MANUFACTURING ENGINEERING DEPARTMENT
K.Long/G.Barber Mice Tracker Mechanical Status CM20 Feb 08 1 Mice Tracker Mechanical Status Contents:- Tracker 1 Status Tracker 2 Status Further Hardware.
All kinds of cranes have the advantage. Longfellow Bridge: “Salt and Pepper” Towers Work More than 100 years after the last stone was set on the “salt.
Kitakami Side AHCAL Assembly or anywhere in any detector.
TPC Support Installation 26 Apr 2016Dan Wenman Mechanical Engineer1 Overview Installation of the support rails Details of the rail from the SAS to the.
What are the criteria to select crane. Hoist Selection After matching the crane manufacturer to your application, the next step is to choose a compatible.
Insulating Glass Manufacturing Quality Procedure Manual TM (07)
Crane, Conveyor, and Rigging Part I - Crane OSHE 112, Spring 2016
Bruno POTTIN, Anne-Catherine CHAUVEAU
Visit us online at Crane Truck Sydney Services By DELTA TRANSPORT.
CLIC Handling Engineering Update
ProtoDUNE – DSS Installation, Alignment and QA
SBN Far Detector Installation & Integration
IT-4189 Supply and installation of a cryogenic distribution system
SX1 manipulation VERSION 1 Version
NA62 LAV Anti1 REMOVAL & TESTS
Status of straw production straw module assembling
INSTALLATION SEQUENCE
F&T Inc. OVERHEAD CRANE SAFETY.
Licensing update ESHAC #9, October 2018
Undulator Tuning Status Heinz-Dieter Nuhn, SLAC / LCLS for Zack Wolf, Yurii Levashov, Achim Weidemann, Seva Kaplounenko, Scott Jansson, Ralph Colon, Dave.
ESS-RFQ Assembly procedure Augustin DUBOIS.
Work Unit AIK 11.2 CDR of the CDS-SL Mechanics
MRV system budget and scheduling Short overview installation
Presentation transcript:

PRELIMINARY VERSION Mechanical integration in the ESS Accelerator tunnel HENRY PRZYBILSKI

PRELIMINARY VERSION SUMMARY 1.ESS Accelerator building 2.CEA – Equipment 1. RFQ 2. RFQ’s section 3. RFQ transport chassis 3.CEA – Tooling 4.Scenario 1. Section transport chassis assembly 2. Section assembly on the RFQ’s support 3. Accelerator building integration | PAGE 2 1-Dec-15 CDR2 - Mechanical integration - H. PRZYBILSKI

PRELIMINARY VERSION REQUIREMENTS ESS Accelerator building Release 13 (ESS ) – 2015/11/20 Inputs: Ground maximum loads (1500 Kg/m² ; 10tn–25*25cm²) Dimensions tunnel (maximum height = 3.5m) Tooling: EU norms + Swedish norms | PAGE 3 1-Dec-15 CDR2 - Mechanical integration - H. PRZYBILSKI

PRELIMINARY VERSION ESS ACCELERATOR BUILDING | PAGE 4 1-Dec-15 CDR2 - Mechanical integration - H. PRZYBILSKI Front-End Building drop hatch Dimensions (10m x 3.5m) Lvl.100 Lvl tn overhead crane (ESS equipment)

PRELIMINARY VERSION | PAGE 5 1-Dec-15 CDR2 - Mechanical integration - H. PRZYBILSKI CEA – EQUIPMENT RFQ

PRELIMINARY VERSION | PAGE 6 1-Dec-15 CDR2 - Mechanical integration - H. PRZYBILSKI CEA – EQUIPMENT SECTION TRANSPORT CHASSIS RFQ’s section transport chassis.

PRELIMINARY VERSION | PAGE 7 1-Dec-15 CDR2 - Mechanical integration - H. PRZYBILSKI CEA – TOOLING GANTRY-CRANE Specifications: Maximum load 1600 kg *Dimensions [4m,<3.2m] are under design 4m* < 3.2m*

PRELIMINARY VERSION | PAGE 8 1-Dec-15 CDR2 - Mechanical integration - H. PRZYBILSKI SCENARIO SECTION INSTALLATION PROCESS Installation procedure after brazing. Step 000 Manufacturer

PRELIMINARY VERSION | PAGE 9 1-Dec-15 CDR2 - Mechanical integration - H. PRZYBILSKI SCENARIO SECTION INSTALLATION PROCESS The section is equipped with a reinforcement structure. This will allow lifting the section without any damage and protect it during the transport period. Step 010 Manufacturer

PRELIMINARY VERSION | PAGE 10 1-Dec-15 CDR2 - Mechanical integration - H. PRZYBILSKI SCENARIO SECTION INSTALLATION PROCESS The reinforcement structure is secured by pins and screws. Step 020 Manufacturer

PRELIMINARY VERSION | PAGE 11 1-Dec-15 CDR2 - Mechanical integration - H. PRZYBILSKI SCENARIO SECTION INSTALLATION PROCESS The RFQ’s section is ready to be lifted on the transport chassis. Step 030 Manufacturer

PRELIMINARY VERSION | PAGE 12 1-Dec-15 CDR2 - Mechanical integration - H. PRZYBILSKI SCENARIO SECTION INSTALLATION PROCESS The section is lifted from the ground vertically. Step 040 Manufacturer

PRELIMINARY VERSION | PAGE 13 1-Dec-15 CDR2 - Mechanical integration - H. PRZYBILSKI SCENARIO SECTION INSTALLATION PROCESS The section is moved above the transport chassis. Step 050 Manufacturer

PRELIMINARY VERSION | PAGE 14 1-Dec-15 CDR2 - Mechanical integration - H. PRZYBILSKI SCENARIO SECTION INSTALLATION PROCESS The section is lowered on the transport chassis. To ensure the correct rotation, the semi-shells have to be put in place and fixed. Semi-shell Step 060 Manufacturer

PRELIMINARY VERSION | PAGE 15 1-Dec-15 CDR2 - Mechanical integration - H. PRZYBILSKI SCENARIO SECTION INSTALLATION PROCESS The RFQ’s section is rotating to its final position around the bearings’ axis. This operation is a combined movement, translation of the pallet truck and the cable. Step 070 Manufacturer

PRELIMINARY VERSION | PAGE 16 1-Dec-15 CDR2 - Mechanical integration - H. PRZYBILSKI SCENARIO SECTION INSTALLATION PROCESS The RFQ’s section is placed next to the top part. Step 080 Manufacturer

PRELIMINARY VERSION | PAGE 17 1-Dec-15 CDR2 - Mechanical integration - H. PRZYBILSKI SCENARIO SECTION INSTALLATION PROCESS When the section is fully fixed, the top part can be approached to the RFQ’s section. Step 090 Manufacturer

PRELIMINARY VERSION | PAGE 18 1-Dec-15 CDR2 - Mechanical integration - H. PRZYBILSKI SCENARIO SECTION INSTALLATION PROCESS The top part is lifted. Step 100 Manufacturer

PRELIMINARY VERSION | PAGE 19 1-Dec-15 CDR2 - Mechanical integration - H. PRZYBILSKI SCENARIO SECTION INSTALLATION PROCESS The top part is lifted and placed above the section. Step 110 Manufacturer

PRELIMINARY VERSION | PAGE 20 1-Dec-15 CDR2 - Mechanical integration - H. PRZYBILSKI SCENARIO SECTION INSTALLATION PROCESS The top part is lowered and fixed to the transport chassis. Step 120 Manufacturer

PRELIMINARY VERSION | PAGE 21 1-Dec-15 CDR2 - Mechanical integration - H. PRZYBILSKI SCENARIO SECTION INSTALLATION PROCESS A nitrogen saturated atmosphere is introduced inside to preserve the integrity of the section. The top part is also a protection during the transportation. Step 130 Manufacturer

PRELIMINARY VERSION | PAGE 22 1-Dec-15 CDR2 - Mechanical integration - H. PRZYBILSKI SCENARIO RFQ INSTALLATION PROCESS Note: the procedure of the RFQ’s section assembly is still under development, considering interactions between ESS and the CEA about the integration in the tunnel ; the RFQ chassis is not entirely designed. Step 000 CEA / ESS 1m On both sides, to perform the RF tuning

PRELIMINARY VERSION | PAGE 23 1-Dec-15 CDR2 - Mechanical integration - H. PRZYBILSKI SCENARIO RFQ INSTALLATION PROCESS Every section is secured in its section’s transport chassis. *off CDR scope RFQ chassis* Mobile gantry-crane ≈5m Pallet truck Section’s transport chassis (x5) Section support* Section assembly support* Step 000 CEA / ESS

PRELIMINARY VERSION | PAGE 24 1-Dec-15 CDR2 - Mechanical integration - H. PRZYBILSKI SCENARIO RFQ INSTALLATION PROCESS The section is placed under the gantry-crane with the pallet truck. Step 010 CEA / ESS

PRELIMINARY VERSION | PAGE 25 1-Dec-15 CDR2 - Mechanical integration - H. PRZYBILSKI SCENARIO RFQ INSTALLATION PROCESS The top part is raised for the transport chassis with the gantry- crane. Step 020 CEA / ESS

PRELIMINARY VERSION | PAGE 26 1-Dec-15 CDR2 - Mechanical integration - H. PRZYBILSKI SCENARIO RFQ INSTALLATION PROCESS For a safer access to the top part, the pallet truck and the section are removed from that area. Step 030 CEA / ESS

PRELIMINARY VERSION | PAGE 27 1-Dec-15 CDR2 - Mechanical integration - H. PRZYBILSKI SCENARIO RFQ INSTALLATION PROCESS The top part is lowered to be removed. Step 040 CEA / ESS

PRELIMINARY VERSION | PAGE 28 1-Dec-15 CDR2 - Mechanical integration - H. PRZYBILSKI SCENARIO RFQ INSTALLATION PROCESS The place is now free to set the section under the gantry- crane. Step 050 CEA / ESS

PRELIMINARY VERSION | PAGE 29 1-Dec-15 CDR2 - Mechanical integration - H. PRZYBILSKI SCENARIO RFQ INSTALLATION PROCESS The hook is fixed to the section reinforcement structure. Step 060 CEA / ESS

PRELIMINARY VERSION | PAGE 30 1-Dec-15 CDR2 - Mechanical integration - H. PRZYBILSKI SCENARIO RFQ INSTALLATION PROCESS The semi-shells have be removed to allow the section to move up. Step 070 CEA / ESS

PRELIMINARY VERSION | PAGE 31 1-Dec-15 CDR2 - Mechanical integration - H. PRZYBILSKI SCENARIO RFQ INSTALLATION PROCESS The section is raised from the transport chassis. Step 080 CEA / ESS

PRELIMINARY VERSION | PAGE 32 1-Dec-15 CDR2 - Mechanical integration - H. PRZYBILSKI SCENARIO RFQ INSTALLATION PROCESS The section is placed above the RFQ chassis. Step 090 CEA / ESS

PRELIMINARY VERSION | PAGE 33 1-Dec-15 CDR2 - Mechanical integration - H. PRZYBILSKI SCENARIO RFQ INSTALLATION PROCESS The section is lowered on the section assembly support. Step 100 CEA / ESS

PRELIMINARY VERSION | PAGE 34 1-Dec-15 CDR2 - Mechanical integration - H. PRZYBILSKI SCENARIO RFQ INSTALLATION PROCESS The section is put in place on the section assembly support sliding on the RFQ chassis. BEAM Step 110 CEA / ESS

PRELIMINARY VERSION | PAGE 35 1-Dec-15 CDR2 - Mechanical integration - H. PRZYBILSKI SCENARIO RFQ INSTALLATION PROCESS The section is moved to the first section support. Step 120 CEA / ESS BEAM

PRELIMINARY VERSION | PAGE 36 1-Dec-15 CDR2 - Mechanical integration - H. PRZYBILSKI SCENARIO RFQ INSTALLATION PROCESS The section is placed in the first section support. Step 130 CEA / ESS BEAM

PRELIMINARY VERSION | PAGE 37 1-Dec-15 CDR2 - Mechanical integration - H. PRZYBILSKI SCENARIO RFQ INSTALLATION PROCESS The second section can be tied up on the section. Step 140 CEA / ESS BEAM

PRELIMINARY VERSION | PAGE 38 1-Dec-15 CDR2 - Mechanical integration - H. PRZYBILSKI SCENARIO RFQ INSTALLATION PROCESS The second section can be taken with the pallet truck to be installed. Step 150 CEA / ESS BEAM

PRELIMINARY VERSION | PAGE 39 1-Dec-15 CDR2 - Mechanical integration - H. PRZYBILSKI SCENARIO RFQ INSTALLATION PROCESS The second transport chassis is under the gantry-crane. Step 160 CEA / ESS BEAM

PRELIMINARY VERSION | PAGE 40 1-Dec-15 CDR2 - Mechanical integration - H. PRZYBILSKI SCENARIO RFQ INSTALLATION PROCESS The section assembly support is designed to be separated in two parts to be released from the two section supports, and be used to continue the assembly of the RFQ. Step 170 CEA / ESS BEAM

PRELIMINARY VERSION | PAGE 41 1-Dec-15 CDR2 - Mechanical integration - H. PRZYBILSKI SCENARIO RFQ INSTALLATION PROCESS These operations have to be repeated to perform the RFQ assembly. Then, elements like pumps, tuner… can be mounted. Step 180 CEA / ESS

PRELIMINARY VERSION | PAGE 42 1-Dec-15 CDR2 - Mechanical integration - H. PRZYBILSKI SCENARIO ACCELERATOR BUILDING INTEGRATION ESS Accelerator building – Warm Linac Release 13

PRELIMINARY VERSION | PAGE 43 1-Dec-15 CDR2 - Mechanical integration - H. PRZYBILSKI SCENARIO ACCELERATOR BUILDING INTEGRATION As the “climate conditions” (temperature, humidity rate…) in the warehouse above the FEB drop hatch will not be regulated, the CEA equipment needs to be stored in the tunnel, immediately after delivery. FEB drop hatch 20 tn overhead crane (ESS equipment)

PRELIMINARY VERSION General requirements to be discussed: Storage area in the tunnel Regulated conditions: Temperature (25 ±1°C) Cleanliness Air draft | PAGE 44 1-Dec-15 CDR2 - Mechanical integration - H. PRZYBILSKI SCENARIO ACCELERATOR BUILDING INTEGRATION

PRELIMINARY VERSION | PAGE 45 1-Dec-15 CDR2 - Mechanical integration - H. PRZYBILSKI SCENARIO ACCELERATOR BUILDING INTEGRATION 20 tn overhead crane (ESS equipment) RFQ chassis The section transport chassis and the RFQ chassis are on the delivery area (level 100), waiting to be lifted in the tunnel. FEB drop hatch Wire rope hoist Section transport chassis (x5)

PRELIMINARY VERSION | PAGE 46 1-Dec-15 CDR2 - Mechanical integration - H. PRZYBILSKI SCENARIO ACCELERATOR BUILDING INTEGRATION The overhead crane is performing the lifting manoeuvre for the RFQ chassis and the section transport chassis (x5). Slings / hoisting hooks are necessary to lift this equipment. 20 tn overhead crane (ESS equipment) Wire rope hoist RFQ chassis FEB drop hatch

PRELIMINARY VERSION | PAGE 47 1-Dec-15 CDR2 - Mechanical integration - H. PRZYBILSKI SCENARIO ACCELERATOR BUILDING INTEGRATION 20 tn overhead crane (ESS equipment) Wire rope hoist RFQ chassis Section transport chassis (x5) FEB drop hatch

PRELIMINARY VERSION | PAGE 48 1-Dec-15 CDR2 - Mechanical integration - H. PRZYBILSKI SCENARIO ACCELERATOR BUILDING INTEGRATION The RFQ chassis is lifted to the FEB drop hatch. 20 tn overhead crane (ESS equipment) Wire rope hoist RFQ chassis FEB drop hatch

PRELIMINARY VERSION | PAGE 49 1-Dec-15 CDR2 - Mechanical integration - H. PRZYBILSKI SCENARIO ACCELERATOR BUILDING INTEGRATION Once the section transport chassis is lowered to level 090, a pallet truck is handling it to the RFQ assembly area.

PRELIMINARY VERSION | PAGE 50 1-Dec-15 CDR2 - Mechanical integration - H. PRZYBILSKI SCENARIO ACCELERATOR BUILDING INTEGRATION Careful! There is a 50 mm gap between the tunnel area and the FEB drop hatch. 50mm gap

PRELIMINARY VERSION | PAGE 51 1-Dec-15 CDR2 - Mechanical integration - H. PRZYBILSKI SCENARIO ACCELERATOR BUILDING INTEGRATION

PRELIMINARY VERSION | PAGE 52 1-Dec-15 CDR2 - Mechanical integration - H. PRZYBILSKI SCENARIO ACCELERATOR BUILDING INTEGRATION This is the final position of the RFQ in the tunnel. The gantry-crane is removed when the installation process is completed.

PRELIMINARY VERSION Tooling After brazing process Assembly at the CEA / ESS Lund Similar environment Validation of the procedure at Saclay, by the CEA Tunnel integration | PAGE 53 1-Dec-15 CDR2 - Mechanical integration - H. PRZYBILSKI CONCLUSION

PRELIMINARY VERSION ESS ESS CEA-ESS-RFQ-RP-0001 A ESS | PAGE 54 1-Dec-15 CDR2 - Mechanical integration - H. PRZYBILSKI REFERENCES