Eurisol DS, Task 11 meeting, Helsinki September‘07 Task 11.2: Fragmentation of post accelerated ISOL beams David Pérez Loureiro Universidad de Santiago de Compostela, Spain
Eurisol DS, Task 11 meeting, Helsinki September‘07 Production of extremely neutron-rich nucleus Two step scheme; fission + cold fragmentation n,p U 132 Sn + Be X Milestones and expected results: - preparation of an experiment (month 12) - data analysis of the experiment (month 28) delayed (Nov 06) - optimal post-acceleration energy estimation (33 month)
Eurisol DS, Task 11 meeting, Helsinki September‘07 Proposed experiment S2-S4: Sn + Be X A/A ~ Z/Z ~ B / ~ ToF ~ 150 ps L ~ 36 m S0-S2: 238 U(950 A MeV)+Pb Sn Z/Z ~ B / ~ ToF ~ 150 ps L ~ 18 m A/A ~ FRS-GSI
Eurisol DS, Task 11 meeting, Helsinki September‘07 Proposed experiment S0-S2: 238 U(950 A MeV)+Pb Sn Z/Z ~ B / ~ ToF ~ 150 ps L ~ 18 m A/A ~ Experiment proposal was submitted and approved by the GSI PAC (18 shifts 136 Xe-parasitic and 18 shifts 238U ) Beam time expected scheduled July 2006 delayed until November FRS-GSI
Eurisol DS, Task 11 meeting, Helsinki September‘07 Completed work during the first 18 months Detection setup: plastic scintillator at S1 - two fast photo-multipliers Hamamatsu H mod delivered to GSI last December - these photo-multipliers were tested in a beam time last April The experiment proposal was submitted and approved by the GSI PAC (18 shifts 136Xe-parasitic and 18 shifts 238U ) Acquisition system: new readout using the buffer memory of the CAEN converters - the system has been implemented and tested with 2 TDC + 1 ADC - final implementation in the FRS DAQ after summer Detection setup: tracking detectors at S2 - TPCs will be used. New TPCs tested in a beam time last April New on-line analysis based on Go4 implemented and tested
Eurisol DS, Task 11 meeting, Helsinki September‘07 Planned work for the next months Implementation and test of the new acquisition at the FRS Fix last details of the experimental setup - calibration requirements for TPCs - photo-multipliers at S2 - removable target at S2 Detailed planning of the experiment - calculation of the magnetic tunings of the FRS - calibration planning with the 136 Xe beam - definition of working teams Final schedule of the beam time: constraints
Eurisol DS, Task 11 meeting, Helsinki September‘07 Preliminary beam-time schedule at GSI
Eurisol DS, Task 11 meeting, Helsinki September‘07 Modifications of initial plans The beam time will be scheduled 9 months later than expected - all milestones of these subtask will be delayed by 9 months