This talk is not a summary of costs for conventional facilities This talk is Review of conventional facilities used by CDF Discussion of status of systems.

Slides:



Advertisements
Similar presentations
Setup/Installation/Operation of an Environmental Control Unit (ECU)
Advertisements

Assembly Hall in Hybrid-A’ and ILD 2014/9/6 Yasuhiro Sugimoto 1.
Current status Arkadiy Klebaner November 21, 2012
Dirty Tour December 2005 UN Capital Master Plan. 2 Dirty Tour- introduction The UN building was a state-of-the-art, code compliant structure when it was.
CNN Center John Hester Turner Properties, Inc.. CNN Center Built in ,583,000 square feet on 18 floors Five structures joined by a common atrium.
Global Design Effort Detector concept Plenary introductory talk IRENG07 Kurt Krempetz September 17, 2007.
Central Region Discussion Power and Cooling GDE Beijing-CFS.
Learning, our way Examples of bad installation. CONTENT Installation related examples Installation related examples Application related examples Application.
PIP Update Linac Utilities for 2014 shutdown Matthew Gardner, 4/23/14.
1 The Support Structural System for Sicbar and EC Detector of SciBooNE FermiLab/PPD/MD May 08, 2006 Edward Chi.
ILCTA_NML Progress at Fermilab Jerry Leibfritz September 10, 2007.
CDF Decommissioning Status Jonathan Lewis D&D Task Force 22 November 2011.
1 MICE-Video Conference Status of MICE Hall Contents: General status Electrical Mechanical Preparing for Steps II & III Risks and worries Andy Nichols,
Thomas Jefferson National Accelerator Facility Page 1 UITF Progress meeting Approved Labyrinth Fresh air pulled through “chicken wire” gate.
NUMI NuMI Review of the Infrastructure – W, G & V 20 July 2001 WBS Page 1 1 Infrastructure Review - W.B.S Water Systems Water Systems –Upstream.
MTA Cryogenics: Where We Are The Work of Fermilab AD/Cryo Barry Norris, Christine Darve and a host of wonderfully talented Cryogenic Personnel John Thompson,
CDF Decommissioning Status Jonathan Lewis Master Planning Meeting 9 November 2011.
Conceptual Design Study - Cryogenic Requirements How to decide the layout of ILC cryogenic system Conceptual design of cryogenic system Layout of cryogenic.
1 5 December 2012 Laurent Roy Infrastructure / Electronics Upgrade -Cabling (long distance) -Rack and Crate (space, electrical distribution, cooling) -Detector.
1 Discussion for basic options — engineering video conference July 12, 2006 Outline Water pool — advantages — issues, problems, engineering options Aquarium.
Thomas Jefferson National Accelerator Facility Page 1 Hall B Drift Chambers Review, March 2007 George Jacobs Jefferson Lab Hall B 12 GeV Upgrade Drift.
WP2 Superbeam Work Breakdown Structure Version 2 Chris Densham (after Marco Zito version 1 )
Cryo AIP Muon Campus AIP Review Arkadiy Klebaner January 23, 2012.
Magnetic Mitigation - Contents l Magnetic Mitigation General l West Wall Compressors l Rack Room 2 l Magnetic Shielding Yoke Jason Tarrant – Integration.
ORKA Preservation Task Force ORKA Preservation Task Force first meeting Wednesday, February 8, Notes by Peter H. Garbincius Notes from meeting are.
SC Project Review of NCSX, April 8-10, 2008 NCSX Cryogenics Systems WBS-62 Steve Raftopoulos NCSX Cryogenic Systems WBS(62)
Progress Completed Order/Fabricate SS Piping for HBD Purge gas from all detectors DAQ tests Prep. for Shutdown work (open doors, move carriages, etc. Pave.
CMS FPIX Cooling System Studies Joe Howell, Fermilab for the FPIX Upgrade Mechanical Working Group CMS Upgrade Workshop April 27,
Spectrometer Solenoid Fabrication Status and Schedule Steve Virostek Lawrence Berkeley National Lab MICE RAL October 20, 2008.
1 MICE Hall and Infrastructure - Progress since CM18 Chris Nelson MICE CM19 Oct 2007.
1Page # Machine Assembly WBS 700 By: James H. Chrzanowski January 24, 2001.
Paolo Guglielmini - TS / CV LHCb Install Meeting - 20/04/2005 LHCb Install Meeting 20/04/05 TS / CV / Detector Cooling Installations.
PHENIX WEEKLY PLANNING 2/2/06 Don Lynch. Prep Schedule for Run 6 BBC N&S dried, tested re-installed, final tested [DONE] MuTr FEE and anode purge lines.
ILC Test Facility at New Muon Lab (NML) S. Nagaitsev Fermilab April 16, 2007.
Kurt Krempetz (Director's Review - Dec. 7, 99) 1 Mechanical Infrastructure Kurt Krempetz Introduction Existing Systems New Systems Schedule Manpower Conclusions.
Johan Bremer, 22th-26th September 2008 Cryogenics Operations 2008, CERN, Geneva, Switzerland 1 CRYOGENICS OPERATIONS 2008 Organized by CERN Safety aspects.
1 Mice Collaboration Meeting CM33 Glasgow University 25 th – 29 th June 2012 STFC Daresbury Laboratory Electrical Infrastructure Report Authors : Ian Mullacrane.
SC Project Review of NCSX, April 8-10, 2008 NCSX Cryogenics Systems WBS-62 Steve Raftopoulos NCSX Cryogenic Systems WBS(62) Manager.
Karl Williams Mechanical Engineer AD/MS Fluids Group Absorber RAW Cooling Systems.
1 13 Octobre 2011 Laurent Roy ATCA Crate / Infrastructure in place -Rack in D3: dimension -Electrical power availability -Tell1 racks running in D3 (air.
Iouri Ivaniouchenkov RAL Specifying the needs for MICE July 8, RAL MICE Collaboration Meeting 1.
Preparations for Run 6 Don Lynch February 13, 2006.
FESS/Ops Shut Down Summary Week Ending 9/7/12. – FESS needs a CUB Cooling Outage for installation of Barriers in the CUB Chiller 4160 Volt Starter Cabinet.
CMTF Infrastructure Jerry Leibfritz PIP-II Machine Advisory Committee 9-11 March 2015.
NML - RF Unit Test Facility Jerry Leibfritz Fermilab.
CD-doc-650 Fermilab Computing Division Physical Infrastructure Requirements for Computers FY04 – 07 (1/4/05)
Mike Andrews May 10, Week 54 NuMI Activities Initial test controls on the MI65 RAW exchange skid Complete hydrostatic test of the MI65 exchange.
FESS/Ops Week Ending 1/20/13. CUB Status – Boiler #1 ON LINE CB Kramer due in to Wire in second recirculating Pump and install NFPA 70E mitigations –
PXIE Layout and Infrastructure Building, Cryogenics, Utilities… Rich Stanek On behalf of the CMTF Team PXIE Collaboration Meeting November 28, 2012.
West Cambridge Data Centre Ian Tasker Information Services.
Facility Layout and Infrastructure Requirements Rich Stanek (on behalf of CMTF facility team) PXIE Program Review January 16-17, 2013.
ILCTA_NML Progress at Fermilab Jerry Leibfritz August 16, 2007.
Schedule to completion, Risk and Critical Interfaces Roy Preece STFC RAL RLSR 16 th April 2015.
Schedule and Milestones Roy Preece STFC RAL FAC 17 th April 2015.
CD-doc-650 Fermilab Computing Division Physical Infrastructure Requirements for Computers FY04 – 07 (1/4/05)
Installation of the T600 at Fermilab Fermilab, February 15,
1 CFS Utilities – What’s included in RDR for IR July CFS Utilities – IRENG WG C WATER COOLING: none. Unknown loads on IR. Only have water plants.
WELCOME. Glycol Refrigeration A most basic definition of refrigeration is taking heat from someplace we don’t want it and moving it to someplace where.
James McIntyre VRF Training Manager V5 Key Components.
S A Griffiths CM42 June 2015 Electrical & Control.
1 Update of detector hall in mountain regions Y.Sugimoto in Granada.
ARAC/H/F Air-cooled water chillers, free-cooling chillers and heat pumps Range: kW.
CBETA Technical Review
Detector Utility/Service Cavern
SBN Far Detector integration model overview
Update of experimental hall in Japanese mountain site
Detector Service Cavern for ILC
FRESNO COUNTY WEST ANNEX JAIL
Maintenance at ALBA facility: Strategy for the conventional services
SNS Cryoplant Commissioning Past Experiences
Presentation transcript:

This talk is not a summary of costs for conventional facilities This talk is Review of conventional facilities used by CDF Discussion of status of systems moving forward A request for specifications so we can coexist with IARC Possibly get some things paid for before ORKA is funded Context Fermilab is planning a rehab of the CDF assembly building in FY14 We should make sure ORKA’s needs are met or we will pay later 10/17/ Conventional Facilities

10/17/2012Conventional Facilities 3

CDF had counting rooms on three floors Third floor: low quality computer room Convert to IARC offices First floor: easy access to high-bay areas Use for technician space Second floor 70’x22’ Maintain aisle, so probably use only 18’ 225A 3-phase electrical panel Service cable to add two more if needed Electronics cooling water loop Cable raceways to first floor with easy access to penetrations to collision hall (see drawing) Plan for ORKA shifts in IF control room in high rise 10/17/2012Conventional Facilities 4

10/17/2012Conventional Facilities 5 Cable penetrations 4 or 6 per location 14”x6”each Proposed Assembly Area

10/50 ton crate West high bay and deep pit to be used by IARC We need to reserve space at south end of pit for a transport cart to move ORKA package or components into hall 10/17/2012Conventional Facilities 6

All CDF muon elements will be removed Central Detector to be moved 10’ north for ORKA Requires new cryo connections, floor pads Electrical Power Electronics cooling loop Maintain racks in 8 corners Facility for 3 crates per corner with 10A 208 three-phase power each Cooling fans with air-water heat exchangers Do we need a crane for assembly? What are the fire suppression needs? Can/should we keep the existing Halon spheres? 10/17/2012Conventional Facilities 7

Solenoid operated at 14.1 T 1.25T should not be a problem Field map exists Some modification expected if we proceed with current plan for mounting rails Field probably not reversible Power supply intact Plan nearly complete for preservation Requires sign-off by experts Probably will fill vacuum vessel with dry nitrogen 10/17/2012Conventional Facilities 8 Work needed to resurrect New current and cryo feeds for new position, also power for pumps, etc. Update controls Do we want to repair the Watt can? Risk vs. benefit analysis required

Cryo system intact Equivalent to one Tevatron satellite fridge Relies on Micom compressor in B0 service building Cooled with pond water Control system must be updated New ODH system also needed IARC will need additional refrigerators for their program Not wise to share even if capacity exists Need to spec out needs on both sides 10/17/2012Conventional Facilities 9

10/17/2012Conventional Facilities 10

Three Main Feeds Building Power Lights, receptacles, crane, etc. Misc. panels around high-bay and collision hall Utility Power Solenoid Trailers 225A each to 1st and 2nd floor counting rooms 10/17/2012Conventional Facilities 11 Experimental Power Collision Hall (800A) Assembly Hall Pit (IARC) Open circuits (IARC) Feed for two 225A circuits in 2nd floor counting room Need transformers

CDF had facilities to serve many wire chamber systems Control and measurement components removed Extant infrastructure Tube trailer connections and mix shed over berm Large storage tanks behind building Supply lines from gas platforms to CH Two large LN2 dewars For cryo and interting flows 10/17/2012Conventional Facilities 12

10/17/2012Conventional Facilities 13

Chilled water (CW) Cooled by two 185-ton Trane chillers Can use PW/ICW heat exchanger for low load periods Serves HVAC and secondary cooling loops Plumbing to Mechanical Rooms, Assembly Pit and 3 rd floor counting room Pipes to 1 st and 2 nd floor cut – can reroute if needed 10/17/2012Conventional Facilities 14

Ponds empty from A2 to B3 Require extensive reconstruction Needed for beamline? Pumps intact Used for LCW Previously used with compressors for CW ICW can be used in place of PW Single pass Don’t know capacity 10/17/2012Conventional Facilities 15

Low conductivity water (LCW) Cooled by PW/ICW Water-water tube heat exchanger is very old Original capacity was 650 kW Could not keep up with conventional test magnet during Run II Solenoid is 150 kW Shared with IARC Plan to reuse plumbing in assembly pit Currently no power to pumps Motor control center requires rebuild Should be part of IARC rehab project 10/17/2012Conventional Facilities 16

10/17/2012Conventional Facilities 17

Electronics Cooling Water (ECW) Secondary loop off CW Serves collision hall, 1 st and 2 nd floor counting rooms Racks on detector have water cooling Pumps in alcove of pit No sharing with IARC Other Pluming from SVX and ISL water-glycol system from alcove to collision hall can be repurposed Rest of system is obsolete SUVA system for COT has been claimed by mu2e 10/17/2012Conventional Facilities 18

10/17/2012Conventional Facilities 19

Two separate systems Assembly Building: Metasys Collision hall : CDF Slow Controls High rate of recirculation to avoid stratification Both must be replaced Must include capability for ODH and flammable gas protection CDF priorities Pressure to protect drift chamber Temperature Humidity Avoid HV breakdown 10/17/2012Conventional Facilities 20

10/17/2012Conventional Facilities 21

Plan from Joe Howell and John Rauch See DocDB Projects-doc /17/2012Conventional Facilities 22

10/17/2012Conventional Facilities 23

What are ORKA’s cooling loads? ECW, LCW, HVAC Collision hall HVAC requirements? Gas delivery requirements? Safety issues? ODH, flammable gas Nitrogen inerting? Large volume inside solenoid Installation Plan? Do we need crane(s) in the collision hall 10/17/2012Conventional Facilities 24