JOINT WORKSHOP ON MULTIPLE-USE APPLICATIONS
AMS’S 50 MW FLEET FOR SO. CAL EDISON MULTIPLE USE CASE #5: BEHIND- THE-METER DISTRIBUTED ENERGY RESOURCES PROVIDING SERVICES TO END-USE CUSTOMERS, THE DISTRIBUTION GRID AND THE CAISO MARKET AMS PROJECT 250 KW / 1,500 KWH INSTALLATION
MULTIPLE USE | UTILITY, CUSTOMER AND GRID VALUE
KEY POINTS CLARITY & CONSISTENCY: INTERCONNECTION, METERING, TELEMETRY AND GENERAL MARKET RULES URGENCY: THESE PROJECTS ARE ONLINE NOW! ERR ON THE SIDE OF INNOVATION: PARTICIPATION IN MULTIPLE PROGRAMS KEEP THINGS SIMPLE
RECOMMENDATIONS CONTINUE TO DEVELOP AND REFINE MEASUREMENT RULES OPEN MORE OF MARKET FOR PDR (REGULATION SERVICES) RECOGNIZE VALUE OF BTM RESOURCES ON DISTRIBUTION GRID IDENTIFY USES THAT ARE COMPLIMENTARY / IN CONFLICT - BREAK DOWN BARRIERS FURTHER EXPLORE: WHOLESALE AND RETAIL MARKET PARTICIPATION OTHER VALUES STORAGE CAN PROVIDE (LOCATIONAL VALUE, CVR)
APPENDIX
BATTERY METER MEASURES PERFORMANCE OF FIRM & DISPATCHABLE RESOURCE ‣ BASELINES FOR DR TRIES TO GUESS THE COUNTERFACTUAL OR ALTERNATE UNIVERSE. THEY ARE “GOOD” FOR LOADS BECAUSE THEY ESTIMATE “NORMAL” LOAD PATTERNS ‣ A COUNTERFACTUAL FOR ENERGY STORAGE BEHAVIOR IS A MYTH. WITHOUT DUAL USE, THE STORAGE SYSTEM WOULD NEVER BE INSTALLED ‣ WHEN METERING IS AVAILABLE, PRIOR ACTIVITY OF AN ENERGY STORAGE FACILITIY SHOULD NOT BE USED FOR PERFORMANCE EVLAUTION ‣ DON’T GUESS THE COUNTERFACTUAL IF WE DON’T NEED TO
DEMAND REDUCTION ‣ UNIT CAN SUPPLY 8 UNITS OF ENERGY ‣ RAMP IS “FAST”, I.E. CAN DELIVER ALL 8 UNITS IN ONE HOUR IF NECESSARY ‣ CHARGING IS PERFORMED DURING OFF- HOURS, AND NOT CONSIDERED IN ANALYSIS ‣ “NORMAL” OPERATIONS ASSUMES PEAK- SHAVING ‣ BATTERY IS USED TO SHAVE 8 UNITS OF ENERGY OVER 4 HOURS ‣ PEAK IS REDUCED FROM 9 TO 6
MARKET DISPATCH ‣ ASSUME NOW THAT RESOURCE MAY NOW BE CALLED FOR REDUCTION EITHER BY AN ISO OR A DISTRIBUTION OPERATOR ‣ THE RESOURCE IS ENROLLED TO PROVIDE THE FULL RANGE OF REDUCTION, IN THIS CASE 8 UNITS OF ENERGY ‣ BATTERY IS CALLED TO REDUCE DURING A 3 HOUR WINDOW ‣ 8 UNITS OF ENERGY ARE CONTRIBUTED (MEASURED VIA METER) ‣ NOTE THAT PEAK LOAD IS UNCHANGED DISPATCH WINDOW
DEMAND REDUCTION & DISPATCH ‣ STORAGE OPERATOR MIGHT DECIDE TO NOT PROVIDE FULL REDUCTION AS CALLED, IN ORDER TO PERFORM SOME PEARK REDUCTION ‣ THE RESULTING PROFILE WILL SHOW LESS PEAK REDUCTION BUT ALSO SOME DR, NEITHER OF WHICH SHOW THE FULL BENEFIT OF THE PREVIOUS SCENARIOS ‣ BATTERY TO CALLED TO REDUCE DURING A 3 HOUR WINDOW ‣ 5 UNITS OF DEMAND REDUCTION SUPPLED (AS OPPOSED TO 8) ‣ PEAK REDUCED TO 7 (AS OPPOSED TO 6) DISPATCH WINDOW
DISPATCH PERFORMANCE USING METER PEAK LOAD VIA IOU METER DAY 1 = 6 UNITS DAY 2 = 9 UNITS DAY 3 = 7 UNITS DAY 1 DAY 2 DISPATCH DAY 3 DISPATCH DISPATCH PERFORMANCE CAN BE MEASURED DIRECTLY: DAY 1 = NOT APPLICABLE DAY 2 = FULL REDUCTION (8 ENERGY UNITS) DAY 3 = PARTIAL REDUCTION (5 ENERGY UNITS)
DISPATCH PERFORMANCE USING BASELINE DAY 2 ACTUAL REDUCTION IS THE FULL AMOUNT (8 ENERGY UNITS) BUT THE BASELINE, DAY 1 IS THE SELECTED BASELINE DAY, AND THE CALCULATED REDUCTION WILL BE ONLY 5 ENERGY UNITS DAY 1 DAY 2: DISPATCHDAY 3: DISPATCH DAY 3 ACTUAL REDUCTION IS 5 ENERGY UNITS, A PARTIAL REDUCTION USING THE BASELINE, DAY 1 IS AGAIN THE SELECTED BASELINE DAY, AND THE CALCULATED REDUCTION WILL BE ONLY 2 ENERGY UNITS
THANK YOU 25 Stillman Street, San Francisco, CA |