High Energy Dump of the Super Proton Synchrotron at CERN – Present and Future designs A. Perillo-Marcone (EN-STI) Contributions from several colleagues.

Slides:



Advertisements
Similar presentations
Matt Rooney RAL The T2K Beam Window Matt Rooney Rutherford Appleton Laboratory BENE November 2006.
Advertisements

Internal H0/H- dump Cesare Maglioni, Melanie Delonca Thanks to: R. Chamizo, R. Versaci, O. Aberle, J. Borburgh.
SSRF1 ALUMINUM ALLOY VACUUM CHAMBERS FOR SSRF L.X. Yin, D.K. Jiang, H.W. Du, X.L. Jiang SSRF Vacuum Group Shanghai National Synchrotron Radiation Center.
UCN Phase 2 Design Status September 10, Design Components Bulk Shielding Target Crypt Cryogenic Insert Target Insert UCN Port Beam Window Cooling.
TED Thermomechanical Analyses Esposito Raffaele EN-STI-TCD.
SLAC rotating collimator for HiRadMat beam tests 14 March 2014 S. Redaelli, A. Bertarelli, CERN T. Markiewicz, SLAC US LHC Accelerator Research Program.
LARP Rotatable Collimator Prototype Assembly completed and all mechanical tests successful: Cooling tubes twist, under vacuum, as jaws turn, with R~1 m.
High Energy Dump LSS5 STI Cost Estimate A.PERILLO MARCONE & F.PASDELOUP 2015/04/16 With contribution of R.FOLCH & D.GRENIER.
Engineering Department ENEN Choice of the material for TCTP ferrite supports Collimation Working Group F. Carra, G. Cattenoz, A. Bertarelli,
MECHANICAL DESIGN OF TCSP COLLIMATORS Secondary Collimators Embedding BPMs L. GENTINI, A. Dallocchio, A. Bertarelli, F. Carra, M. Garlasche.
Introduction to collimators Integration of BPM Mechanical design Electrical design Processing Simulations Results Conclusions & Outlook.
LARP LHC PHASE II COLL RC1 TESTS - S. Lundgren 06 June 2006 No 1 /17 LARP Phase II Secondary Collimator RC1 Collimator Test Program Plan Forward Revised.
1 Status of the CLIC two-beam module program A. Samochkine, G. Riddone Acknowledgements to the Module WG members 4 February 2014 CLIC Workshop 2014 (3-7.
Engineering Department ENEN Screwed solutions for the new tertiary collimator jaw assembly Federico Carra (CERN EN/MME) Geneva, 4 th September th.
PSB dump: proposal of a new design EN – STI technical meeting on Booster dumps Friday 11 May 2012 BE Auditorium Prevessin Alba SARRIÓ MARTÍNEZ.
A. Bertarelli – R. Perret CERN TS – MME Group 1 CERN European Organization for Nuclear Research Mechanical Engineering and Thermo-mechanical.
XFEL-INJ1/2 DUMPS Remarks / Requirements, Injector Beam Dynamic Review Meeting, DESY, Mon. 23. October 2006 ‹#› XFEL - INJ 1/2.
F. Regis, LINAC4 – LBS & LBE LINES DUMP DESIGN.
Preliminary View on the LHeC Experimental Vacuum Chambers Jonathan Bosch - University of Manchester And Ray Veness - TE/VSC J.Bosch and R.Veness LHeC -
TCLDA Design status Collimation Upgrade Specification Meeting L. GENTINI.
Internal H0/H- dump M. Delonca, C. Maglioni On behalf of EN/STI Thanks to: A. Christov, S. Mathot, C. Pasquino, A. Patapenka.
STATUS OF H0/H- DUMPS M. Delonca – LIU meeting 29/11/2012 Thanks to: C. Maglioni, A. Patapenka, C. Pasquino, A. Perez, N. Mariani.
Beam line Experiment area SC magnet Pion production target
ISOLDE Activities for LS2 Richard Catherall EN-STI ISOLDE Technical Coordinator.
Beam loads & dump concepts T. Kramer, B. Goddard, M. Benedikt, Hel. Vincke.
PSB dump replacement 17 th November 2011 LIU-PSB meeting Alba Sarrió.
Presentation at BBC, Linac 4 Commissioning Dump at 50 and 100MeV 1 Øyvind Dahle Lauten, EN-STI.
PS/SPS Days Roberto Losito/Oliver Aberle 13th January 2004
LHC Collimators Phase 2 - Visit to Plansee 28th August Materials for Phase II collimators.
TIDVG2014 PRODUCTION AND INSTALLATION STATUS 23/07/2014 – “TIDVG Follow-up Meeting” Ivo Leitão.
TPSG4 validation at HighRadMat #6 Cedric Baud, B. Balhan, Jan Borburgh, Brennan Goddard, Wim Weterings.
A. Bertarelli – A. DallocchioWorkshop on Materials for Collimators and Beam absorbers, 4 th Sept 2007 LHC Collimators (Phase II): What is an ideal material.
Engineering studies for CN2PY secondary beam. LAGUNA-LBNO General Helsinki, 26/08/20141 F. Sanchez Galan (CERN) on behalf of the CERN Secondary.
HL-LHC-UK Thermal Shield Update Niklas Templeton 07/03/2016.
RECENTLY OBSERVED PROBLEMS WITH PRESENT TIDVG 30/07/2014 – “LIU-SPS External Beam Dump” Ivo Leitão.
Design for a 2 MW graphite target for a neutrino beam Jim Hylen Accelerator Physics and Technology Workshop for Project X November 12-13, 2007.
Target Systems and Monolith Design Update Rikard Linander Group Leader Monolith and Handling April 2, 2014.
1 Target Introduction Chris Densham STFC/RAL Mu2e Target, Remote Handling, and Heat & Radiation Shield Review Nov
Engineering of the power prototype of the ESRF HOM damped cavity* V. Serrière, J. Jacob, A. Triantafyllou, A.K. Bandyopadhyay, L. Goirand, B. Ogier * This.
Internal H0/H- dump M. Delonca On behalf of EN/STI Thanks to: A. Christov, C. Maglioni, S. Mathot, C. Pasquino, A. Patapenka.
Movable beam pipe and NNC Study & prototype development Manchester 14/12/20091D. FP meeting.
SPS High Energy LSS5 Thermal contact & cooling aspects
V. Raginel, D. Kleiven, D. Wollmann CERN TE-MPE 2HiRadMat Technical Board - 30 March 2016.
Chiara Di Paolo EN-STI-TCD Material Choice for the Vacuum Window at the Exit of BTM.
New nTOF target: Design Issues
STI test HRMT-35 and Collimator plans for 2017 Special ColUSM: Material and design readiness for LS2 productions 2th May 2017 I. Lamas Garcia,
Status of HRMT23 Activities F. Carra, E. Berthomé, G
n_TOF Target HiRadMat Experiment Proposal (1704)
Proposal TDIS-TZM WP14 TDIS jaw validation testing
A. Vande Craen, C. Eymin, M. Moretti, D. Ramos CERN
Impact of TIDVG problem on LSS5 dump design schedule
Preliminary Y-chamber specifications – First draft
Components for the Machine-Interface Regions
Design of TIDVG#4 A. Perillo-Marcone (EN-STI).
Vacuum System Failures at HERA
Dump Core Studied Design Solutions
TIDVG-4 TIDVG-4 Dump assembly, welding and installation Process sector BA1 February 2017 J. Humbert, (EN/MME) 06/02/2017 J. Humbert, EN-MME.
Thermo-mechanical simulations jaws + tank
TCTW Collimator Design F. Carra1,2 A. Bertarelli, M. Garlasche, L
TDI Coating test at HiRadMat Proposal 1605 HiRadMat Scientific Board Meeting 27th June 2016 I. Lamas Garcia, M. Calviani, R. Ferreire, A. Perillo-Marcone.
Federico Carra – EN-MME
Beam Dump outline work plan (UK perspective)
Linac4-PSB 160 MeV connection readiness review ( TE/VSC )
Status of the PANDA Solenoid Magnet Production in BINP
Scrubbing progress - 10/12/2012
Phase II Collimators : design status
HiRadMat Test Facility
Ch. Boccard, M. Krupa, G. Schneider, R. Veness, M. Wendt
n_TOF Target #3 Baseline Design
Presentation transcript:

High Energy Dump of the Super Proton Synchrotron at CERN – Present and Future designs A. Perillo-Marcone (EN-STI) Contributions from several colleagues from EN/STI, EN/MME, EN/HE, EN/ACE.

SPS/Dump Layout 6th April 2016SPS High Energy Dump Design - A. Perillo-Marcone22 Current Dump position Future Dump position

Current Dump – TIDVG (to be replaced during LS2 by the dump presented here) 6th April 2016SPS High Energy Dump Design - A. Perillo-Marcone33 Iron Shielding (EN-GJL-200) Copper Core – 4.3 m (OFE, C10100 H02) Graphite – 2700 mm (2020 PT) Aluminium – 800 mm (EN AW 6082 T6) Copper – 500 mm (OFE, C10100 H02) Tungsten – 300 mm (Densimet 180) Beam Beam opening Copper core (Envelope+blocks) Shielding Section A-A Section B-B Cooling circuit for copper core Cooling pipes for shielding B B A A

Previous dump failure 6th April 2016SPS High Energy Dump Design - A. Perillo-Marcone44 TIDVG 1 ( )TIDVG 2 ( ) Aluminum block after operation

Operating limits imposed by current design (applied only after LS1) 6th April 2016SPS High Energy Dump Design - A. Perillo-Marcone55 Beam Beam Power (kW) Number of pulses accepted Max. T in Aluminium (°C) Cooling time to 35 °C (min) LHC-Standard (25 ns) LHC-50 ns57.7unlimited12121 Doublet62.3unlimited18329 FT 100%178.03x3 (40s spacing)20524 LHC-Std. – FT 100%62.5unlimited25046 The interlock has been set so that if more than 3.66E13 protons are dumped within a sliding time window of 36s, then a waiting time of 70s is enforced.

Operation of Current Dump 6th April 2016SPS High Energy Dump Design - A. Perillo-Marcone66 Good agreement for total power transfer as shown by water pipe measurements. Also good agreement in primary shielding Observable difference for temperature in Copper jacket around Al section. This indicates a lower TCC than anticipated, implying the possibility of higher temperatures in the Al section Possible explanation: flatness defects of copper jacket surfaces To be verified with higher intensity beams and if necessary re-set limits Water temperature Cu core temperature

Aspects of current design to be improved 6th April 2016SPS High Energy Dump Design - A. Perillo-Marcone77 Graphite installed before welding Cu core (long time exposed to air and other possible contaminants). High outgassing rates. No proper bake-out possibilities after installation. No internal instrumentation (blind during operation). Only visual inspection possible (limited by high radioactivity). Aluminium as beam-absorbing material. Poor performance at high temperature, low melting point, resulting in limited operation. High uncertainty, unreliability of cooling efficiency due to unpredictable thermal contact between blocks and Cu core. Limited choice of suppliers due to design.

New Design Proposal 6th April 2016SPS High Energy Dump Design - A. Perillo-Marcone8 Primary shielding (cast iron) (5m long x ~1m diameter) Core (Copper) (5m long x ~300mm diameter) Graphite (4300 m) Copper (400mm) Tungsten (300mm)

Dump Core + Primary Shielding 6th April 2016SPS High Energy Dump Design - A. Perillo-Marcone9 < 22 t 850

Dump Core - Current Design 6th April 2016SPS High Energy Dump Design - A. Perillo-Marcone10 EB Welding 4 sub-parts welded Material: OFE copper 2500mm

Dump core cooling – preliminary design 6th April 2016SPS High Energy Dump Design - A. Perillo-Marcone11 Cooling channels Absorbing block Compression Spring Cooling plate CuNi pipe Brazed to Glidcop plate

Preliminary Thermo-mechanical Analysis 6th April 2016SPS High Energy Dump Design - A. Perillo-Marcone12 Graphite Temperature MaterialMax. Temp ( o C) Stress (MPa) Strength (MPa) Graphite Copper192230>300 Tungsten 67143>500

Improvements, advantages over TIDVG 6th April 2016SPS High Energy Dump Design - A. Perillo-Marcone13 Improved cooling of absorbing blocks. Decoupling of cooling and positioning of absorbing blocks. Possibility to insert/extract absorbing blocks after manufacturing of Cu core Temperature measurements of absorbing blocks, Cu core and primary shielding. Integrated bake-out system for dump core. Smaller, more manageable parts (more suppliers for Cu core). External shielding (personnel protection). Better shower attenuation (machine protection). More accurate positioning/alignment.

Feasibility, open questions 6th April 2016SPS High Energy Dump Design - A. Perillo-Marcone14 Open questionsIssuesActions/Future studies Thermal contact effectiveness between absorbing blocks and cooling plates TCC test bench Prototype Feasibility of cooling plate – cooling pipe assembly. Cooling pipe supply Bending Research of suppliers. Prototype Design optimisation Robustness, inspectability, reliability of welds. Risk of leaksPrototype Design to allow NDT of all welds. Erosion-corrosion in cooling system. Risk of long term leaksMinimise water velocity. Erosion/corrosion tests for OFE-Cu. Material selection to prevent this issue. Long term performance (20-30 years) of materials and welds under irradiation. Embrittlement => cracks => leaks. Relaxation of springs cooling plates Literature research previous/ongoing studies. Selection of materials. Long term of temperature sensors and bake-out system. Loss of monitoring in long term Collect data and analyse it from early stages of operation.

Prototype 6th April 2016SPS High Energy Dump Design - A. Perillo-Marcone15 500mm

Schedule (main milestones) 6th April 2016SPS High Energy Dump Design - A. Perillo-Marcone16

Thank you for your attention.

Back-up slides 6th April 2016SPS High Energy Dump Design - A. Perillo-Marcone18

External Shielding Dump Core Proposed Design for future dump 6th April 2016SPS High Energy Dump Design - A. Perillo-Marcone19 Primary Shielding Supports (jacks) Alignment rods Vacuum chamber Mushroom for remote handling

Full assembly 6th April 2016SPS High Energy Dump Design - A. Perillo-Marcone20