ATLAS Upgrade Report to the LHCC ATLAS Upgrade Report to the LHCC Phil Allport 25/09/12 Schedule Assumptions Phase-0 –IBL –Consolidation of Many Systems.

Slides:



Advertisements
Similar presentations
M. Gilchriese US ATLAS Pixel Meeting July 18-19, 2002 UC Santa Cruz.
Advertisements

H1 SILICON DETECTORS PRESENT STATUS By Wolfgang Lange, DESY Zeuthen.
The ATLAS Pixel Detector
(ATLAS) Higgs Prospects at HL-LHC. ATLAS CMS ALICE LHCb Center-of-Mass Energy ( ) 7 TeV Center-of-Mass Energy (Nominal) 14 TeV ? Center-of-Mass.
The ATLAS Upgrade Programme Thorsten Wengler ECFA High Luminosity LHC Experiments Workshop 1 st – 3 rd October 2013 Aix-les-Bains, France.
The LAr ROD Project and Online Activities Arno Straessner and Alain, Daniel, Annie, Manuel, Imma, Eric, Jean-Pierre,... Journée de réflexion du DPNC Centre.
The LHCb Inner Tracker Marc-Olivier Bettler SPS annual meeting Zürich 21 February 2007.
1.ATLAS and ID 2.SCT 3.Commissioning 4.Integration 5.Latest Runs 6.Conclusions Commissioning the ATLAS Silicon Microstrip Tracker IPRD08 - Siena Jose E.
Module Production for The ATLAS Silicon Tracker (SCT) The SCT requirements: Hermetic lightweight tracker. 4 space-points detection up to pseudo rapidity.
ATLAS detector upgrades ATLAS off to a good start – the detector is performing very well. This talk is about the changes needed in ATLAS during the next.
The BTeV Tracking Systems David Christian Fermilab f January 11, 2001.
February 19th 2009AlbaNova Instrumentation Seminar1 Christian Bohm Instrumentation Physics, SU Upgrading the ATLAS detector Overview Motivation The current.
March 20, 2001M. Garcia-Sciveres - US ATLAS DOE/NSF Review1 M. Garcia-Sciveres LBNL & Module Assembly & Module Assembly WBS Hybrids Hybrids WBS.
D. Lissauer, BNL. 1 ATLAS ID Upgrade Scope R&D Plans for ATLAS Tracker First thoughts on Schedule and Cost.
Pixel Upgrade Plans ROD/BOC PRR July 17, 2013 T. Flick University of Wuppertal.
M. Gilchriese ATLAS Upgrade Introduction January 2008.
14/November/2002 CF NSS2002 in Norfolk, Virginia, USA 1 The First Integration Test of the ATLAS End-cap Muon Level 1 Trigger System Introduction Overview.
Pixel hybrid status & issues Outline Pixel hybrid overview ALICE1 readout chip Readout options at PHENIX Other issues Plans and activities K. Tanida (RIKEN)
Leo Greiner TC_Int1 Sensor and Readout Status of the PIXEL Detector.
Concluding Summary WBS1.1.2 SCT Subsystem A. Seiden BNL March 2001.
CERN, Main challenges for the ATLAS upgrade project in the coming year.
U.S. Deliverables Cost and Schedule Summary M. G. D. Gilchriese U.S. ATLAS Review Revised Version November 29, 2000.
M&O status and program for ATLAS LAr calorimeter R Stroynowski (on vacations)
Santa Cruz Meeting August 12 th 2008 Layout options & Schedule Issues David Lissauer 8/12/2008 1David Lissuaer, Santa Cruz Meeting.
U.S. Deliverables Cost and Schedule Summary M. G. D. Gilchriese Revised Version December 18, 2000.
2 Silicon pixel part Done and to be written Written! Under way To be done Introduction 1.Hybrid Pixel Assembly Concept 2.Silicon sensor 1.First thinned.
ATLAS PIXEL SYSTEM OVERVIEW M. Gilchriese Lawrence Berkeley National Laboratory March 11, 1999.
8/18/2004E. Monnier - CPPM - ICHEP04 - Beijing1 Atlas liquid argon calorimeter status E. Monnier on behalf of the Atlas liquid argon calorimeter group.
T. Kawamoto1 ATLAS muon small wheels for ATLAS phase-1 upgrade LHCC T. Kawamoto (New) small wheels ? Why new small wheels for high.
ATLAS micromegas activities (MAMMA)
Tevatron II: the world’s highest energy collider What’s new?  Data will be collected from 5 to 15 fb -1 at  s=1.96 TeV  Instantaneous luminosity will.
July 17, 2013 CERN T. Flick University of Wuppertal.
15/09/20111 ATLAS IBL sensor qualification Jens Weingarten for the ATLAS IBL Collaboration (2 nd Institute Of Physics, Georg-August-Universität Göttingen)
Walter Sondheim 6/9/20081 DOE – Review of VTX upgrade detector for PHENIX Mechanics: Walter Sondheim - LANL.
ATLAS Upgrade Report ATLAS Upgrade Report (20/03/12) Planning Assumptions Phase-0 Plans Phase-I Plans - Letter of Intent Phase-II - LoI Planning Conclusions.
1. Efficient trigger for many B decay topologies Muon System CALORIMETERS PRS + ECAL+ HCAL RICH1 VERTEX LOCATOR Efficient PID Good decay time resolution.
AFP Trigger DAQ and DCS Krzysztof Korcyl Institute of Nuclear Physics - Cracow on behalf of TDAQ and DCS subsystems.
LHCf Detectors Sampling Calorimeter W 44 r.l, 1.6λ I Scintilator x 16 Layers Position Detector Scifi x 4 (Arm#1) Scilicon Tracker x 4(Arm#2) Detector size.
IBL – UniGe involvements UniGe Team : G. Barbier, F. Cadoux, A. Clark, S. Débieux, D. Ferrère, C. Husi, G. Iacobucci, M. Weber Other member (KEK): Y. Takubo.
Upgrade Review Meeting Introduction Craig Buttar University of Glasgow RAL 10/5/11.
ATLAS Inner Detector MO_B 2013 to-date status 2014 approve budget H. Pernegger / Pixel PL & ID Resource Coordinator D. Robinson / SCT PL and ID PL A. Romaniouk.
A Fast Hardware Tracker for the ATLAS Trigger System A Fast Hardware Tracker for the ATLAS Trigger System Mark Neubauer 1, Laura Sartori 2 1 University.
Geoff HallLECC LHC detector upgrades Introductory comments on electronic issues Organisation of this short session.
Eric Vigeolas, July the 3 rd Status The IBL detector construction already started and the components assembly (flex, modules, stave loagin) will.
Upgrade intro and report on DESY Upgrade Meeting 5 May 2010 Norman Gee.
Steinar Stapnes, LHCC June The ATLAS inner detector TRT endcap A+B TRT endcap C TRT barrel SCT barrel SCT endcap Pixels uWhole ID sits inside bore.
August 24, 2011IDAP Kick-off meeting - TileCal ATLAS TileCal Upgrade LHC and ATLAS current status LHC designed for cm -2 s 7+7 TeV Limited to.
NSW Electronics Preliminary Design Review Feb 2015 Introduction and Review Scope Feb 2015 NSW ELTX PDR S. Zimmermann 1 Stephanie Zimmermann.
1/20 LHCb upgrade, Jeroen van Tilburg Nikhef Jamboree, 14 Dec 2015 Preparing for the LHCb upgrade.
TDAQ and L1Calo and Chamonix (Personal Impressions) 3 Mar2010 Norman Gee.
ATLAS Italia – IBL G. Darbo – INFN / Genova CERN, 2 March 2011 o IBL ATLAS Italia / Referee CERN, March 2 nd 2010 G. Darbo – C. Meroni INFN / GE – MI Agenda:
RD42 Status Report W. Trischuk for the RD42 Collaboration LHCC Meeting – June 12, 2013 Development of CVD Diamond Tracking Detectors for Experiments at.
Atlas Upgrade week - November 15 th, 2011M. Raymond – CERN/PH-ADO-PO 1 Introduction Many activities are planned to be performed during the shut down
Upgrade Intro 10 Jan 2010 Norman Gee. N. Gee – Upgrade Introduction 2 LHC Peak Luminosity Lumi curve from F.Zimmermann : Nov Upgrade Week ? ?
Straw man layout for ATLAS ID for SLHC
Detector building Notes of our discussion
Micromegas Vertex Tracker Status Report
FCAL R&D towards a prototype of very compact calorimeter
Project definition and organization milestones & work-plan
IOP HEPP Conference Upgrading the CMS Tracker for SLHC Mark Pesaresi Imperial College, London.
P. Morettini Towards Pixel TDR PM - ITk Italia - Introduction 8/2/2017.
2018/6/15 The Fast Tracker Real Time Processor and Its Impact on the Muon Isolation, Tau & b-Jet Online Selections at ATLAS Francesco Crescioli1 1University.
Silicon Pixel Detector for the PHENIX experiment at the BNL RHIC
Optical data transmission for
ALICE upgrade plans Paolo Giubellino LHCC Upgrades
TK Upgrade report.
Francesco Forti University and INFN, Pisa
Preparation of the CLAS12 First Experiment Status and Time-Line
The LHCb Front-end Electronics System Status and Future Development
Presentation transcript:

ATLAS Upgrade Report to the LHCC ATLAS Upgrade Report to the LHCC Phil Allport 25/09/12 Schedule Assumptions Phase-0 –IBL –Consolidation of Many Systems Phase-I –New Small Muon Wheel (see talk of Tatsuo Kawamoto) –Calorimeter L1 Granularity, Trigger/DAQ, FTK, AFP Phase-II –Inner Tracker Replacement –Calorimeter and Muon Readout, Trigger/DAQ, Computing Conclusions

?, IR 4x, bunch spacing 25 ns ~20-25 fb -1 ~ fb -1 ~350 fb -1, bunch spacing 25 ns, bunch spacing 50 ns Go to design energy, nominal luminosity Injector and LHC Phase-I upgrade to full design luminosity HL-LHC Phase-II upgrade, IR, crab cavities √ s=14 TeV, L=5x10 34 cm -2 s -1, luminosity levelling √ s=14 TeV, L~2x10 34 cm -2 s -1, bunch spacing 25 ns √ s=13~14 TeV, L~1x10 34 cm -2 s -1, bunch spacing 25 ns √ s=7~8 TeV, L=6x10 33 cm -2 s -1, bunch spacing 50 ns  LHC startup, √ s = 900 GeV LHC Schedule Assumptions (See for example “HiLumi LHC” Submission to ESPG) (Phase-0) 2

Phase-0

IBL Overview IBL Modules and staves –Sensors & Chips done, Bump-bonding: processing of sensor and electronic wafers completed - first batch of bare modules received, under assembly and qualification –Focus on systematic understanding of FEI4B modules in electrical tests –Several improvements implemented to module assembly and in stave assembly –Stave flex had production hick-up resulting in re-production of more Cu parts –First IBL stave assembled and systematically tested for 2 months now - stave works, some items remain to be understood Integration –Stave production testing ready and gear up now to prepare final test setups for full IBL –Integration tooling being finalized and SR1 area prepared for IBL integration Installation –Service design finalized and working on orders now –Installation tooling is tested in Bat 180, Beam pipe well on the way, IST assembly started –Prepare now detailed installation plan for LS1 Off-detector –Final prototypes for ROD, BOC, opto available, first major FW released and under test now –Integrate now off-detector elements to system test with staves in SR1

Stave Electrical Tests Stave works in calibration scans and source scans –More optimization ongoing (minimal threshold, configuration, powering…) Use first stave for several system-related tests: –Tuning at different thresholds, gains, supply voltages,… –Test of all modules IV –Test of module noise –LVDS Signal transmission and power- up studies –Special test on power line noise and ripple during/after scans –Source test of modules –Cross-talk –Test for merged and disconnected bumps IV curves Signal out Eye diagrams Source scan Noise e- typically Double-chip Module Single- chip Module

Integration in SR1: IBL Around Beam Pipe Currently prepare all tools and SR1 clean room for the final assembly of beam pipe with IBL staves and final test of IBL on surface –Space sharing and room preparation include preparation for Pixel on surface for exchange of service quarter panels Expect to start with stave integration around beam pipe in March 2013 Prepare test system for full IBL Will operate full IBL on surface as final function check before installation in Pixel detector Expect to be ready for final tests in summer 2013 New ATLAS VI beam pipe –Assembly completed end June ahead of schedule –Leak tested after bake-out – found leak –Decided to cut faulty weld and re-weld –Expect delivery as planned in Dec. –Working now on optimizing final layout of beam pipe wrapping (for X 0 and envelop considerations in centre)

Phase-I

LVL1 Calorimeter and Trigger Key target (see also New Small Wheel Presentation) is to maintain high efficeincy for Level-1 triggering on low PT leptons and photons In the calorimeter this implies changes to the front-end electronics to allow greater granularity to be exploited at Level-1. Trigger upgrades include topological trigger, cluster and jet energy processor, feature extractors, muon sector logic and CTP =46, L=2 x From LoI electron rate vs threshold Distribution of the R η parameter for electrons and jets, defined as the ratio of the energy in the 3x2 over the energy in the 7x2 clusters of the 2nd layer of the EM calorimeter.

FTK and AFP Fast TracK (FTK): Global hardware based tracking by start of L2 –Descendent of the CDF Silicon Trigger (SVT) –Inputs from Pixel and SCT. –Data in parallel to normal read-out. –Provides inputs to L2 in ~ 25 μs with track parameters at ~offline precision for b tagging, tau ID and lepton isolation –Two phases: Pattern recognition (10 9 ) Track fitting ATLAS Forward Physics (AFP) –Tag and measure scattered protons at ± 210m –Radiation-hard edgeless 3D silicon developed in IBL context –10ps timing detector for association with high p T primary vertex –Probe hard diffractive physics and central exclusive production of heavy particles → New High Speed Optical link (HOLA) cards installed with dual outputs to allow testing of FTK functionality with real data → < 20 ps timing achievable and minimum gain loss up to ~3C/cm 2

Phase-II

Phase-II (installation ) Integrated radiation levels and particle densities per beam crossing well beyond the design specifications of the experiment. Requirements include: ­New Inner Detector (strips and pixels) − very substantial progress in many R&D areas ­ New LAr front-end and back-end electronics ­ New Tiles front-end and back-end electronics ­ TDAQ upgrade ­ TAS and shielding upgrade ­ Various infrastructure upgrades ­ Common activities (installation, safety, …) ­ New FCAL (if conditions require it)? ­ LAr HEC cold electronics consolidation (radiation hardness)? ­ L1 track trigger (latency budget and physics case)? ­ Muon Barrel and Large Wheel system electronics upgrade? ­ Forward detectors upgrade? 11 FCal Cold cover

ATLAS: Draft Target Specifications Plan for occupancy numbers based on this (see µ values below) Plan integrated dose figures based on this µ values going with the peak luminosity figure if achieved with 25ns beam crossing When we calculate the dose figures which are used to specify the radiation hardness of components which can be reliably tested for post-irradiation performance (eg ASICs, silicon sensors, diamond,...) apply this safety factor to the dose calculations in setting the radiation survival specification 12 * * *

New All-silicon Inner Tracker Baseline layout of the new ATLAS inner tracker for HL-LHC Aim to have at least 14 silicon hits everywhere (robust tracking) Forward pixel Long Barrel Strips Short Barrel Strips Forward Strips Barrel pixel Microstrip Module Prototypes Pixel Quad Module Prototype

14 Possible Trigger Scheme with L1 Track

Full Calorimeter Granularity Level-1 Trigger

ATLAS Phase-II Draft LoI Timeline

Conclusions IBL progressing well for installation in LS1 (Phase-0) Phase-I LoI upgrade projects progressing towards TDRs New Small Wheel upgrade plans being presented for CB approval (see next presentation) LoI for Phase-II well advanced R&D behind these proposals is in a mature state Preliminary exploration of Phase-II physics case undertaken for ESPP ATLAS looks forward to a programme which fully exploits the physics potential of the LHC and its upgrades

Back-up

IBL Modules Sensors - FE chip FEI4B – bump-bonding status –Planar and 3D sensor batches delivered and tested ok with good yield - Done Planar Double Chip Sensor (DCS, 168 installed) : 544 good of 600 delivered = 90.1% yield 3D sensors Single Chip Sensor (SCS, 112 installed) : 306 good SCS on selected 62 wafers (120 wafers total in runs) –FEI4B Chip received in sufficient quantity – have tested ~40 wafers (e.g. ~1600 good chips – IBL installed is 448 –Bump-bonding is well on the way at IZM, which will reach production throughput (~30 modules/week) soon Have flip chipped 136 modules to date for the installed 112 3D modules +168 planar modules –Module flex V3 Finalized design (V3) after module review in June and submitted for production at Pheonix and Mipot 151 SC and 150 DC flexes delivered for first production, then loaded 125 DC and 120 SC at Mipot for first production modules – expect SMD loaded flexes Sept 20 for tests Key topic now: Module assembly –Several changes from FEI4A modules and new FEI4B chip resulted in an ~3 months “learning curve” since review and an overall delay of ~ 6-8 weeks in module production Understanding powering and chip performance through tests New flex and changes to glue (radiation hardness checked) Choice of glue and assembly procedure adapted Several improvements on bonding quality and procedure

Module Tests: Noise, Source Tests, IV, Powering

IBL Stave Assembly Carbon Fibre – 1 st production batch received –1 st batch: 8 staves received (2 rejects) 2 nd batch of staves (~12) for delivery end September –Sufficient bare staves in hand to start final IBL stave loading Stave flex production –First 3 sets received for tests –Delay on production due to accidental over-etching during Copper-layer manufacturing Assembled first stave in June/July – “Stave-0” in Geneva –Thermal cycling of stave+flex –Loaded stave with FEI4A modules –Test and thermal cycling of finished stave –Metrology of stave Several important lessons learned –Bonding on module and stave -> feed-back to module assembly: –Adhesion of flex on stave to improve through abrasion and secure with clamp –Metrology setup improvements to measure module positions Stave design and manufacture fully reviewed in July Next stave with first FEI4B modules to demonstrate final IBL stave for production loading

Off-detector Elements ROD and BOC –5 boards of each produced –Readout first FEI4s with ROD & BOC –Main target now is firmware for first operation –Goal is full system test of IBL stave with ROD/BOC –Plan review later this year to release production of boards Opto & PP2 –First IBL opto board ready for tests. Tests together with nSQP optoboard (same design, different channel count) –20 Finisar VCSELs are in an accelerated lifetime study for at least 1000 hours. –PP2LV design completed & prototyped, 4 boards under test, controller boards done, HV on-going Services –Finalized cable length calculation and routing for cables and fibres –Prepared orders for type 2 cable –Receiving quotes for other cables and fibres –Goal is ready for installation when Atlas opens ROD BOC

IBL Overview Schedule ActivitiesStartingEnding FEI4-BSept 11: SubmissionDec 11 received first chips, Aug 12 received all remaining wafers, testing ongoing Bump bondingAug 11: pre-productionNov 12: Completion (incl. Spares) Module assemblyEnd May 12: 1 st modules ready for loading Feb 13 (spare and contingency incl) Module loadingAug 12:  4 staves to be ready by Oct 12 May 13: Completion (spare and contingency incl) Stave loadingMar 13: starting with the 1 st large batch of available staves June 13: Completion Final tests and commissioning July 13Sept 13: IBL Installation (Nov 13 with contingency) Sensors done, FEI4B available and working, Modules and Staves reviewed Numerous improvements on module assembly, more detailed module tests on FEI4B caused about 2 months delay Stave loading with modules similarly delayed by ~2 months: First FEI4B stave in October, aim to go to stave production loading in November to complete first 4 production staves by end of this year

DBM Modules and Integration Sensors – 12 sensors at bump-bonding assembly, more in production Finalize module assembly now for DBM –Assembled 4 prototype modules with DBM layout, components and module carrier (using planar sensors+ FEI4A for assembly tests) Module assembly worked well, all 4 of 4 test modules fully functional Mechanics –Have build 2 sets of first telescopes as integration test assemblies (verify assembly sequence and check mounting/space on nSQP setup and cruciform Finished PP0 power & readout board design and produced board Finished 1 st set of signal and power bundle (2 needed) HITBUS chip on PP0: –This chip makes the L1 trigger from DBM for Lumi measurement based on Pixel Hitbus signal (Pixel-OR) –Chip received back in May and tested ok –Now first chip included on PP0 and will test DBM telescope self-triggering in October testbeam