11th November 2007 by Eng. Martin O. Ogada Financing of Small-Scale Hydropower Projects & Risks Mitigation for Tea factories A Case for Unilever Tea Kenya.

Slides:



Advertisements
Similar presentations
Presentation to Venture Association of New Jersey 3/16/04.
Advertisements

15 MW Geothermal Energy Plant Stephen Mc Loughlin Stephen Devlin Paul O Reilly Mark Flanagan.
© OECD A joint initiative of the OECD and the European Union, principally financed by the EU Mag. Martin Oder, LL.M. OECD/SIGMA Concessions and Public.
3.2 Investment Appraisal Chapter 19. Investment To purchase capital goods  Equipment  Vehicles  New buildings  Improving existing fixed assets.
© Mcgraw-Hill Companies, 2008 Farm Management Chapter 17 Investment Analysis.
Chapter 17 Investment Analysis
Bootstrapping and Financing the closely held company
Operating under a lower G & A Carlos Garcia Owner/CEO KIRA National 8(a) Association Winter Conference 2015.
Finance Lecture # 4 Jan H. Jansen
Financing Renewable Energy Projects: Issues and Opportunities Peter Y. Flynn Bostonia Partners July, 2013.
Making the Right Wind Power Investment University of Toronto Wind Workshop October 12th, 2005 Mike Crawley, President/CEO AIM PowerGen Corporation.
Mini-Grid Based on Renewable Energy (Biomass) Sources to Augment Rural Electrification Implemented by UNIDO.
Community Energy Opportunities Jon Bell Business Development Manager Mosscliff Environmental Ltd.
Preparing Your Business Plan
The Deal: Valuation, Structure & Negotiation Venture Planning Chapter 14 Dowling Fall 2006.
FDM11 Capital investment apprasal 3 Capital investment appraisal 3.
Financial Strategies For Property Projects. Development Plan  Residential units – area, no. of units, flat size, target buyers  Car parks – no. of car.
Overview Summary from Africa and ASEAN assistance Dr. Peter Pembleton, UNIDO.
‘SIDF’s role in Development of Industrial Sector in Saudi Arabia’ By Ali Al-Dhalaan 8th Rajab, /05/2012.
1 Role of the African Development Bank in Developing Clean Investments Mrs. Hela Cheikhrouhou – Manager Infrastructure Finance, Private Sector Operations,
Financing Urban Public Infrastructure
Introduction ► This slide deck provides a suggested framework for the financial evaluation of an investment project. When evaluating any such project,
Renewable Energy Support Schemes & Capacity Building Needs Benon Bena Manager, Off-Grid Renewable Energy Development Rural Electrification Agency-Uganda.
Background of PPP Negotiation
INVESTMENT AND FINANCING OF RENEWABLE ENERGY PROJECTS
Saving With Solar: LESSONS FROM THE MORRIS HYBRID Power Purchase Agreements MODEL April 18, 2013 ASES ANNUAL CONFERENCE BALTIMORE, MARYLAND.
Capital Budgeting
March 2010 Developing Community Hydro Schemes in Oxfordshire Alison Wilshaw Renewables Advisor TV Energy.
A Typical Business Plan
EIB and the energy sector financing Krzysztof Szyszko Warsaw, 23 rd November 2005.
ENTR 452 Chapter 11: Sources Of Capital.
Utilities Committee Review Illinois Board of Higher Education June 5, 2007 The Energy Resources Center College of Engineering University of Illinois at.
CP methodology adapted to UNFCCC Swedish International Development Agency S ESSION 9.A United Nations Environment Program Division of Technology Industry.
BUSINESS OPPORTUNITIES IN RENEWABLE ENERGIES FOR CHILE BUSINESS OPPORTUNITIES IN RENEWABLE ENERGIES FOR CHILE Javier García M. Deputy Head Investment and.
Keith Girling Panel 1 Information Systems and Professional Issues 2007 (BMAN 30801) – Session 2 Monday 8th October hours Roscoe Building Lecture.
$$ Entrepreneurial Finance, 5th Edition Adelman and Marks 10-1 Pearson Higher Education ©2010 by Pearson Education, Inc. Upper Saddle River, NJ Capital.
INFRASTRUCTURE FINANCING. What is Infrastructure? “Infrastructure is define as the physical framework of facilities through which goods and services are.
Overview of Financial Management. OVERVIEW OF FINANCIAL MANAGEMENT The Corporation Life Cycle Value Creation & Maximization Financial Institutions & Process.
Developing and opening a new facility. Stages in hospitality facility development There are five (5) steps in the development of a hospitality facility:
FOR SIXTY YEARS WE HAVE BEEN TAKING THE POWER FROM WATER AND HANDING IT OVER TO NATIONS LINKING THE DOTS Bucharest, February 20, 2014.
Energy Commission Ministry of Economic Affairs May 2004 Financing Renewable Energy Development in Chinese Taipei.
Conceptual Tools The creation of new and improved financial products through innovative design or repackaging of existing financial instruments. Financial.
$$ Entrepreneurial Finance, 4th Edition By Adelman and Marks PRENTICE HALL ©2007 by Pearson Education, Inc. Upper Saddle River, NJ Capital Budgeting.
Community Finance Partnerships Mick Brown Founder member, Robert Owen Credit Union Project Designer, Robert Owen CBP Manager, Robert Owen Community Banking.
Copyright ©2003 South-Western/Thomson Learning Chapter 11 The Cost of Capital.
INTRODUCTION A process of implementing and managing financial control systems, collecting financial data, analyzing financial reports, and making sound.
Feasibility Study.
MINING AND INFRASTRUCTURE INDABA 2015 ZPC PRESENTATION Presented by: N.F. Gwariro (MD)
Ayumi Konishi Director General, East Asia Department Asian Development Bank CCICED Annual General Meeting 2015 Forum G20 and Green Finance 11 November.
Private Sector Expectations towards NAMA Financing Latin America and Caribbean Regional NAMA Workshop 14 th September 2015.
Presentation to Select Committee on Economic Development
RECOMMENDATIONS ON IMPROVEMENT OF PUBLIC PROCUREMENT SYSTEM Experts: Bazakeeva Jyldyz Jamanchaevna Abdymomunona Saina Ryskeldievna Recommendations were.
Risks for Investment in Hydropower Sector in Nepal; Developers’ Perspective Power Summit 2008 Kathmandu, Nepal September 24th 2008 Presented by: Dr. Sandip.
SME Funding Winston Smit 24 November [Southern Africa/Forests] Slide 2 Key Strategic Drivers for SME in Forestry Sector  Forestry Sector BBBEE.
Army Directorate of Public Works Support Contractor of the Year Building a government contractor for the 21 st century By Carlos Garcia Owner and CEO KIRA.
1 SYMPOSIUM: U G A N D A A F T E R I D I A M I N A N D M I L T O N O B O T E Hamburg, Germany 29 th September 2008 INVESTMENT OPPORTUNITIES IN POWER GENERATION.
Social investment and the voluntary sector 7th October, 2014 Lucy Inmonger.
By: Robert Anderson Economic Feasibility Model for Biogas Facilities in Ontario.
Presented By: Budget & Research Department FY STATUS REPORT & THREE-YEAR FINANCIAL FORECAST SUMMARY (FY )
$$ Entrepreneurial Finance, 5th Edition Adelman and Marks PRENTICE HALL ©2010 by Pearson Education, Inc. Upper Saddle River, NJ Capital Budgeting.
Developments in our water sector policy
Water Services Training Group
Entrepreneurial Finance
Planning and implementation of Energy efficiency
Financials of Solar Water Pumping and Off-grid Power Plant Dr
Capital Budgeting Techniques (cntd.)
Chapter 11 Sources of Capital
How Small Developers and EPC Contractors Can Add PPA Financing to their Arsenals John Langhus, VP Business Development Midwest Solar Expo 2019 New Energy.
Summary from Africa and ASEAN assistance Dr. Peter Pembleton, UNIDO
Presentation transcript:

11th November 2007 by Eng. Martin O. Ogada Financing of Small-Scale Hydropower Projects & Risks Mitigation for Tea factories A Case for Unilever Tea Kenya Limited

UTKL HYDROPOWER STATIONS KERICHO TOWNSHIP DERBY HOUSE KIMUGU RIVER I.T.C. Drawn: F. Ouko Checked: M. Ogada Date: Nov 2007 CURRENT STATUS: - Present Hydro Capacity2050kW Kerenga420kW Tagabi 800kW Jamji740kW Chemosit 90kW CHEMOSIT HYDRO 0.09 MW KIPTIGET ITARE CHEPKOSIS KITOI JAMJI HYDRO 0.74 MW DIESEL 1.0 MW 4xHYDRO M/C 740 KW 30.5% OF POWER DEMAND AND DIESEL ENGINE 1200KW (STANDBY) 1xHYDRO M/C 90 KW 3.6% OF POWEER DEMAND 1xHYDRO M/C 800 KW 33% OF POWER DEMAND 2xHYDRO M/C 420 KW 16.5% OF POWER DEMAND SAOSA TAGABI HYDRO 0.8 MW KERENGA HYDRO 0.4 MW 5 KM FURROW 3 KM FURROW JAMJI DAM TAGABI DAM KERENGA DAM CHEMOSIT WEIR TOINSOIYET RIVER

TAGABI HYDRO & KIMARI GRID PROPOSAL

Financing Conditions - Unilever All Hydropower projects developed so far were in-house financed. Projects subjected to a financial appraisal & compete 4 funding Discounted Cash Flow (DCF) Method is used Internal Rate of Return (IRR) subjected to a sensitivity analysis, lowest rate that passes is 15% on constant terms. Inflation rate used set by Commercial Department The project is forwarded to functional director Functional Director tables the project appraisal to his colleagues Once approved, it is put in the company annual capital budget A capital proposal is raised which summarises the key objectives of the project, key benefits, highlighting any major risks & the proposed mitigating factors. SHEQ compliance top priority The project goes through an approval process with every approver observing his/her authority limit Project Team is formed for implementation

Video

Development Costs for Hydro 1989/1990 Vs Today Item1990 Cost Kshs. % of Total Estimate Today Kshs. Site Investigations258, ,035,000 Consultancy2,138, ,200,000 EIA & Licenses/PermitsNegligible0.0200,000 Weir3,863, ,220,000 5Km Furrow & Head pond13,617, ,550,000 Powerhouse Building705, ,300,000 Inlet Pipe (Penstock)1,320, ,834,000 3Km Furrow2,739, ,956,000 Turbine/Alternator9,307, ,000,000 Other Electrical Works (Power line)1,590, ,200,000 Total35,609, ,495,000 NB: Today: Kshs/kW – 143,000 (USD 2100) Civil works: 70%, Electromechanical:30%

DCF Results of 800KW Project Today 6% Inflation11% Inflation16% Inflation IRR Current20.4%24.0%27.3% IRR Constant14.3%13.8%13.4% Conclusion: This project will not qualify for financing in Unilever under normal circumstances Assumptions: Investment – Kshs. 114,495,000 Annual Units generated – 4,555,000 kWh Base Inflation rate – 11% Sensitivity Analysis to inflation done ±5% Average Hydro Cost – Kshs.1.56/kWh Average KPLC Cost – Kshs. 8.06

Project Risks/Pitfalls Cost overruns Poor forecasting of revenues (usually too optimistic) Exchange rate fluctuations Interest rate risk – inflation dependent Poor payment mechanism to contractors Poor cash inflow/outflow arrangement Increased water turbine wear rate due to silt Erratic weather patterns Force Majeure – earth quakes, fires & other unpredictable circumstances

Mitigating Risks in SHP Projects High quality Feasibility Studies Reduce cost of the project development – e.g. procurement Realistic revenue forecasts Government incentives (loans, PPA, guarantees, tax relief) Simplifying legislation procedures – permits/licenses/EIA Joint Developments of projects in one area to reduce costs – collective planning, procurement, negotiations, funding Keeping high quality water flow & rainfall data Use of expert advice from qualified consultants Establishment of advisory resource centres e.g. PMO Establish better sources of equity funding Insurance against natural disasters

Conclusion Local banking institutions need to take advantage of existing opportunities to finance the private sector in SHP development With high quality Feasibility study reports, SHP projects are not high risk projects and the Unilever case shows they are viable. Criteria within private companies may be too tight but it remains attractive to commercial banks. The Governments hold the key to removing many financing barriers to financing SHP projects by: - Introducing incentives (grants, equity capital) Reducing risk to developers & financiers (Govt guarantees, high quality stream flow data) Joint development ventures in one area to reduce development costs By education & resource centres to provide technical support during early stages of development

Thank you for your Attention Tel. (052) 20120/1 Fax. (052) 30103