… getting there … 112/02/2014A. Fabich, EN-MEF-LE.

Slides:



Advertisements
Similar presentations
Project Managers Update Roy Preece Particle Physics Department, STFC MICE Video Conference, 18 th September 2014.
Advertisements

DAQ&CM Infrastructure Paul Drumm. Issue Space is running out! Power supplies, RF system –Big kit, legislation dictates space requirements (not a clear.
G2p Safety Readiness Review January 17, 2012 Expected Radiation Exposure Levels from Activated Local Dump George Kharashvili, Radiation Control.
EMCal Meeting CERN – July 2 nd 2007 LPSC Status 1 J-F Muraz LPSC Status LPSC Status.  Assembly Hall. - Removal starts and is in progress. - Main infrastructure.
GLAST I&T January T Borden 1 Tracker EM Mechanical Mock-up T Borden I&T Tracker Mock-up.
LHCf 2015 Questions from LMC: – LHCf run scheduled shortly after initial commissioning – can it be delayed? – Present plan below. LHCf to removed at first.
Gas systems for GIF++ 14/02/2015 Ernesto Regaño 1.
Experimental Area Meeting V. Bobillier1 Good connection to earth (in many points) of every metallic parts to be installed in the cavern is very.
08/24/07Shutdown’07 Week 3 F.G. Garcia1 MTA beam line installation Weekly Report August 24, 2007 Period covered: August 17 th to August 24 th (Week 3)
GIF++ ACCESS SYSTEM Dorothea Pfeiffer GIF++ Project Meeting Thanks to: V. Martins De Sousa Dos Rios, D. Vaxelaire, D. Haasler.
Summary of Hg System Review at CERN Van Graves 13 Sep 2005.
FUNCTIONAL SPECIFICATION Dorothea Pfeiffer Dennis Haasler GIF++ User Meeting
CMS Muon Chambers Long term studies at GIF++ Andrey Marinov On Behalf of Long Term Studies of the CMS Muon Detectors 1.
09/28/07Shutdown’07 Week 8 F.G. Garcia1 MTA beam line installation Weekly Report September 28, 2007 Period covered: September 24 th September 28 th (Week.
July LEReC Review July 2014 Low Energy RHIC electron Cooling Al Pendzick LEReC Civil Construction.
Installation issues - update, July 2006A.Fabich1 MERIT installation: Update July 2006 A.Fabich CERN AB-ATB July 2006.
GIF in EHN1- layout, construction and schedule Adrian Fabich, EN-MEF-LE GIF users meeting, 12 th February 2014.
1 NSTX Outage - Plan 1. 2 NSTX Outage – Diagnostic considerations 2 1.Erik Perry will be the manager of the construction activities in the Test Cell.
AHCAL Mechanics status report Karsten Gadow CALICE Collaboration Meeting Argonne,
08/31/07Shutdown’07 Week 4 F.G. Garcia1 MTA beam line installation Weekly Report August 31, 2007 Period covered: August 24 th to August 31 st (Week 4)
Run 12: STAR Status and Schedule Update RHIC Coordination Meeting October 18, 2011 Bill Christie BNL Outline Status update Schedule update and issues Summary.
1st LTEX 22 June 2009D.LACARRERE1 Protection of UX85 EDMS No IP8 Current Status & Plans  UX85 Expt Area  RB84 (8-7 sector)  RB86 (8-1 sector)
EHN1 North Wall Dismantling Schedule Bastien Rae.
LHCb Experimental Area Meeting V. Bobillier1 Earth network in UX85 experimental cavern.
AWAKE E. Gschwendtner, EATM, 1 July Highlights Since April 2015 Cabling, piping and rack installation campaign for the AWAKE facility has started.
How 3D models and photos are organized in the database ADO-PO meetingTatiana KLIOUTCHNIKOVA.
NA YETS: schedule week by week S. Evrard.
HiRadMat – Users Meeting 6/2/2015 Adrian Fabich EuCARD-2 is co-funded by the partners and the European Commission under Capacities 7th Framework Programme,
K. Foraz & Perrot A. L., EN/MEF - R2E Project LMC 25th May 2011 Thanks to EN/EL, EN/HE, EN/MEF, equipment owners the LHC integration team & the R2E team.
L-band test stations in End Station B Richard Swent.
LS1 planning meeting /4/13 ALICE TBStatus of LS1 activities - A.Tauro2 LS1 plan 2013Weeks Remove plug, mobile shielding, open doors8-9 Prepare.
SBS Magnet and Infrastructure Status Robin Wines July 2015.
8/31/05DR Lynch1 HBD Preparations in the IR Don Lynch.
NSTX Upgrade Test Cell Initial Schedule Vent vacuum vessel by 9/19 No vessel entry at this time Period of removals prior to start of outage: 9/19 – 10/14.
09/07/07Shutdown’07 Week 5 F.G. Garcia1 MTA beam line installation Weekly Report September 07, 2007 Period covered: August 31 st to September 7 th (Week.
1 G. Aielli for the RPC community. General information  BOE to be delivered in September  Detector design is over  Production facility reviewd and.
MVD installation, fall 2004 Pads only:. Work done with IhnJea Choi MVD after successful installation Beam pipe is pushed to the center with a plastic.
Radiation Protection studies for the Linac4 / Linac2 interface Joachim Vollaire, DGS-RP 28/09/2015 Linac4 Coordination Meeting.
1 PS cabling status and planning Overview Rustem DZHELYADIN (CERN&IHEP, Protvino) PS-Cabling: what has been done : 1.PS/C top cable tray (3days)installed.
8/4/2015R. Guida PH-DT-DI1 Info 1)Air conditioning system Status: Adrian Fabich contacted CV and he is waiting for info. Today I’m going to meet experts.
1 Project Infrastructure for steps I-III Tim Hayler, STFC – RAL MICE Collaboration Meeting, RAL, nd October 2008.
EHN1 – EN/EL Progress update J. Devine G. Gross 11/02/16.
EHN1 – EN/EL Planning Lighting _ Containment_ Cabling J. Devine G. Gross 11/02/16.
MICE Project Progress Update Power Converters Rack housing MQ1 to MQ3 magnet power converters –Marshalling for all other quadrupole & dipole units –Houses.
Status of GIF++ Adrian Fabich, Dorothea Pfeiffer, EN-MEF-LE EATM, 27th August 2013.
Tuesday 9 th January Project Status Report Project Achievements Project Schedule Issues Finance Summary Risk Register Photos.
LHCb Week 27/11-01/ D.LACARRERE on behalf of Expt Area Team1 Experimental Area Latest News from IP8  Radiation Shield – Upper & Front Parts  Structures.
1 MICE PM Report Phase One installations to date Phase One remaining items Progress with Phase Two Worries Don’t have time for a detailed status report,
GIF++ implementation Adrian Fabich, Sylvain Girod, Dorothea Pfeiffer, EN-MEF-LE GIF++ 3rd users’ meeting, 11th July 2013.
GIF in EHN1 - Vision 112/02/2014A. Fabich, EN-MEF-LE.
GIF completion status Adrian Fabich, EN-MEF-LE on behalf of the GIF project team GIF users meeting, 14 th January 2015.
Two half-day seminars on the remaining work packages to complete the MEDICIS Facility POWER CONVERTERS FOR MEDICIS Davide Aguglia & Julien Parra-Lopez.
Operations meeting on FY07 Shutdown Date: June 27, W.B. Christie Outline Brief Overview of Shutdown Plan Details/discussion of next few weeks Comments.
GIF++ implementation Adrian Fabich, Sylvain Girod, EN-MEF-LE Technical meeting with Supplier of Irradiator, 3 rd October 2013.
Neutrino Platform Proximity Cryogenics 59th EHN1 Cryogenics Integration Redouan Abdennour, Johan Bremer, Michel Chalifour, Joaquim Creus, Aurelien Diaz,
H4 beam line for GIF Adrian Fabich, EN-EA-LE GIF users meeting, 17 th February 2016.
NA61/SHINE run schedule/plans:
The Next Generation of a Gamma Irradiation Facility GIF++
Neutrino Platform Proximity Cryogenics 72th EHN1 Cryogenics Integration TE-CRG
Identification of the unused cables
Francois and Lau EATM 17 July 2012
EHN1 Extension North Side wall (Removal of Existing services & platforms) Michael Jeckel & Bastien Rae.
CE Status: Activities executed until 03/08 and ongoing
SPS Planning for the EYETS Meeting 8 (07/12/2016)
2016.
Experimental Areas – LS2 planning
EHN1 visiting point at the Open Days September 2019 EDMS:
Polarized 3He target installation
Cryogenic upgrade of B163, B165 & B253 Status Meeting 19th December 2018
Linac4 Connection Broken Line 07/08/19
Presentation transcript:

… getting there … 112/02/2014A. Fabich, EN-MEF-LE

GIF today 212/02/2014A. Fabich, EN-MEF-LE False floor Cable trays Service area illumination

Schedule 3  EN/EL installation until mid September  Irradiator delivery mid September  Irradiator Site-Acceptance-Test at end September  Limited access to EHN1 during few periods of couple of hours  Commissioning with beam in December 12/02/2014A. Fabich, EN-MEF-LE

PPE152 shielding 413/5/2014A. Fabich Central passage NA61 target beam

Modifications on the Jura side 512/02/2014A. Fabich, EN-MEF-LE

PPE152 works 6  August – completed:  Disconnecting NA61 racks, cables and piping  Removal of gang way and (unnecessary) beam line blocks  First layer of blocks installed  Minor actions from September until end of the year  NA61 commissioning  Completing installation in December/January  See EDMS for details 12/02/2014A. Fabich, EN-MEF-LE