Two half-day seminars on the remaining work packages to complete the MEDICIS Facility POWER CONVERTERS FOR MEDICIS Davide Aguglia & Julien Parra-Lopez.

Slides:



Advertisements
Similar presentations
ALICE © | RRB | 17 April 2013 | Catherine Decosse 24 th meeting of the ALICE Resources Review Board CERN-RRB
Advertisements

AB-PO-PH 2005 Pulsed and High voltage converters Responsibilities: PS complex exploitation, active maintenance (documentation, improvement, spare), follow-up.
Industry information day INDUSTRY INFORMATION DAY Assembly & Installation Laurent Schmieder Buildings Infrastructure and Power Supplies Project.
Technical studies for the HIE- ISOLDE Frontend upgrade Jacobo Montaño Marie Curie Fellow; CATHI Project * The research project has been supported by a.
31.March.2004 C. A. Martins, CERN AB/PO 1 Analysis of the possibility of using of a ALICE/LHCb type power converter in TT2A target test by Carlos DE ALMEIDA.
Consolidation program SPS Main Power Converters (Dipole & Quadrupole) K. Kahle / Q. King / G. Le Godec (TE-EPC) IEFC Workshop, 9 March 2012.
Accelerator Complex Controls Renovation, LHC Excluded Purpose and Scope M.Vanden Eynden on behalf of the AB/CO Group.
TE/MPE/EE J. Mourao T/MPE/EE 1 November 2012 LHC Machine Local protection Redundant Power supply (DQLPUR) - Review.
HIE-ISOLDE (High Intensity and Energy) project Protection of superconducting solenoids MPE work shop – December 14, 2010 G.J. Coelingh TE-MPE-CP.
HIE-ISOLDE Design Study and the CATHI Project Richard Catherall EN-STI ISOLDE Technical Coordinator HIE-EBIS Workshop 16 th -17 th October CERN.
Impact on Project Planning and Cost. Agenda CERN Project Budget Planning Summary E. Gschwendtner, 9 April
Consolidation of access systems for the injector Complex ATOP days 4-6 March 2009 P. Ninin & R, Nunes in behalf of the PS and SPS access project teams…
112/09/2013. Summary  Events on the network  Incidents  Network reconfigurations  Network operation  Update on activities  Tests  Projects and.
17.March.2005 C. A. Martins, CERN AB/PO 1 Power converter for the TT2 mercury target project by Carlos DE ALMEIDA MARTINS (AB/PO)
Accelerator Consolidation Workshop TE/EPC consolidation plan 2 Jean-Paul Burnet ACC consolidation day, 12/09/2013.
18-20 December rd ATF2 Meeting, KEK ATF2 Power Supplies1 ATF2 High Availability DC Magnet Power Supplies By Paul Bellomo, Antonio de Lira, David.
Electrical Integration CM38 Steve Griffiths & Ian Mullacrane.
HINS 6-Cavity Test 3 Month Plan Jan 12, Current Schedule 2-3 day shutdown scheduled to start Jan 18 (Wednesday) to upgrade BPM system and reinstall.
Bulding 245 schedule update LIU Booster Meeting Fulvio Boattini & Michel Obrecht TE-EPC / EN-CV TEEPC.
TE/MPE/EE J. Mourao T/MPE/EE 1 November 2012 LHC Machine Local protection Redundant Power supply (DQLPUR) & interface Module (DQLIM) progress status.
Consolidation and Upgrade of the SPS Electrical Networks Current Status JP. Sferruzza, on behalf of EN/EL.
1 MICE Hall and Infrastructure - Progress since CM18 Chris Nelson MICE CM19 Oct 2007.
2 Davide Aguglia TE-EPC-FPC Sept. 23 rd rd PSB injection EPC powering rack space coordination meeting Stripping foil chicane BSW magnets powering.
Work Effort in the LHC Injector Complex for the Upgrade Scenarios B. Mikulec Thanks to all the valuable input from the LIU project leaders and LIU work-
LIU-ABT systems: SPS B.Balhan, J.Borburgh, H.Day 20 th November 2015.
ISOLDE Activities for LS2 Richard Catherall EN-STI ISOLDE Technical Coordinator.
K. Foraz & Perrot A. L., EN/MEF - R2E Project LMC 25th May 2011 Thanks to EN/EL, EN/HE, EN/MEF, equipment owners the LHC integration team & the R2E team.
BI.DIS10: Magnets & generators R. Rosol, L. Sermeus, T. Stadlbauer, TE-ABT LIU review, 20 November
Technology Department 1 ELENA Fast Deflectors status Nicolas Voumard, Jan Schipper TE/ABT/EC TCM 17/11/2015 1/11.
1 S-FRS Magnet Test Bench SuperFRS Magnet Test Bench Power Converter Status H. Thiesen 13 May 2015.
MERIT review, Dec. 2005CERN AB-ATB1 CERN installation I. Efthymiopoulos, A. Fabich, J. Lettry CERN AB-ATB MERIT review, Dec.
Serge Pittet (Work-Package holder) Konstantinos Papastergiou (Work-unit: Sirius converters) CERN Technology Department | Electrical Power Converters 12.
CLIC Permanent Magnet Quadrupole Engineering Development update Norbert Collomb, STFC Daresbury Laboratory 1N. Collomb 03/10/2011.
VAC – CTRL SYS internal meeting, 14 Dec A list of topics Start of the disassembly works: mid Jan. At first the W arm shall be off- service, then.
ELENA KICKERS AND SEPTA ELENA Meeting, Prepared by J. Borburgh, E. Carlier, A. Fowler, L. Sermeus TE/ABT.
Each converter 3 racks (fighting for 2?) Access from front and rear of each rack! 56 racks total + 6 racks Ethernet/control Existing RF equipment to be.
LINAC3 UPGRADE Source and LEBT modifications for YETS and recommissioning timetable 28/10/2015 Ville Toivanen.
LIU EL-FC ACTIVITIES Georgi Minchev Georgiev EN-EL-FC EDMS
February 4 th, Quality assurance plan: production, installation and commissioning N.Vauthier TE-CRG Technical Review on Beam Screen Heater Electronics.
Linac4 BCC 14/10/2010 Linac4 Measurement and Dump Lines BCC on the Linac4 Transfer Line Status.
LIU-PSB Working Group meeting: 25/06/2015, Markus Zerlauth Consolidation of magnet interlocks in the PS complex – Warm magnet Interlock System (WIC) R.Mompo,
Electrical Group Inputs for LIU-Ions J. Devine, on behalf of EN/EL.
Cost and schedule for ELENA Beam Transfer Systems W. Bartmann, J. Borburgh, E. Carlier, L. Ducimetiere, T. Fowler, M. Hourican, R. Ostojic, L. Sermeus.
ELENA installation progress F. Butin / ELENA collaboration.
The HiLumi LHC Design Study is included in the High Luminosity LHC project and is partly funded by the European Commission within the Framework Programme.
S A Griffiths CM42 June 2015 Electrical & Control.
Report Technical Director Storage-Ring-Installation Completed
Magnet activities in SPS during EYETS
TE-EPC internal review of the ELENA project
Target & Frontend Switch Yard & Collection Boxes Medicis Seminar, 2nd and 3rd March 2016 Stefano Marzari EN-STI & Vincent Barozier EN-ACE.
Cabling for LHCb Upgrade
CLIC Civil Engineering & Infrastructure Working Group Meeting
Brief Status SPS Prototype PSB Prototype Installed in LS1
ELENA installation and commissioning status
LIU Wire Scanner Milestones June 2017
LIU – EVM status and next steps
AD consolidation activities in LS2
EC Activities Status for the LIU
BE/RF-IS Contribution to LIU C. Rossi and M. Paoluzzi
The ELENA Safety Documentation «time to prepare the safety clearance»
News from Projects Lau Gatignon / EN-EA Input from F.Butin, Q.Bouirek
Additional ancillaries for the operation of the Hollow Electron Lens
TE/EPC activities for LINAC 2, PSB, PS & TT2 during EYETS
352MHz Klystron Control for the 3MeV Linac test stand
Renovation of the 45-year old PS magnets
Update on the Ethernet Network Installation Campaign
TE-MSC activities in SPS during YETS
MEDICIS Facility Isotope Separator Controls and HMI
Safety Readiness Review (SRR) Thomas Hansson, ESH
East Hall under construction
Presentation transcript:

Two half-day seminars on the remaining work packages to complete the MEDICIS Facility POWER CONVERTERS FOR MEDICIS Davide Aguglia & Julien Parra-Lopez on behalf of TE/EPC 2 March TE/EPC Power converters for MEDICIS

Outline TE/EPC Power converters for MEDICIS Equipment overview Items not included within TE/EPC Cost estimate Resources Schedule Conclusion

Equipment overview TE/EPC Power converters for MEDICIS Today total of: 23 power converters with control systems + 9 in option 1 isolation transformer + MCB

TE/EPC Power converters for MEDICIS 60kV platform for power converters Powered by Isolated 400VAC transformer Insulated cable tray Equipment overview Example of similar/smaller installation in ISOLDE OFFLINE 60kV Isolation 400VAC transformer

TE/EPC Power converters for MEDICIS Equipment overview Items to be delivered by TE/EPC – Target & ion source ItemI [A]V [V]Reg. in: StabilityReference/setting resolution Target Heating120015Current1x10 -3 – 0.1% 3.1x10 -3 – 0.31% Proposed by EPC High end for EPC necessary? Line Heating60010Current1x10 -3 – 0.1% Ion Source 15300Voltage1x10 -4 – 0.01% Ion Source 25300Voltage1x10 -4 – 0.01% Mass Marker Current1x10 -3 – 0.1% Mass Marker Current1x10 -3 – 0.1% Magnet Target1024Current1x10 -3 – 0.1% Pre-extraction0.04+/-3500Voltage1x10 -4 – 0.01% Extraction0.002+/-60000Voltage1x10 -4 – 0.01% All power converters are DC!

TE/EPC Power converters for MEDICIS Equipment overview Items to be delivered by TE/EPC – Beam line ItemI [A]V [V]Reg. in:StabilityReference/setting resolution H deflector Voltage 1x10 -4 – 0.01% 3.1x10 -3 – 0.31% Proposed by EPC High end for EPC necessary? H deflector H deflector H deflector V deflector V deflector V deflector V deflector Einzel lens All power converters are DC!

TE/EPC Power converters for MEDICIS Equipment overview Items to be delivered by TE/EPC – Options added 2 days ago! ItemI [A]V [V]Reg. in:StabilityReference/setting resolution H deflector Voltage 1x10 -4 – 0.01% 3.1x10 -3 – 0.31% Proposed by EPC High end for EPC necessary? H deflector H deflector H deflector V deflector V deflector V deflector V deflector Einzel lens All power converters are DC!

TE/EPC Power converters for MEDICIS Equipment overview Items to be delivered by TE/EPC – Other grounded items ItemI [A]V [V]Reg. in:StabilityReference/setting resolution Double focusing 140?40?Current 100ppm? (FGC3)TBD Switchyard left Voltage 1x10 -4 – 0.01% 3.1x10 -3 – 0.31% Proposed by EPC High end for EPC necessary? Switchyard left Voltage 1x10 -4 – 0.01% Switchyard right Voltage 1x10 -4 – 0.01% Switchyard right Voltage 1x10 -4 – 0.01% Insulating transformer 75/75400/ MCB32400 AC - -- All power converters are DC! Other Deliverables Complete control system from converters to FEC (included) Tests, installation, commissioning, operation & maintenance

TE/EPC Power converters for MEDICIS Remote control concept Equipment overview Depending on precision specs

TE/EPC Power converters for MEDICIS Items not included within TE/EPC Power network 400VAC distribution → EN/EL DC cabling on earth side → EN/EL Vacuum and cooling Interlocks distribution → EN/STI Mechanical design & manufacturing of HV Platform → EN/STI

TE/EPC Power converters for MEDICIS Cost Estimate DesignationQuantityPrice (kCHF)Remark Target Heating120 Line Heating114 Ions source25 Mass marker210 Magnet target15 Pre-extraction112 Extraction118 Deflectors816 Einzel lens115 Magnet separator130Included FGC3 Switchyard415 Insulated transformer130Included MCB PLC control150Interfaces and controller Front-end computer220 Depending on precision specs

TE/EPC Power converters for MEDICIS Cost Estimate DesignationQuantityPrice (kCHF) Power converter summary23~190 Control devices & infrastructure23~70 Installation (included Manpower)-~60 If options included9~50 TOTAL (with FGC3 for magnet)~370 TOTAL (without FGC3 for magnet)~350 This is a preliminary estimation, request to EPC still not final Once power converters functional specification approved (prepared by TE/EPC), the final cost estimation can be released

TE/EPC Power converters for MEDICIS Resources (FTEs) unitItemFTE EFTE C TE/EPC/FPCDesign, purchasing, tests, etc TE/EPC/LPCMagnet converter (separator) TE/EPC/HPMCalibration/performances-0.1 TE/EPC/CCSControl PLC+FGC30.3- Total ~1.3 FTEs. FTEs not foreseen in 2016!

TE/EPC Power converters for MEDICIS Schedule Ideal schedule if all FTEs were available Activity or milestoneDate Request from EN/STI clarifiedMar (end) EPC project mandate signed (EDMS approval)Mar (end) EPC functional spec. (EDMS approval)Apr Budget code obtainedApr Purchasing's + production + qualificationFeb x DOs>50kCHF prep. + contract placedJun Converters delivered to CERN: >4 monthsNov PLC, rack assembly, Distrib. ChassisDec Installation: 6 weeksFeb (end) EPC ready for commissioningMar. 2017

TE/EPC Power converters for MEDICIS Schedule Considering projects priorities within EPC (LIU in primis with EYETS works) Making an effort and providing FTEs in 2016 to launch orders Here is a realistic and still tight schedule for EPC: MarAprMayJunJulAugSepOctNovDecJanFebMarAprMayJun EN/STI Request clarification EPC projetc mandate signed EPC func. Spec. Approved Budget code obtained Purchasings -Conv. DOs preparation -Conv. contracts placed -Conv. Delivered -Conv. Tested -Chassis ready Installation EPC ready for commissioning EYETS reminder

Conclusion TE/EPC Power converters for MEDICIS Complete draft request received Feb Detailed request still to be finalised Since then EPC: Is preparing a detailed functional spec. Discussed (group level) priorities for 2016 Proposed schedule already impacts 2016 EPC objectives Earliest date for project completion is June 2017 Reminder: delivery date ≡ EPC Func. Spec. signed + 13 months!

Thank you very much! 18