UK Project Plan (Finance & Risk) Alan Grant STFC DL RLSR 5 th April 2016.

Slides:



Advertisements
Similar presentations
1 UK Project Alan Grant, STFC. Finance How savings are made Update on stepIV position Milestones Critical Path - stepIV Concerns 2.
Advertisements

Project Managers Update Roy Preece Particle Physics Department, STFC MICE Video Conference, 18 th September 2014.
MICE Superconducting Solenoids: Status and Update RAL: T W Bradshaw M Courthold J Rochford M Hills D Baynham Oxford: J Cobb W Lau S Yang MICE.
1 MICE PM Report General Update –Phase I civil engineering –R5.2 in June –Phase II design work –Phase II hardware –A few questions –Schedule, milestones.
Project Plan The Development Plan The project plan is one of the first formal documents produced by the project team. It describes  How the project will.
1 Implications Of Infrastructure Build The Infrastructure Project is bigger than anyone thought, but now it’s understood The cost was underestimated, but.
Update Hardware for conductive cooling of the quench resistors has been fabricated at LBNL. Preparation for installation to start this week. Installation.
Project Managers Report Video Conference 172 Roy Preece 11 th December 2014.
Alan Grant OsC 30/4/ UK Project Finance & Schedule.
1 BROOKHAVEN SCIENCE ASSOCIATES Project Performance & Risk Management Aesook Byon, Deputy Project Director NSLS-II PAC Meeting February 8-9, 2011.
1 UK PM Report Costs & Schedule Alan Grant, STFC.
Project manager report paul drumm CM16 October 2006.
U.S. MICE Schedule, Cost, & Risks Peter H. Garbincius Mark Palmer, Alan Bross, Rich Krull Fermilab Presented at RAL – November 13, 2013.
1 MICE CM28 PM Report Progress since CM27 Schedule, dates, milestones Electrical substation Visiting RAL Andy Nichols, STFC 4 th October 2010.
RSLR mtg 28/3/2014 RLSR mtg Alan Grant. 2 RLSR mtg 28/3/ MICE Finances - Forward Look.
The status of the construction of MICE Step IV K. Long, on behalf of the MICE collaboration.
Electrical Integration CM38 Steve Griffiths & Ian Mullacrane.
Schedule and Work We are moving into a very intensive 4 months with a lot of work to be carried out Electrical services to the devices – after the South.
January LEReC Review 12 – 13 January 2015 Low Energy RHIC electron Cooling Kerry Mirabella Cost, Schedule, Personnel.
Status of the MICE Project & Dashboard MICE Project Board 14 th November 2013 Roy Preece.
Hydrogen Delivery System Schedule MICE Schedule Review 23 rd -25 th May 2011 M Hills STFC.
U.S. Muon Accelerator Program: MICE Milestones & Resource-Loaded Schedule M. A. Palmer, Director October 31, 2012.
Spectrometer Solenoid Fabrication & Testing Update Steve Virostek Lawrence Berkeley National Lab MICE CM25 at RAL November 6, 2009.
RLSR 16/4/2015 UK Financial Plan & Risks. Content Finances – Cost to Completion Risks – Top level to completion – R9 working space – Summary 2 RLSR 24/11/2014.
MICE FAC Alain Blondel 21 september   MICE The International Muon Ionization Cooling Experiment BRIEF STATUS OF MICE.
January LEReC Review 12 – 13 January 2015 Low Energy RHIC electron Cooling Kerry Mirabella Cost, Schedule, Personnel.
Project Managers Report CM40 Collaboration Board – Rome Roy Preece 28 th October 2014.
MPB 31 October 2012 and FAC 15 November monitor how well we are doing in assembling step IV ! -- should deliver a ‘realsitic schedule scenario’
MICE Oversight Committee Meeting RAL, 24 April 2014 Paul Soler on behalf of the MICE Collaboration Status of MICE and Spectrometer Solenoids.
MICE Project Report Alan Bross (for Paul Drumm). Project Issues ● Key dates: – ISIS Synchrotron start-up scheduled for 1st August ● Shielded area around.
US Project Plan for MICE Mark Palmer Peter Garbincius, Alan Bross, Rich Krull Fermilab November 24, 2014.
OsC mtg 24/4/2014 OsC mtg Alan Grant. 2 OsC mtg 24/4/ MICE Finances - Forward Look.
1 UK PM Report Costs & Schedule Alan Grant, STFC.
MICE CM20 Alain Blondel 10 February The International Muon Ionization Cooling Experiment MICE CM20 Spokesmouse remarks.
Status of the MICE Construction Project Resource Loaded Schedule Review 29 th April 2014 Roy Preece.
OsC mtg 15/10/2014 MICE Step IV Alan Grant. Content Step IV – Construction Status – Finances – Schedule – Risks – Summary 2.
Finance Roy Preece STFC RAL Oversight Committee Meeting 27 th November 2015.
1 MICE RLSR Summary of Issues Relating to Question One of Review charge ‘ Given a resource-limited, year-by-year schedule for the project, how reasonable.
MICE – UK Plan Roy Preece STFC RAL DOE Review of MAP Brookhaven National Laboratory 13 th August 2014.
1 UK Project Roy Preece – STFC Alan Grant, STFC. Finance Staffing Update on stepIV position Milestones Critical Path – stepIV Magnetic field mitigation.
RLSR 16/4/2015 UK Financial Plan & Risks. Content Finances – FY 2014/15 – Cost to Completion Risks – Top level to completion – R9 working space – Summary.
PSAG mtg 3/2/2014 PSAG mtg Alan Grant. 2 PSAG mtg 3/2/ MICE Finances FY 2013/14.
US Project Plan for MICE Peter H. Garbincius, Mark Palmer, Alan Bross, Rich Krull Fermilab April 5, 2016.
The MAP 3-Year Plan Mark Palmer Fermilab September 26, 2014.
US Construction Project: SSs, PRY, Cavities and test program 1.
Schedule to completion, Risk and Critical Interfaces Roy Preece STFC RAL RLSR 16 th April 2015.
Schedule and Milestones Roy Preece STFC RAL FAC 17 th April 2015.
1 UK Project Finance & Schedule. Overview Finance  Budget Setting 2013/14  June Finance  Forward look to complete stepVI Schedule  Overview 2.
DOE Mini-Review Summary and Management Updates Mark Palmer Fermilab March 15, 2013.
MICE Spectrometer Solenoids Step IV running. MICE Spectrometer Solenoids Remember: Both magnets met the full specification at the vendor and were fully.
Schedule and Milestones Colin Whyte STFC RAL Resource Loaded Schedule Review 5 th April 2016.
US Project Plan for MICE Peter H. Garbincius, Mark Palmer, Alan Bross, Rich Krull Fermilab April 16, 2015.
UK Project Plan Roy Preece STFC RAL RLSR 26 th October 2015.
MICE Spectrometer Solenoids Step IV running
Project Managers Report CM38 – Napa Roy Preece 24th February 2014.
Step IV Step IV extended through 2016 QP/QD – in progress at FNAL Target dates SSU ECE for Feb now only 20% probability – no-field Feb Remainder for April/March.
Reported by Ron Prwivo for Ian Robson. Overview Response to Recommendations from the RLSR of November 2014 – very good, RF staffing remains an issue Very.
ESS Program Plan and Schedule Update
Muon Ionisation Cooling Experiment Overview
Resource Loaded Schedule and Budget Profile
Status of the MICE Construction Project
HFT Overview Flemming Videbæk BNL 3/14/12 F2F LBNL.
UK Financial Plan & Risks
MICE CM31 Schedule summary
MICE Project in the US: Completion of Efforts
Completing the Step IV Programme
<Location> – <Project Name>, Sponsor: <name>
Proposed Strategic Planning Process for FY 2013/14 thru FY 2015/16
Conventional Facilities
SNS-PPU upgrades the existing accelerator structure
Presentation transcript:

UK Project Plan (Finance & Risk) Alan Grant STFC DL RLSR 5 th April 2016

Cost to Complete 2 Full Cost Flat Cash +10% Flat Cash OsC requests Risk Summary Overview 2 Alan Grant

Cost to Complete DoIC – Full Cost 3 Key Dates:- Step IV running till end Dec 16 SSD delivery Jan 18 DoIC installation complete mid Feb 18 Commissioning Complete End July 18 Data Taking from End July 18 to Jun 19 Analysis ends end Mar 2020 Includes University costs & resource charges Budget £3,050M IN ALL CASES!! Costs do not include US FTE’s for commissioning for SS’s Costs do not include US FTE’s for commissioning for RF systems 3 Alan Grant

Cost to Complete DoIC – Full Cost – Critical Path 4 SSD delivery Jan 2018 is on the critical path Assumes full working SSD ready to be installed All magnet testing to be carried out at contractors 4 Alan Grant

Cost to Complete DoIC – Flat Cash + 10% 5 Assumptions:- Complete RF system#2 build and test at DL and deliver to RAL mid July 17. Push back installation of RF system#2 until April 18 – effort saving!! Only test RF system #2 into dummy loads. Do not carry out HPRF tests on the cooling channel for cavity#1 using RF system#2. This set of tasks which takes approx. 1mth but may not be necessary. Small risk to project. Key Dates:- Step IV running till end Dec 16 SSD delivery Jan 18 DoIC installation complete mid Jun 18 – 4 mth slippage Commissioning Complete early Dec 18 Data Taking from early Dec 18 to mid Oct 19 Analysis ends early August 2020 Length of duration time for Commissioning & Data taking remains the same 5 Alan Grant

Cost to Complete DoIC – Flat Cash + 10% – Critical Path 6 RF system#2 on the critical path Installation in MICE Hall begins 2/4/18 6 Alan Grant

Cost to Complete DoIC – Flat Cash 7 Assumptions:- Continue running step IV until end Dec 17 (12mth delay) – allows to redistribute effort and capital spending into latter yrs across work packages. Only test RF stem #2 into dummy loads. Do not carry out HPRF tests on the cooling channel for cavity#1 using RF system#2. This set of tasks which takes approx. 1mth but not really necessary. Key Dates:- Step IV running till end Dec 17 SSD delivery Jan 18 DoIC installation complete mid Aug 18 Commissioning Complete early Feb 19 Data Taking from early Feb 19 to mid Dec 19 Analysis ends early Oct 2020 Length of duration time for Commissioning & Data taking remains the same 7 Alan Grant

Cost to Complete DoIC – Flat Cash – Critical Path 8 Critical Path runs from end of stepIV operations, beginning with de-comissioning May need SSD before end of Dec 2017 to carry out repair work if this is the chosen path. 8 Alan Grant

OsC mtg 21 st March 9 requested - to look at further cost reductions may involve restructuring to deliver meaningful experiment also to understand cost savings if we stop at stepIV 9 Alan Grant

Risk 10 Alan Grant

UK Risks 11 New Risk Added Failure of Upstream Spectrometer Solenoid Magnet Failure of M2 in SSU. Failure of Helium space feedthrough in SSU. Cannot agree program and budget SSD delivery on schedule, quality & cost After mitigation 11 Alan Grant

UK Top Level Risks 12 UK risk level 12 and above Baseline set 2015 US risk level 12 and below 12 Alan Grant

Summary 13 Further work being carried in preparation for the upcoming Cost to Completion review. 13 Alan Grant

14 Allocation and required figures include risk mitigation costs for equipment and staff The 2018/19 FY request is for data analysis, paper writing …. And does include a fraction of Technical and Engineering support in the event of further operations and data taking. Phase 3 costs based on Flat Cash figures Required allocation for Phase 3 - £11,977k Total UK spend for MICE £46,726k Summary 14 Alan Grant