Ken McIntyre VP Grid Planning and Operations Dan Woodfin Director, System Operations Warren Lasher Director, System Planning Planning and Operations Overview.

Slides:



Advertisements
Similar presentations
Briefing on California ISO Dynamic Transfers Stakeholder Process For WECC Seams Issues Subcommittee Meeting May 4, 2010 Jim Price, Lead Engineering Specialist.
Advertisements

Demand Response: The Challenges of Integration in a Total Resource Plan Demand Response: The Challenges of Integration in a Total Resource Plan Howard.
1 Regulatory Developments and Impacts Involving Electricity Storage in Texas Elizabeth Drews 31 st USAEE/IAEE North American Conference Austin TX, November.
Resource Adequacy in PJM
NARUC-FERC Demand Response Collaborative Meeting NARUC Fall Meeting Anaheim, CA T. Graham Edwards President & CEO November 11, 2007.
MISO’s Midwest Market Initiative APEX Ron McNamara October 31, 2005.
Understanding Ontario’s Electricity System
Susan Covino Senior Consultant, Emerging Markets March 31, 2015
Utility Regulation March 10, 2011 Raj Addepalli Deputy Director, Electric, Office of Electric,Gas and Water New York State Department of Public Service.
Overview of LMP Markets Features of ISOs / RTOs David Withrow Senior Market Economist Fall 2007 Meeting of the NARUC Staff Subcommittee on Accounting and.
North American Electricity Markets APEX Paris, France October 15-16, 2007 Kenneth Laughlin, PJM.
1 The Effects of Integrating Wind Power on Transmission System Planning, Reliability, and Operations Phase 1 Preliminary Overall Reliability Assessment.
Demand Response in MISO Markets NASUCA Panel on DR November 12, 2012.
RenewElec October 21, 2010 Robert Nordhaus, David Yaffe Van Ness Feldman 1050 Thomas Jefferson Street, NW Washington, DC (202) FERC’s.
Joel Koepke, P.E. ERCOT Operations Support Engineer ERCOT Experiences During Summer 2011.
Costs of Ancillary Services & Congestion Management Fedor Opadchiy Deputy Chairman of the Board.
1 Transmission Development at Ameren and in the Midwest ISO Mid-America Regulatory Conference Maureen A. Borkowski June 8, 2010.
Intermittent Resources and Demand Response Integration 2007–2016 Long-Term Reliability Assessment Workshop Bill Bojorquez VP, System Planning August 16,
An Overview of the Australian National Electricity Market Brian Spalding Chief Operating Officer.
PJM © PJM Overview ARIPPA Valley Forge, PA November 8, 2007.
Warren Lasher Director, System Planning October 4, 2014 Our Energy Future.
Welcome New York Independent System Operator. (Pre-NYISO) Regulated Market Physical contracts Regulated industry Cost Based System Two Party Deals Bundled.
Overview of the North American and Canadian Markets 2008 APEX Conference in Sydney, Australia October 13, 2008 Hung-po Chao Director, Market Strategy and.
1 Renewable Technology Working Group (RTWG) July 14, 2009 Henry Durrwachter.
10/03/ Report on Existing and Potential Electric System Constraints and Needs Within the ERCOT Region October 3, 2002.
FERC Assessment of Demand Response & Advanced Metering 2006 APPA Business & Financial Conference September 18, 2006 – Session 11 (PMA) Presented by: Larry.
April 16, 2010 RPG Meeting ERCOT Five-Year Transmission Plan Update Jeff Billo.
OSC Meeting April 27, Transmission Cost Allocation Overview.
1 Capacity Markets Investment in Generation Capacity Payments October 31, 2005 J. W. Charlton.
Texas Wind Energy American Meteorological Society Summer Community Meeting – Norman Oklahoma Henry Durrwachter, P.E. August 12, 2009.
“Demand Response: Completing the Link Between Wholesale and Retail Pricing” Paul Crumrine Director, Regulatory Strategies & Services Institute for Regulatory.
Demand Response Workshop September 15, Definitions are important Demand response –“Changes in electricity usage by end-use customers from their.
Economic Planning – Theory and Current Practice Dan Woodfin Director, System Planning Joint PLWG/CMWG Meeting 2/4/2011.
Presentation to House Regulated Industries Committee Chairman Phil King Trip Doggett Chief Operating Officer The Electric Reliability Council of Texas.
PJM© Demand Response in PJM 2009 NASUCA Mid-Year Meeting June 30, 2009 Boston, MA Panel: Price Responsive Demand – A Long-Term Bargain.
©2005 PJM 1 APEx The Mature PJM Market Kenneth W. Laughlin PJM October 31, 2005 Orlando, FL.
IWWG Annual Conference Wind Management at MISO July 22, 2011.
Electric Reliability Council of Texas (ERCOT) A Success Story… In Progress Ingmar Sterzing United States Association of Energy Economics (USAEE) Pittsburgh.
May 11, 2012 RPG meeting YTP Scope and Process – RPG Comments.
SPP.org 1. Status Update for Reliability and Economic Assessments Stakeholder Meeting September 16, 2008 Austin, TX.
Integrating Wind Energy Capabilities of Wind Power Plants Mark Ahlstrom Wind Energy: A Good Citizen of the Electric Grid Four Corners Wind Resource Center.
2003 State of the Market Report ERCOT Wholesale Electricity Markets.
Floyd Trefny, P.E. Director of Wholesale Market Design Nodal Market Tools to Manage Wind Generation January 29, 2009 Presentation to the Renewables Technology.
ERCOT TAC11/2/ CREZ Study Update ERCOT TAC 11/2/2006.
TRANSMISSION CONSTRAINTS KENNETH A. DONOHOO, P.E. Manager of System Planning, Technical Operations
©2003 PJM North American Markets Status APEx Seoul, Korea October 29-31, 2006 Kenneth W. Laughlin.
Long Term Study Transmission Results May 21 st, 2013.
ERCOT Public 1 Project Panel 1 Dan Woodfin Director, System Operations August 15, 2014.
3/28/2008 RPG CREZ Meeting CREZ Transmission Optimization (CTO) Study And The Oscar Goes To… Warren Lasher Manager, System Assessment.
Oncor Transmission Service Provider Kenneth A. Donohoo Director – System Planning, Distribution and Transmission Oncor Electric Delivery Co LLC
Capacity, Demand and Reserves Report Bill Bojorquez May 4, 2007.
ERCOT Monthly Operational Overview (January 2015) ERCOT Public February 15, 2015.
Capacity, Demand and Reserves Report Bill Bojorquez Board of Directors Meeting May 16, 2007.
ERCOT Transmission Planning Process Overview and Recommendations November 6, 2002.
August 24, 2007 ERCOT Regional Planning Group Meeting CREZ Transmission Optimization Study Warren Lasher System Assessment.
07/27/2006 Overview of Replacement Reserve Procurement ERCOT Staff PRS RPRS Task Force.
03/06/2008 TAC CREZ Transmission Optimization (CTO) Study Update Dan Woodfin Director, System Planning.
4/16/2010 Regional Planning Group Meeting Long-Term Planning Study of the ERCOT Interconnection Warren Lasher Manager, System Assessment.
Texas Nodal Program ERCOT Readiness & Transition (ERT) Supplemental Information TPTF January 12, 2009 Kevin Frankeny.
The Midwest ISO – Platform to Meet Tomorrow’s Challenges Wisconsin Industrial Energy Group August 7, 2008.
Transmission Planning in ERCOT- Overview
Wind Management at MISO
Asia-Pacific Energy Regulatory Forum
Appeal of PRS Rejection of NPRR 667
ERCOT – Southern Cross Transmission ROS/WMS Working Group Assignments
The New Texas Wholesale/Retail Market
EU-IPA12/CS02 Development of the Renewable Energy Sector
31st USAEE/IAEE North American Conference
Sandip Sharma ERCOT Manager, Operations Planning
Forecasting and Operations CAISO Case
Presentation transcript:

Ken McIntyre VP Grid Planning and Operations Dan Woodfin Director, System Operations Warren Lasher Director, System Planning Planning and Operations Overview April 23, 2014 AMDEE/ERCOT

The ERCOT Region The interconnected electrical system serving most of the state of Texas, which has only Direct Current (DC) limited interconnections to the rest of North America 85% of Texas load 68,294 MW peak demand (set August 3, 2011) More than 40,000 miles of transmission lines 2 DC ties with eastern United States; 3 DC ties with Mexico; 1106 MW total 550+ generation units February 18, CRE/ERCOT

ERCOT Independent System Operator (ISO) February 18, 2014 ERCOT Inc.: A non-profit corporation designated the “Independent Organization” under state law and assigned these responsibilities [Texas Public Utility Regulatory Act (PURA) ]: Maintaining System Reliability Ensuring Open Access to Transmission Facilitating the Competitive Wholesale Market Facilitating the Competitive Retail Market Regulatory Characteristics: ERCOT is regulated by the Texas Public Utility Commission with oversight by the Texas Legislature ERCOT is not a market participant and does not own generation or transmission/distribution wires 3 CRE/ERCOT

Texas Competitive Model GenerationT&D (“Wires”) Competitive Production Regulated Open Access End Users REP Competitive Sales REP Retailers 4 CRE/ERCOTFebruary 18, 2014

ERCOT Markets February 18, Wholesale Fully unbundled Wholesale market ERCOT operates a single Balancing Area 5-Minute security constrained economic dispatch with day-ahead and ancillary services markets Generators are paid Locational Marginal Prices (LMPs) at node Load-serving entities pay averaged load-zone prices Transmission All transmission costs rolled-in to single postage-stamp rate paid by load Any transmission owner who transmits power for another entity is a regulated utility under state law No transmission service market Retail Full Retail competition for all customer types Except in municipal and cooperative utility areas Customers choose retail provider and terms of contract Smart meters (which measure time of consumption) installed on all customer types – over 6 million meters CRE/ERCOT

Normal Operations Market participants bring generation on-line; ERCOT may start additional generation needed to maintain reliability Market participants submit offers for generation output ERCOT clears market every five minutes, using the generation with the lowest bids to serve the load, subject to transmission constraints CRE/ERCOTFebruary 18, 2014 Prices received by generators signal whether more or less output is needed from generators in that area at that time Ancillary Services (also procured through markets) are used to cover variation in load within five minute intervals, if a generator trips, or to cover forecast variability 6

“Normal” Transmission Planning and Development 7 CRE/ERCOTFebruary 18, 2014

ERCOT Region Continues to Add Significant Transmission 41,500 Miles of Transmission Lines in ERCOT 8 CRE/ERCOTFebruary 18, 2014 >9,500 circuit miles of transmission (>60kV) built since 1999 ~2500 circuit miles of transmission under study $14.3 billion investment in transmission placed in service since 1999 ~$3.7 billion under development (including CREZ transmission)

Regional Planning Framework Coordinated 5-Yr. Transmission PlanLong-Term System Assessment Annual study of transmission needs of ERCOT system over next five years Projects identified by ERCOT in coordination with TOs with comment from stakeholders Projects included to meet all identified reliability requirements and congestion reduction projects that meet economic criteria Local and already-Reviewed projects are included without review Study of long-term transmission needs of ERCOT system Includes scenario-based analysis of future resource investment by market participants and resulting transmission system needs Produced in even years and re-evaluated annually Provides directional vision to near-term decisions with goal of long-term efficiency in transmission plans Transmission Owner PlansIndividual Project Reviews Projects developed by each transmission owner Generally include projects that are “Local” (<$15M) or “Neutral” Included in Steady-State Working Group (SSWG) powerflow cases Additional projects or studies can be proposed by any Market Participant, Transmission Owner or ERCOT Staff Individual projects included in 5-Yr. Transm. Plan also reviewed at appropriate time 9 February 18, 2014 CRE/ERCOT

ERCOT Transmission Development Process Project Need Identified –Either through Five-Year Plan Development Process or Stakeholder Proposal RPG Review of Project –Open RPG(stakeholder) comment period for all non-trivial projects –Level of RPG review depends on size of project; Independent Review by ERCOT Staff and ERCOT Board Endorsement for large Projects –Rule-based assignment of Project Developer Project Developer responsible for line engineering and routing studies PUCT determines Need and Routing for lines on new-right of way, through filing by project developer –ERCOT recommendation given “great weight” by PUCT in determining Need Cost recovery through annual transmission rate base adjustment; postage stamp rates paid by loads February 18, CRE/ERCOT

Generation Interconnection Study Process ERCOT role in interconnection process –Initial screening studies –Participate in the meeting to scope the full I/C study to be performed by the TSP –Oversee process (not technical studies) to ensure it is non- discriminatory –Review technical I/C studies performed by TSPs –Manage consolidated interconnection process to energization TSPs perform full interconnection and facilities studies ERCOT is not party to Interconnection agreement CRE/ERCOTFebruary 18,

Competitive Renewable Energy Zones Program 12 CRE/ERCOTFebruary 18, 2014

CRE/ERCOT Competitive Renewable Energy Zones Legislation By 2004, had a Chicken versus Egg Problem with wind development and transmission –Transmission Service Providers (TSPs) needed assurance that transmission would be used and useful –To develop transmission project and file CCN, TSPs wanted interconnection agreements, backed by security from wind developer –Wind developers were unwilling to commit security for 4- 7 years needed to complete new transmission with no guarantee In 2005, Texas Legislature directed the Public Utility Commission of Texas (PUCT), after consultation with ERCOT, to: –Designate areas with sufficient renewable resource potential (CREZs) o Consider level of financial commitment by developers –Develop a plan for transmission to deliver renewable resource to consumers February 18,

CRE/ERCOTFebruary 18, 2014 ERCOT Load ~62,000 MW peak demand (2007) Majority of load is concentrated in eastern half of state 14

CRE/ERCOTFebruary 18, 2014 Potential Wind Resource Nearly 100,000 MW above 35% capacity factor (CF) Concentrated in western half of state Limited Transmission Approximate wind capacity (in MW) potential in each area is indicated by pink bars 15

CRE/ERCOT ERCOT CREZ Study ERCOT led study during 2006 to support PUCT determination –Hired wind modeling consultant to identify best wind resource sites and provide expected characteristics of wind generation –Developed initial transmission plans through open stakeholder process to accommodate many of the potential zones in various combinations –Filed results with PUCT in December 2006 February 18,

CRE/ERCOTFebruary 18, 2014 Designated Zones and Scenario Wind Levels Capacity of New CREZ Wind by Scenario (MW) Wind Zone Scen. 1Scen. 2Scen. 3Scen. 4 Panhandle A 1,4223,1914,9606,660 Panhandle B 1,0672,3933,7200 McCamey 8291,8592,8903,190 Central 1,3583,0474,7355,615 Central West 4741,0631,6512,051 Total * 12,05318,45624,85924,419 * Assumes 6,903 MW of existing wind capacity 17

CREZ Transmission Plan FEBRUARY 18, 2014 CRE/ERCOT 18

Transmission Provider Selection PUCT solicits transmission developer interest –Portion of the CREZ Plan of interest –Financial and Project Management Capabilities Contested case hearings are held by PUCT –All but one of the proposing companies are selected for a portion of the Plan, determined by PUCT –Incumbents, existing utilities expanding into new area, new entities Selected transmission developers begin engineering, routing and certification filings –Line Certification filings at PUCT are made according to a schedule established based on expected time to develop projects February 18, 2014CRE/ERCOT 19

CRE/ERCOTFebruary 18, 2014 Transmission Developer Selection 20

CREZ Timeline SB 20 is Passed Initial ERCOT CREZ Study Completed PUCT Chooses TSPs for Projects ROWs Chosen 2011 CREZ Construction Begins Construction Complete PUCT Opens Docket designating the CREZ zones ~42 months ERCOT CREZ Transmission Optimization Plan Completed February 18, CRE/ERCOT

Increase in Installed Wind Generation 22 CRE/ERCOTFebruary 18, 2014

Wind Integration 23 CRE/ERCOTFebruary 18, 2014

Wind Output Peak wind generation output on 9,674MW on 5/2/13 8.7% of Nameplate Capacity of wind counted towards reserve margin % Energy Produced by Fuel Type 2012 February 18, 2014CRE/ERCOT 24

Operational Challenges for Wind Integration Uncertainty Variability Interconnection February 18, 2014CRE/ERCOT 25

Wind Forecast February 18, 2014 Wind power production forecast –Hourly 50% probability of exceedance forecast for a rolling 48 hour period –Provided for each wind farm and total for system Used to determine need for “residual” unit commitment Actual Hour-ahead Day-ahead CRE/ERCOT 26

Wind Forecast Error February 18, 2014 Average hour-ahead wind forecast error is significant (MAPE is ~7%) MW errors may be high (>1000 MW; occasionally >2000 MW) CRE/ERCOT 27

Wind Forecasting ERCOT Large Ramp Alert System (ELRAS) –Probabilistic forecast which alerts Operators of ramps during the next 6 hours –Provided on the system and regional level Predicting Large Ramps in Wind Power Output February 18, 2014 CRE/ERCOT 28

Ancillary Services - Regulation ERCOT typically dispatches generation each five minutes Regulation Service is used to balance the variation in load and generation between five-minute economic dispatch executions Primary driver for determining required amount of regulation is historical deployments –Adjusted for increase in installed wind capacity February 18, 2014CRE/ERCOT 29

Ancillary Services – Non-Spin Non-spin Reserve Service –30 minute product that can be provided by unloaded capacity, offline Generators, and Load Resources –Wind power forecast error is one of the inputs used for calculating the requirement for this service February 18, 2014 Non- Spin Deployed CRE/ERCOT 30

Primary Frequency Response All generation in ERCOT is required to provide governor response with a 5% droop setting Wind farms are required to provide primary frequency response to frequency deviations from 60 Hz. February 18, 2014CRE/ERCOT 31

Proposed New AS Framework – Frequency Control Services CRE/ERCOTFebruary 18, 2014 Regulation Old Framework New Framework Regulation Responsive Fast Frequency Response Primary Frequency Response Contingency Reserve Non-Spin Supplemental Reserve Synchronous Inertial Service Only change to unit-specific Full response in 30 cycles based on freq threshold Sustained for 10 mins Provides instantaneous proportional change in power output to stabilize freq Full Deployment in 10 mins Full Deployment in 30 mins Will be phased out in long-term Provided by synchronous machines Unit commitment 32

Generation Ramps February 18, 2014CRE/ERCOT 33

Interconnection-Related Requirements February 18, 2014 Inverter-connected resources may not fit with traditional technical requirements Need to address these issues to maintain system reliability:  Static and dynamic reactive capability  Voltage-ride through capability  Modeling o Collector system and support device modeling o Dynamic model and parameters CRE/ERCOT 34

Impact of Wind Generation on Prices There is a clear shift down in the duration curve of real-time prices for higher levels of wind power output February 18, 2014CRE/ERCOT 35

Summary of Wind Integration Needs Sufficiently large Balancing Area Nodal market mechanisms with short dispatch cycle to incent flexibility in generation fleet and efficiently allocate curtailment Accurate wind forecast and wind ramp projections All generators required to contribute to system needs for voltage support and frequency control Incorporation of wind uncertainty and variability into ancillary services requirements February 18, 2014CRE/ERCOT 36

Generation Planning/Resource Adequacy 37 CRE/ERCOTFebruary 18, 2014

Capacity, Demand and Reserves February 18, 2014CRE/ERCOT 38

Questions? April 23, 2014 AMDEE/ERCOT