Proton PMG September 3 rd 2015 Cons Gattuso AD Shutdown Manager.

Slides:



Advertisements
Similar presentations
LCW Upgrades - Final Booster RF Cavity LCW Isolation Valve Replacement. – 8 valves and unions previously replaced – An additional 10 valves and unions.
Advertisements

Proton Source Workshop Booster Downtime Wednesday, December 8, 2010 T. Sullivan.
FAC, 10/12/06 D. Schultz 1 e-Beams Systems Update Linac Injector Undulator Production MMF commissioning ARR David Schultz.
Proton Source Workshop December 7 & 8, 2010 John Reid December 8, 2010.
Proton Source Task Shutdown 2014 RFQ Injection Linac Tank 1 to 2 emmittance probe and Collimator NTF Beam Line Repair 400 MeV Turbo Station Replacement.
NOvA meeting PIP Update W. Pellico. PIP Goals and Scope (Provided in 2011 – Directorate S. H. / DOE Talk ) Goals: Specific to the issues surrounding the.
FAC, 10/12/06 D. Schultz 1 Readiness for 2007 Startup Linac Injector Controls ARR David Schultz.
ANU Shutdown Status AEM meeting Cons Gattuso 6/3/2012.
ILCTA_NML Progress at Fermilab Jerry Leibfritz September 10, 2007.
PIP Update April 30 th Agenda Summary Update – Current Activities/Updates – Nathan Eddy – Booster Longitudinal Damper.
NUMI NuMI Review of the Infrastructure – W, G & V 20 July 2001 WBS Page 1 1 Infrastructure Review - W.B.S Water Systems Water Systems –Upstream.
PIP Update Aug 6 th Agenda Summary Update – Current Activities/Updates – New Tuner Test Result: Reid & Slabaugh – Anode Supplies: Crawford.
Proton Improvement Plan Bob Zwaska August 3, 2015 All-Experimenters Meeting.
PIP Update Feb 20 th Agenda Summary Update – Current Activities/Updates – Startup Schedule Highlights – Upcoming Talks, Reports, Meetings Updates/Talks:
Muon Campus Projects Jerry Annala Jan 23, µ AIP Scope Recycler RF system to provide needed bunch structure to future Muon Experiments Recycler RF.
Proton Source Water Systems Proton Source Workshop December 8, 2010 Maurice Ball.
09/28/07Shutdown’07 Week 8 F.G. Garcia1 MTA beam line installation Weekly Report September 28, 2007 Period covered: September 24 th September 28 th (Week.
ANU Shutdown Status AEM meeting Cons Gattuso 7 May 2012.
August 05, Startup 2013 Machine Status:  Proton Source Commissioning and Studies RFQ Injector Line (RIL) Linac Booster  Main Injector Startup.
Injector/Re-injection Chicane Michael Bevins May 17, GeV Upgrade - Beam Transport Injection, Linac, Extraction, & Correctors Preliminary Design.
All Experimenters’ Meeting November 03, 2014 Photo by Greg Vogel.
All Experimenters’ Meeting February 09, Accelerator Operation Summary Calendar Week # 06 NuMI Weekly Integrated Intensity 6.69 E18 protons Beam.
HINS 6-Cavity Test 3 Month Plan Jan 12, Current Schedule 2-3 day shutdown scheduled to start Jan 18 (Wednesday) to upgrade BPM system and reinstall.
PIP Update June 3 rd Agenda Summary Update – Current Activities – Updates Ken Domann – Budget & Schedule Ryan Crawford – Anode Supply Update – Additional.
2015 Shutdown Joe Compton 3/11/2015. RIL PIP Work  Install operational laser notcher  5 days  Dave Johnson & Todd Johnson.
Accelerator and NuMI Upgrades Shutdown Update Cons Gattuso July 02, 2012 July 2, 2012 Cons Gattuso1.
Proton Improvement Plan Bob Zwaska January 7, 2013 All-Experimenters Meeting.
08/31/07Shutdown’07 Week 4 F.G. Garcia1 MTA beam line installation Weekly Report August 31, 2007 Period covered: August 24 th to August 31 st (Week 4)
Proton Improvement Plan Keith Gollwitzer January 5th, 2015 All Experimenters’ Meeting 11/5/2015Gollwitzer AEM.
PIP Update July 30 th Agenda Summary Update – Current Activities/Updates – Project Controls Update: K. Domann – Linac Lattice – Valeriy Kapin.
PIP Update April 8 th Agenda Summary Update – Current Activities – Updates (V. Kapin: Booster Collimator) – Additional Meetings/Notes.
PIP Update April 8 th Agenda Summary Update – Current Activities – Updates (Joe Compton - shutdown) – Additional Meetings/Notes.
TD Help for Shutdown 2012 Preliminary, will be updated April 18, 2012.
PIP Budget Codes Budget FY12 Updates October 19, 2011 PIP Meeting.
Booster Bias Supply and Cavity Upgrade November 16 th, 2011.
Proton Plan PMG 9/27/07 E Prebys 1 Proton Plan Status Eric Prebys.
Proton Improvement Plan Bill Pellico April 19, 2013 NOvA collaboration Meeting Bill Pellico NOvA.
Accelerator Status and Plans
All Experimenters’ Meeting January 26, Accelerator Operation Summary Calendar Week # 03 NuMI Weekly Integrated Intensity 2.74 E18 protons Beam.
All Experimenters’ Meeting October 20, 2014 Photo by Greg Vogel.
All Experimenters’ Meeting December 8, 2014 Photo by Greg Vogel.
PIP Update June 18 th Agenda Summary Update – Current Activities/Updates – Reid, Slabaugh.
PIP Update April 10 th Agenda Summary Update – Current Activities/Updates – Startup Plans – Upcoming Talks, Reports, Meetings Updates/Talks: Eliana.
PIP Update Aug. 21 st Agenda Summary Update – Current Activities/Updates – Startup Plans – Upcoming Talks, Reports, Meetings Updates/Talks: B Pellico.
09/07/07Shutdown’07 Week 5 F.G. Garcia1 MTA beam line installation Weekly Report September 07, 2007 Period covered: August 31 st to September 7 th (Week.
PIP Update April 3 rd Agenda Summary Update – Current Activities/Updates – Startup Plans – Upcoming Talks, Reports, Meetings Updates/Talks: Trevor.
Machine Status  Proton Source Commissioning and Studies 8/13-8/14: Linac & Booster Maintenance Period  Main Injector MI30 vacuum ○ Work continues to.
Booster Shutdown Work - Week 4 Dump and Shielding installation completed Q805/Q806 re-installed, Septum in place Need to align quads and septum before.
PIP Update Jan. 16 th Agenda Summary Update – Current Activities/Updates – Shutdown ScheduleHighlights – Upcoming Talks, Reports, Meetings Updates/Talks:
August 12, Machine Status: 2013  Proton Source Commissioning and Studies RFQ Injector Line (RIL) Linac : Roof hatch installed Booster : Magnet.
Proton Source Meeting, August 8, 2003 – E. Prebys 1 Major Projects in Linac/Booster  New Linac Lambertson  (4) New EDWA magnets in MI-8 line  (3) New.
PIP Update July 29 th Agenda Summary Update – Current Activities – Updates Tom Kubicki (Station 20,21,22 – Gallery and Equipment Work) – Additional.
PIP Update August 12 th Agenda Summary Update Current Activities Update – Ryan Crawford - Booster Anode Power Supplies – Dave Johnson - Laser Notcher.
All Experimenters’ Meeting November 4, Accelerator Operation Summary Calendar Week # 44 NuMI Weekly Integrated Intensity 5.97 E18 protons BNB.
Mike Andrews May 10, Week 54 NuMI Activities Initial test controls on the MI65 RAW exchange skid Complete hydrostatic test of the MI65 exchange.
09/21/07Shutdown’07 Week 7 F.G. Garcia1 MTA beam line installation Weekly Report September 21, 2007 Period covered: September 14 th September 21 th (Week.
Booster Status, September 4, 2003 – E. Prebys 1 Frantic Shutdown Preparations Continue…
09:00 Meeting Shutdown Update June 29 th 2015 Cons Gattuso AD Shutdown Manager.
PIP Shutdown Status 9/17/2014. RIL/Linac Jobs L1 Transformer ◦Rigging complete ◦Electrical work started ◦Turn on this coming weekend Laser notcher flange.
ILCTA_NML Progress at Fermilab Jerry Leibfritz August 16, 2007.
PIP Update May Agenda Summary Update – Activities – Budget – Plans Update Slides – Solid StateTom – ModulatorsRene – High Power Ferrite Testing.
Friday 5/1/ meeting. I wish to lock in the power outage onTuesday 5/5/09 at the end of the 0930 lab scheduling meeting speak now or :
Work in the Tevatron A0 D0 B0 C0 E0 F0 Separators A49 Separator B48 TEL 2 installation A0 Xtal Collimator 1.5 m collimator A48 Shimming 6 magnets/day At.
MI/RR Shutdown 2012 Dec Gev Lines/Injection region: Staging equipment, cleaning and prepping new part to start vacuum work. Preparing to modify the.
10/3/2014 Proton Source Update. RIL Update Source B is back in place and under vacuum It will be baked over the weekend It will be started early next.
Mike Andrews January 31, Weeks Activities Target Pile Fan Upgrades Install piping for new cooling coil units Install controls for new coil.
All Experimenters Meeting PIP Report Fernanda G. Garcia on behalf of PIP team 10/06/2014.
Proton PMG May 7 th 2015 Cons Gattuso AD Shutdown Manager.
Injector –Linac Status & Schedule E. Bong LCLS FAC October 12, 2006
Linac4 Connection Broken Line 07/08/19
Presentation transcript:

Proton PMG September 3 rd 2015 Cons Gattuso AD Shutdown Manager

Project Schedule 11/4/14C. Gattuso| AD Shutdown Manager2 End of shutdown Beam Based Alignment

Major Jobs in the shutdown Linac –Laser Notcher installation –Marx Modulator Booster –Anode power supplies replacement –Vacuum upgrades –Installation of BRF 20 and prepare area BRF21 & 22 install –Water system upgrades –ADCW magnet harvesting –Beam pipe Downs stream of MP02 vacuum leak –Vacuum Leak on Primary collimator –BMA short9 and short10 were replaced MI/RR –TSP to Ion Pump conversion –Replacement of beam pipe at 421/425/429 location –Installed Electron Cloud detector –ADCW magnet replacement –Removal of instrumentation package at MI102 location 11/4/14C. Gattuso| AD Shutdown Manager3 Muon Campus F0 Aperture improvement F17 region rework AP1 line rework RR to P1 installation NuMI Multi wire replacement Horn 1 replacement External Beams F36-2 Water lean on a B2 dipole F32-3 Water leak on B2 dipole Control Standard Database system and JAVA updates Infrastructure Master Sub Station Upgrade September 8th handover to ComED

Linac/Booster Job Status Linac –Laser Notcher installation -Completed ( remaining work does not impact operations) All of the vacuum components have been installed Still testing laser amplifiers On scheduled for beam base testing in late fall –Marx Modulator – Completed (remaining work does not impact operations) In parallel with the modulator in LRF1 Can by put into and out of the system within 30 min time frame. Booster –Anode power supplies replacement East status ~85% complete –Life safety systems being installed –Water system has been installed Loop system in the process of improving resistivity –High voltage testing Will start next week, ~ 2 week process West Side status ~15% complete –On schedule to be completed by the week of September 25 th 11/4/14C. Gattuso| AD Shutdown Manager4

Linac/Booster Job Status –Vacuum upgrades – 100% Completed –Installation of BRF 20 and prepare area BRF21 & 22 install ~85% Complete BRF20 will be shipped today –Cavity will be install mid next week/ –Buss bar connection are nearly complete final connection will be made next week –Modulator and Bias supply for the Stations 20 will be installed next week –Misc RF rack modifications that need to be made. –Water system upgrades 100% Completed Upgrades are done We are in the process of filling the system ~50% complete –Filling will take a few days to a week as we fix leaks that are discovered along the way, 11/4/14C. Gattuso| AD Shutdown Manager5

Main Injector/Recycler Job Status RR TSP to Ion pump conversion – 100% Completed –In the check out process we have discovered 1 cable that was damaged during installation. IP6331 will need to be re-pulled, this will take place in the next few weeks RR 307 Beam Pipe replacement -100% Completed MI-8 Heat exchanger repair –Pitting on internal welds is causing the tubes to leak Working on several plans to fix this problem ADCW installation at the 904 location –Take will start tomorrow MI 307 Duplex Pipe replacement 5% Completed –Fabrication of spool pieces is still underway –Working through a safety plan on this job RR 425/429 Beam loss issues 50% Completed –Several segments of beam pipe we discovered with welds that intruded within the aperture –A segment of pipe was found to have a chicane that limit the aperture size –First of 2 bakes will be completed Friday –Second bake will start middle of next week 11/4/14C. Gattuso| AD Shutdown Manager6

Muon Campus Job status RR to P1 line ~95% complete –Stands and girders have been installed –The P1 line has been restored –Cable pulls have been completed –All that remains Reinstallation of the MI quad Q525 Cable termination and hook ups are underway F0 Region Reconfiguration ~95% complete – Lamberstons have been removed –Vacuum system has been rebuilt –All that remains V714 dipole needs to have the 500 MCM cable lengthened and connected Instrumentation components need to be hooked up and tested 11/4/14C. Gattuso| AD Shutdown Manager7

Muon Campus Job status F17 Region Reconfiguration ~75% complete –Stands have been installed –Magnet installation is underway and should be completed today –All that remains Vacuum system installation Magnet/beam pipe alignment Pre-Target/Prevault ~20% complete –Work scheduled to start next week Stand installation Magnet installation Vacuum installation Alignment 11/4/14C. Gattuso| AD Shutdown Manager8

External Beams Shutdown Job Status F32-3 water leak ~75% complete –Dipole was removed and taken to A0 transfer hall and the leak was repaired –Remaining work Install the magnet ( should take place week 10/11 of the shutdown) Rebuild the vacuum system NS2 LCW System modernization ~55% complete –Old system has been removed –Reinstallation of the new system is underway ~1.5 weeks left to completion MS2 LCW System modernization (will occur during January Down period) H202 dipole replacement (should take place week 11/12 of the shutdown) 11/4/14C. Gattuso| AD Shutdown Manager9

External Beams Shutdown Job Status BNB –Cable pulls for MI12 Instrumentation -50% completed –Interlock system modification Cables for Safety System Gates – 75% completed Gates 100% completed Procedure changes need to be made/reviewed –Work has start on this task Software changes to the Safety System need to be done/tested –Some work has been started on this task. 11/4/14C. Gattuso| AD Shutdown Manager10

External Beams Shutdown Job Status NuMI –Pretarget Multi wire replacement for PMTGTL, PM114 and PM117 – 100% complete –Muon Alcove 1 shielding wall installation 100% complete –Drain Cleaning -100% complete –Raw water system Maintience 100% complete –Dehumidifier system repairs and maintience 100% complete –Started Horn 1 replacement process has commenced ~ 20% complete 11/4/14C. Gattuso| AD Shutdown Manager11

Misc. Safety System Test: –Semi-Annual test potential impact on the order of 1-2 days to overall schedule Linac was completed this last Wednesday As work is completed in tunnel enclosures testing will be scheduled/done –MI12A/B –F-sector –Muon Campus Transport/Pre-Target/Pre-Vault –Booster –MI enclosures –NuMI enclosures –SY enclosures 11/4/14C. Gattuso| AD Shutdown Manager12

On schedule –Completion of shutdown work Friday October 2 nd Power supply turn-on and checkout the Weekend of October 3 rd Turning on Week of October 5 th –1-2 Week of Start up/ Commissioning Resumption of Physic Program –Week of the October 19 Conclusion 11/4/14C. Gattuso| AD Shutdown Manager13