Resolution No WATERFALLS REGIONAL POND CHANGE ORDER NO. ONE WATERFALLS REGIONAL POND CHANGE ORDER NO. ONE Contract Cost: $2,969, Contract Time: 185 wd
Background January Resolution approved awarding Waterfalls Regional Project to Burn Construction Co.: Bid Amount $ 2,969, Tax $ 219, CM Contingency $ 148, TOTAL $ 3,337, Construction included excavation of a 125 acre detention pond to alleviate storm runoff concerns.
US 70 Holman Dunn NMDOT Reynolds Waterfalls Regional Pond 125 Acre Pond Waterfalls Subdivision
North Fork Arroyo at Sonoma Ranch Blvd. - $124,416 Project Limits North Fork Arroyo Golf Club Road Sonoma Ranch
North Fork Arroyo at Sonoma Ranch
Chandler Tank at Sonoma Ranch Blvd. - $82,972 Chandler Tank Entrada de Sierra Sonoma Ranch Project Limits US 70
Chandler Tank at Sonoma Ranch Rundown Outlet Tower Box Culvert
Changes North Fork Arroyo $ 124, Chandler Tank$ 82, Total $ 207, North Fork Arroyo work was proposed to be completed by Philippou. Utilities has completed the majority of the arroyo improvements in conjunction with a settlement agreement between Philippou and LC Utility board. Chandler Tank work as part of Entrada de Sierra subdivision is a result of settlement agreement between Philippou and the City.
Fund 4400 Flood Control
Fund 4413 NMFA Flood Control 2008
Changes Contract Cost to date $ 3,177, Council Approved Amount$ 2,969, Difference $ 207, Increase in contract of $207, (6.98%) over Council approved amount and exceeds the City Manager approved contingency of $148, by $58, Final Contract Time will be increased by 55 working days days for work in the North Fork Arroyo - 30 days for work in Chandler Tank Pond
Council Options Waterfalls Regional Pond Change Order One Option 1 –Approve Change Order One. –+$ 207, –55 working days Option 2 –Reject and direct staff to pursue other alternatives Option 3 –Modify resolution per council direction
Summary of Changes ItemChangeReason North Fork$124,416.00Install wire tied rip-rap along arroyo and slopes. Chandler Tank$82,972.00Repair concrete rundown, grading, install wire tied rip-rap. Time25, 30Additional work for North Fork and Chandler Tank.