1 Engineering Economics 140290109017. 2 Engineering Economy It deals with the concepts and techniques of analysis useful in evaluating the worth of systems,

Slides:



Advertisements
Similar presentations
Chapter 4 More Interest Formulas
Advertisements

Engineering Economic Analysis - Ninth Edition Newnan/Eschenbach/Lavelle Copyright 2004 by Oxford Unversity Press, Inc.1 Engineering Economic Analysis 9th.
Interest and Equivalence L. K. Gaafar. Interest and Equivalence Example: You borrowed $5,000 from a bank and you have to pay it back in 5 years. There.
26-1 C APITAL B UDGETING LONG-RANGE PLANNING CHAPTER 26.
Copyright © 2008 Prentice Hall All rights reserved 9-1 Capital Investment Decisions and the Time Value of Money Chapter 9.
Capital Investments Chapter 12. Capital Budgeting How managers plan significant outlays on projects that have long-term implications such as the purchase.
© Mcgraw-Hill Companies, 2008 Farm Management Chapter 17 Investment Analysis.
APPLICATIONS OF MONEY-TIME RELATIONSHIPS
FA2 Module 5. Interest concepts of future and present value 1.Time value of money 2.Basic interest concepts 3.Present and future values a.Single payment.
Engineering Economics I
INTEREST AND CASH FLOW DIAGRAM
Chapter 17 Investment Analysis
TOPIC TWO: Chapter 3: Financial Mathematics By Diana Beal and Michelle Goyen.
Slide to accompany Blank and Tarquin Basics of Engineering Economy, 2008 © 2008 by McGraw-Hill All Rights Reserved Basics of Engineering Economy.
State University of New York WARNING All rights reserved. No part of the course materials used in the instruction of this course may be reproduced in any.
State University of New York WARNING All rights reserved. No part of the course materials used in the instruction of this course may be reproduced in any.
Chapter 3 - Interest and Equivalence Click here for Streaming Audio To Accompany Presentation (optional) Click here for Streaming Audio To Accompany Presentation.
Warm-Up Review Time Value of Money Calculation of Future Value
(c) 2002 Contemporary Engineering Economics
(c) 2001 Contemporary Engineering Economics 1 Chapter 7 Present Worth Analysis Describing Project Cash Flows Initial Project Screening Method Present Worth.
5.0 Chapter 5 Discounte d Cash Flow Valuation. 5.1 Key Concepts and Skills Be able to compute the future value of multiple cash flows Be able to compute.
Topic 9 Time Value of Money.
Time Value of Money – Part II
AEC 422 Fall 2014 Unit 2 Financial Decision Making.
FOOD ENGINEERING DESIGN AND ECONOMICS
Naval Postgraduate School Time Value of Money Discounted Cash Flow Techniques Source: Raymond P. Lutz, “Discounted Cash Flow Techniques,” Handbook of Industrial.
EGR Interest and Interest Rate Interest, I ($) = amount owed now – original amount A)$1000 placed in bank account one year ago is now worth.
Intro to Engineering Economy
Summer Time Value of Money Session 2 07/02/2015.
ENGR 112 Economic Analysis. Engineering Economic Analysis Evaluates the monetary aspects of the products, projects, and processes that engineers design.
1 Microeconomics Lecture 11 Capital market Institute of Economic Theories - University of Miskolc Mónika Orloczki Assistant lecturer Andrea Gubik Safrany,
PRINCIPLES OF MONEY-TIME RELATIONSHIPS. MONEY Medium of Exchange -- Means of payment for goods or services; What sellers accept and buyers pay ; Store.
ACCTG101 Revision MODULES 10 & 11 TIME VALUE OF MONEY & CAPITAL INVESTMENT.
Rate of Return Analysis
THE TIME VALUE OF MONEY TVOM is considered the most Important concept in finance because we use it in nearly every financial decision.
Example [1] Time Value of Money
CTC 475 Review Cost Estimates Job Quotes (distributing overhead) – Rate per Direct Labor Hour – Percentage of Direct Labor Cost – Percentage of Prime (Labor+Matl)
Long-Term (Capital Investment) Decisions
Contemporary Engineering Economics, 6 th edition Park Copyright © 2016 by Pearson Education, Inc. All Rights Reserved Rate of Return Analysis Lecture No.
State University of New York WARNING All rights reserved. No part of the course materials used in the instruction of this course may be reproduced in any.
1 ECGD3110 Systems Engineering & Economy Lecture 3 Interest and Equivalence.
THE TIME VALUE OF MONEY TVOM is considered the most Important concept in finance because we use it in nearly every financial decision.
1 ECGD3110 Systems Engineering & Economy Lecture 3 Cost Estimation.
Capital Budgeting Decisions
Compound Interest. The interest is added to the principal and that amount becomes the principal for the next calculation of interest. OR.
Chapter 4: The Time Value of Money
Engineering Economic Analysis Canadian Edition
Interest and Interest Rate Interest ($) = amount owed now – original amount A)$1000 placed in bank account one year ago is now worth $1025. Interest earned.
0 CHAPTER 10 Long-Term (Capital Investment) Decisions © 2009 Cengage Learning.
Chapter 6 Time Value of Money. Introduction Why money has a time value –The opportunity cost of capital concept Time value of money and risk –Typically.
Engineering Economic Analysis Canadian Edition Chapter 3: Interest and Equivalence.
Chapter 8 Long-Term (Capital Investment) Decisions.
1 Capital Budgeting. 2 n Capital Budgeting is a process used to evaluate investments in long-term or Capital Assets. n Capital Assets n have useful lives.
ISU CCEE CE 203 EEA Chap 3 Interest and Equivalence.
MER Design of Thermal Fluid Systems INTRODUCTION TO ENGINEERING ECONOMICS Professor Bruno Winter Term 2005.
Chapter 3 Interest and Equivalence Copyright Oxford University Press 2009.
1 Engineering Economics.  Money has a time value because it can earn more money over time (earning power).  Money has a time value because its purchasing.
(c) 2002 Contemporary Engineering Economics 1. Engineers must work within the realm of economics and justification of engineering projectsEngineers must.
CAPITAL BUDGETING DECISIONS CHAPTER Typical Capital Budgeting Decisions Plant expansion Equipment selection Equipment replacement Lease or buy Cost.
Chapter 5 Time Value of Money. Basic Definitions Present Value – earlier money on a time line Future Value – later money on a time line Interest rate.
Faculty of Applied Engineering and Urban Planning Civil Engineering Department Engineering Economy Lecture 1 Week 1 2 nd Semester 20015/2016 Chapter 3.
1. 2 Engineering Economics (2+0) Fundamentals of Engineering Economics-2 And Time value of Money Instructor: Prof. Dr. Attaullah Shah Lecture # 2 Department.
Copyright © 2006, The McGraw-Hill Companies, Inc.McGraw-Hill/Irwin BNFO 621: Business and Entrepreneurship : ACCOUNTING Roxanne M. Spindle Associate Professor.
APPLICATIONS OF MONEY-TIME RELATIONSHIPS
Chapter 2 Time Value of Money
Chapter 7 Present Worth Analysis
Managerial Accounting 2002e
Engineering Economic Analysis
Presentation transcript:

1 Engineering Economics

2 Engineering Economy It deals with the concepts and techniques of analysis useful in evaluating the worth of systems, products, and services in relation to their costs

3 Engineering Economy It is used to answer many different questions –Which engineering projects are worthwhile? Has the mining or petroleum engineer shown that the mineral or oil deposits is worth developing? –Which engineering projects should have a higher priority? Has the industrial engineer shown which factory improvement projects should be funded with the available dollars? –How should the engineering project be designed? Has civil or mechanical engineer chosen the best thickness for insulation?

4 Basic Concepts Cash flow Interest Rate and Time value of money Equivalence technique

5 Cash Flow Engineering projects generally have economic consequences that occur over an extended period of time –For example, if an expensive piece of machinery is installed in a plant were brought on credit, the simple process of paying for it may take several years –The resulting favorable consequences may last as long as the equipment performs its useful function Each project is described as cash receipts or disbursements (expenses) at different points in time

6 Categories of Cash Flows The expenses and receipts due to engineering projects usually fall into one of the following categories: –First cost: expense to build or to buy and install –Operations and maintenance (O&M): annual expense, such as electricity, labor, and minor repairs –Salvage value: receipt at project termination for sale or transfer of the equipment (can be a salvage cost) –Revenues: annual receipts due to sale of products or services –Overhaul: major capital expenditure that occurs during the asset’s life

7 Cash Flow diagrams The costs and benefits of engineering projects over time are summarized on a cash flow diagram (CFD). Specifically, CFD illustrates the size, sign, and timing of individual cash flows, and forms the basis for engineering economic analysis A CFD is created by first drawing a segmented time-based horizontal line, divided into appropriate time unit. Each time when there is a cash flow, a vertical arrow is added  pointing down for costs and up for revenues or benefits. The cost flows are drawn to relative scale

8 Drawing a Cash Flow Diagram In a cash flow diagram (CFD) the end of period t is the same as the beginning of period (t+1) Beginning of period cash flows are: rent, lease, and insurance payments End-of-period cash flows are: O&M, salvages, revenues, overhauls The choice of time 0 is arbitrary. It can be when a project is analyzed, when funding is approved, or when construction begins One person’s cash outflow (represented as a negative value) is another person’s inflow (represented as a positive value) It is better to show two or more cash flows occurring in the same year individually so that there is a clear connection from the problem statement to each cash flow in the diagram

9 An Example of Cash Flow Diagram A man borrowed $1,000 from a bank at 8% interest. Two end-of-year payments: at the end of the first year, he will repay half of the $1000 principal plus the interest that is due. At the end of the second year, he will repay the remaining half plus the interest for the second year. Cash flow for this problem is: End of year Cash flow 0 +$ $580 (-$500 - $80) 2 -$540 (-$500 - $40)

10 Cash Flow Diagram $1, $580 $540

11 Time Value of Money Money has value –Money can be leased or rented –The payment is called interest –If you put $100 in a bank at 9% interest for one time period you will receive back your original $100 plus $9 Original amount to be returned = $100 Interest to be returned = $100 x.09 = $9

12 Compound Interest Interest that is computed on the original unpaid debt and the unpaid interest Compound interest is most commonly used in practice Total interest earned = I n = P (1+i) n - P –Where, P – present sum of money i – interest rate n – number of periods (years) I 2 = $100 x (1+.09) 2 - $100 = $18.81

13 Future Value of a Loan With Compound Interest Amount of money due at the end of a loan –F = P(1+i) 1 (1+i) 2 …..(1+i) n or F = P (1 + i) n –Where, F = future value and P = present value Referring to slide #10, i = 9%, P = $100 and say n= 2. Determine the value of F. F = $100 (1 +.09) 2 = $118.81

14 Notation for Calculating a Future Value Formula: F=P(1+i) n is the single payment compound amount factor. Functional notation: F=P(F/P,i,n) F=5000(F/P,6%,10) F =P(F/P) which is dimensionally correct.

15 Notation for Calculating a Present Value P=F(1/(1+i)) n =F(1+i) -n is the single payment present worth factor. Functional notation: P=F(P/F,i,n) P=5000(P/F,6%,10) Interpretation of (P/F, i, n): a present sum P, given a future sum, F, n interest periods hence at an interest rate i per interest period

16 Spreadsheet Function P = PV(i,N,A,F,Type) F = FV(i,N,A,P,Type) i = RATE(N,A,P,F,Type,guess) Where, i = interest rate, N = number of interest periods, A = uniform amount, P = present sum of money, F = future sum of money, Type = 0 means end-of-period cash payments, Type = 1 means beginning-of-period payments, guess is a guess value of the interest rate

17 Equivalence Relative attractiveness of different alternatives can be judged by using the technique of equivalence We use comparable equivalent values of alternatives to judge the relative attractiveness of the given alternatives Equivalence is dependent on interest rate Compound Interest formulas can be used to facilitate equivalence computations

18 Technique of Equivalence Determine a single equivalent value at a point in time for plan 1. Determine a single equivalent value at a point in time for plan 2. Both at the same interest rate and at the same time point. Judge the relative attractiveness of the two alternatives from the comparable equivalent values.

19 Engineering Economic Analysis Calculation Generally involves compound interest formulas (factors) Compound interest formulas (factors) can be evaluated by using one of the three methods –Interest factor tables –Calculator –Spreadsheet

20 Given the choice of these two plans which would you choose? YearPlan 1Plan 2 0$5,000 1$1, Total$5,000 To make a choice the cash flows must be altered so a comparison may be made.

21 Resolving Cash Flows to Equivalent Present Values P = $1,000(P  A,10%,5) P = $1,000(3.791) = $3,791 P = $5,000 Alternative 2 is better than alternative 1 since alternative 2 has a greater present value

22 An Example of Future Value Example: If $500 were deposited in a bank savings account, how much would be in the account three years hence if the bank paid 6% interest compounded annually? Given P = 500, i = 6%, n = 3, use F = FV(6%,3,,500,0) = Note that the spreadsheet gives a negative number to find equivalent of P. If we find P using F = -$595.91, we get P = 500.

23 An Example of Present Value Example 3-5: If you wished to have $800 in a savings account at the end of four years, and 5% interest we paid annually, how much should you put into the savings account? n = 4, F = $800, i = 5%, P = ? P = PV(5%,4,,800,0) = -$ You should use P = $658.16

24 Economic Analysis Methods Three commonly used economic analysis methods are Present Worth Analysis Annual Worth Analysis Rate of Return Analysis

25 Present Worth Analysis Steps to do present worth analysis for a single alternative (investment) –Select a desired value of the return on investment (i) –Using the compound interest formulas bring all benefits and costs to present worth –Select the alternative if its net present worth (Present worth of benefits – Present worth of costs) ≥ 0

26 Present Worth Analysis Steps to do present worth analysis for selecting a single alternative (investment) from among multiple alternatives –Step 1: Select a desired value of the return on investment (i) –Step 2: Using the compound interest formulas bring all benefits and costs to present worth for each alternative –Step 3: Select the alternative with the largest net present worth (Present worth of benefits – Present worth of costs)

27 Present Worth Analysis A construction enterprise is investigating the purchase of a new dump truck. Interest rate is 9%. The cash flow for the dump truck are as follows: First cost = $50,000, annual operating cost = $2000, annual income = $9,000, salvage value is $10,000, life = 10 years. Is this investment worth undertaking? P = $50,000, A = annual net income = $9,000 - $2,000 = $7,000, S = 10,000, n = 10. Evaluate net present worth = present worth of benefits – present worth of costs

28 Present Worth Analysis Present worth of benefits = $9,000(P  A,9%,10) = $9,000(6.418) = $57,762 Present worth of costs = $50,000 + $2,000(P  A,9%,10) - $10,000(P  F,9%,10)= $50,000 + $2,000(6..418) - $10,000(.4224) = $58,612 Net present worth = $57,762 - $58,612 < 0  do not invest What should be the minimum annual benefit for making it a worthy of investment at 9% rate of return?

29 Present Worth Analysis Present worth of benefits = A(P  A,9%,10) = A(6.418) Present worth of costs = $50,000 + $2,000(P  A,9%,10) - $10,000(P  F,9%,10)= $50,000 + $2,000(6..418) - $10,000(.4224) = $58,612 A(6.418) = $58,612  A = $58,612/6.418 = $9,312.44

30 Cost and Benefit Estimates Present and future benefits (income) and costs need to be estimated to determine the attractiveness (worthiness) of a new product investment alternative

31 Annual costs and Income for a Product Annual product total cost is the sum of annual material, labor, and overhead (salaries, taxes, marketing expenses, office costs, and related costs), annual operating costs (power, maintenance, repairs, space costs, and related expenses), and annual first cost minus the annual salvage value. Annual income generated through the sales of a product = number of units sold annuallyxunit price

32 Rate of Return Analysis Single alternative case In this method all revenues and costs of the alternative are reduced to a single percentage number This percentage number can be compared to other investment returns and interest rates inside and outside the organization

33 Rate of Return Analysis Steps to determine rate of return for a single stand-alone investment –Step 1: Take the dollar amounts to the same point in time using the compound interest formulas –Step 2: Equate the sum of the revenues to the sum of the costs at that point in time and solve for i

34 Rate of Return Analysis An initial investment of $500 is being considered. The revenues from this investment are $300 at the end of the first year, $300 at the end of the second, and $200 at the end of the third. If the desired return on investment is 15%, is the project acceptable? In this example we will take benefits and costs to the present time and their present values are then equated

35 Rate of Return Analysis $500 = $300(P  F, i, n=1) + 300(P  F, i, n=2) + $200(P  F, i, n=3) Now solve for i using trial and error method Try 10%: $500 = ? $272 + $247 + $156 = $669 (not equal) Try 20%: $500 = ? $250 + $208 + $116 = $574 (not equal) Try 30%: $500 = ? $231 + $178 + $91 = $500 (equal)  i = 30% The desired return on investment is 15%, the project returns 30%, so it should be implemented