RFQ Installation Plan PIP-II Meeting, 14-July-2015 C. Baffes for R. Andrews, A. Chen, Y. Czajkowski, S. Kazakov, R. Pasquinelli, D. Peterson, O. Pronitchev,

Slides:



Advertisements
Similar presentations
PROJECT MANAGEMENT PROJECT MANAGER ENGINEERING MANAGER PROCUREMENT MANAGER CONSTRUCTION MANAGER.
Advertisements

Project Managers Update Roy Preece Particle Physics Department, STFC MICE Video Conference, 18 th September 2014.
Status of the AFC at RAL Tom Bradshaw John Cobb Wing Lau Matt Hills Elwyn Baynham Mike Courthold Victoria Bayliss MICE Project Board 28 th June 2011.
FAC, 10/12/06 D. Schultz 1 e-Beams Systems Update Linac Injector Undulator Production MMF commissioning ARR David Schultz.
Marion M. White Undulator System 07 April 2005 LCLSLCLSLCLSLCLS Undulator System Tests Marion M. White ANL-ASD-LCLS.
Global Magnet Systems including Field Mapping MICE Project Board 28 th June 2011 M Courthold – RAL R Preece - RAL.
1 MICE PM Report Installations to date Future installation work Preparations for Phase Two Target status MICE Video Conference, 22nd May, 2008.
DCal Meeting
D. Schultz FAC 6/17/08 1 e-Beams Systems Update People Progress the last review LTU and Dump Installation Status Undulator.
K. Long, 27 June, 2015  Target K. Long, Monday, 06 July 2009.
Stephen Milton Undulator System 20 April, 2006 LCLS Undulator System Update S. Milton, ANL FAC, April 20 th, 2006.
1 BROOKHAVEN SCIENCE ASSOCIATES NSLS-II Accelerator Installation Plan Gregory Fries Project Engineer, Accelerator Systems Division CFAC Review of NSLS-II.
LHC Crab Cavities - Phase 1 - Schedule 2008 Mini Workshop - reminder Activities & Planning Planning Remarks 1 LHC-CC09, 3rd Crab Cavity Workshop - Session.
Single-Cavity Module Installation at MuCool Test Area Yağmur Torun MICE Collaboration Meeting February 15, 2013.
EATM12-08 Contribution NA62 Francois Butin, Lau Gatignon / EN-MEF 4 September 2012.
FAC, 10/12/06 D. Schultz 1 Readiness for 2007 Startup Linac Injector Controls ARR David Schultz.
ILCTA_NML Progress at Fermilab Jerry Leibfritz September 10, 2007.
Proton Plan PMG 3/22/07 E Prebys 1 Proton Plan Status February Eric Prebys.
Cryo Update and Power Distribution Alan Bross Tracker Parallel – MICE CM October 7, 2007.
1 BROOKHAVEN SCIENCE ASSOCIATES Preparations for Linac Commissioning Ray Fliller, Associate Physicist 8 th ASAC meeting for NSLS-II Project May 10-11,
+ STAR HFT Upgrade – Installation and Integration Rahul Sharma Brookhaven National Laboratory.
1 BROOKHAVEN SCIENCE ASSOCIATES Transition to Installation Erik Johnson ASD Deputy Director and Interface Manager NSLS-II CFAC Meeting November 9-10, 2009.
RFQ Fabrication Plan, Schedule and QC PXIE RFQ Fabrication Readiness Review LBNL – June 26, 2013 Steve Virostek - Engineering Division Lawrence Berkeley.
Schedule and Work We are moving into a very intensive 4 months with a lot of work to be carried out Electrical services to the devices – after the South.
HINS 6-Cavity Test 3 Month Plan Jan 12, Current Schedule 2-3 day shutdown scheduled to start Jan 18 (Wednesday) to upgrade BPM system and reinstall.
Ronald Lipton PMG June Layer 0 Status 48 modules, 96 SVX4 readout chips 6-fold symmetry 8 module types different in sensor and analog cable length.
Spectrometer Solenoid Schedule MICE Schedule Review May 23 rd 2011 Roy Preece (STFC RAL, LBNL)
Status and schedule for the H - source upgrade at HINS beam line HINS Meson meeting January 5 th, 2012 L. Prost (most inputs from Steve Hays & Alex Chen)
Global Design Effort Introduction and goals of the meeting Andrei Seryi, Toshiaki Tauchi Fifth ATF2 Project Meeting December 19-21, 2007.
CM27 – 8 th July 2010 LH2 System Progress and Future Plans M Hills T Bradshaw M Courthold I Mullacrane P Warburton.
TOB meeting, TOB meeting 20 September 2005, Antti Onnela: TOB mechanical integration status and plans n TST-TOB-TIB integration exercise n.
PASI OsC meeting 12th July 2012
IBL CO 2 cooling planning 03 July 2013 Jan Godlewski, Bart Verlaat, Lukasz Zwalinski 1
1 BROOKHAVEN SCIENCE ASSOCIATES Accelerator Systems Installation F. Willeke, ASD Director 6 th ASAC October 22-23, 2009.
Proton Plan PMG 2/22/07 E Prebys 1 Proton Plan Status January Eric Prebys.
Technical Readiness Review of the n-3He Experiment Seppo Penttila ORNL P-div At SNS Jan
Preproduction: Engineering Design
Technical Board Summary Alan Bross MICE CM17 CERN February 25, 2007.
NML/RFCA002 Status ILC Cryomodule meeting 3 July 2012 E. Harms.
CMTF Infrastructure Jerry Leibfritz PIP-II Machine Advisory Committee 9-11 March 2015.
CMTF GROUNDING FOR PIP-II K. Carlson PXIE Electrical Coordination Meeting December 19 th, 2013.
PX FY14 Budget PXIE Infrastructure R. Stanek J. Leibfritz.
PXIE Beam Instrumentation Status Update – Preparing for MEBT 1.1 Beam Vic Scarpine Feb. 9, 2016.
DTL prototype summary and production sequence F.Grespan LNL _06_22 CDR.
RFQ Installation Status 10/27/2015 October 27, 2015 Jim Steimel & Curtis Baffes.
PXIE Layout and Infrastructure Building, Cryogenics, Utilities… Rich Stanek On behalf of the CMTF Team PXIE Collaboration Meeting November 28, 2012.
PIP-II Environment, Safety, Health & Quality Assurance Strategy John Anderson Jr. DOE Independent Project Review of PIP-II 16 June 2015.
Machine Protection Systems (MPS) Arden Warner, and Jim Steimel Project X Machine Advisory Committee March 18-19, 2013.
LHCb CO 2 cooling meeting Burkhard Schmidt – May 20,
V Thermo-siphon Workshop Test protocol Jan Godlewski PH/DT-PO On behalf of thermo-siphon working group
ILCTA_NML Progress at Fermilab Jerry Leibfritz August 16, 2007.
LEReC System 1. Project Schedule 2015 shutdown COMPETE! Move beam line equipment from IP 01:00 Install cooling section beam line 2016 shutdown Install.
PIP-II Beam Instrumentation Vic Scarpine PIP-II Machine Advisory Committee Meeting March 2016.
Integration of HWR, SSR1, and Cryo in the PXIE enclosure Curt Baffes PIP-II Collaboration Meeting 09 November 2015.
PXIE RFQ Status RFQ Fabrication Summary Module 2 bead pull test complete (Timer will give a talk next). Vane machining continues. We are.
Proton PMG May 7 th 2015 Cons Gattuso AD Shutdown Manager.
PXIE Ion Source & LEBT Commissioning Update Lionel Prost on behalf of A. Shemyakin, R. Andrews, B. Brooker, K. Carlson, J. Czajkowski, R. D’Arcy, B. Hanna,
Status of Mechanical Design of LEBT Rich Andrews, Matt Alvarez, Tim Hamerla, Danny Snee.
RF Systems and Controls for the LERF CM Tests
Bruno POTTIN, Anne-Catherine CHAUVEAU
CBETA Technical Review
LAT Instrument Test Data Analysis in Context
Francois and Lau EATM 17 July 2012
Safety Readiness Review (SRR) Thomas Hansson, ESH
CDS-EL IRR Closeout 28 March 2019 J.G. Weisend II, Chairman.
ThomX – Commissioning Meeting – 25/01/2018
SC1R Cold Box PDR Assembly Sequence
Polarized 3He target installation
Data Protection Privacy Impact Assessment Project Management Process V0.4 Last updated – 29/01/2019.
Racks PC Rack >> 24 mini and 12 tall PC racks Mini Racks
Presentation transcript:

RFQ Installation Plan PIP-II Meeting, 14-July-2015 C. Baffes for R. Andrews, A. Chen, Y. Czajkowski, S. Kazakov, R. Pasquinelli, D. Peterson, O. Pronitchev, D. Snee, J. Steimel, et al. PIP-II Doc DB ID: PIP-II-doc-5PIP-II-doc-5 1

RFQ Installation Plan Planning and documentation Critical Activities Schedule 2

Planning and Documentation Status Top-level installation drawing (F , draft) Covers overall installation of the RFQ in the beamline References some lower-level installation drawings Lower-level drawings are mostly still in work Installation Plan document (ED , draft) Outline of installation sequence RFQ handling/rigging instruction In technical review for rigging safety Schedule 3

RFQ Installation Plan Planning and documentation Critical Activities Focus on critical path and work requiring access to the RFQ itself Shown here ~chronologically Schedule 4

Shutdown Start 5 We need to start a shutdown and begin to clear the cave ~2 weeks prior to RFQ arrival Biggest impact is on LEBT operation and RF device testing Affects power test of full 50ohm kicker – need to relocate this test Working plan is to start the shutdown on M 8/03/15

RFQ Shipping Frame: Pneumatic vibration isolation RFQ transport by LBL 6 M. Hoff, LBL Dedicated transport on LBL-truck Vibration-isolating shipping frame

Unloading at CMTF 7 Forklift shipping frame off truck and set on CMTF dock SNS LBL June 2002 M. Hoff, LBL

Craning off shipping frame 8 A delicate operation due to high center of gravity of RFQ Detailed instructions and stability assessment included in the installation plan Crane to a staging area outside of PXIE cave SNS LBL June 2002 M. Hoff, LBL J

Installation of LEBT scraper 9 Done outside of cave before integration with beamline Risks largely retired by hardware tests in the LEBT After this work and associated survey is done, RFQ moves into the cave Andrews, Snee

Coupler installation 10 Couplers assembled piecewise on the RFQ As-found survey allows spec. of coax lengths

Installation of vacuum hardware 11 Assembly allows final leak check and beginning of vacuum conditioning

RFQ Cooling 12 Cooling lines installed late in the process because they will restrict physical access Biggest single installation task Current status: Parts mostly on hand Distribution manifolds constructed Skids need to be constructed and installed Distribution manifolds

RFQ Coax 13 Routing has been defined Most pieces will be available well before need Significant re-use of HINS coax Order of new pieces based on design lengths in coming weeks Final two pieces to be ordered to a surveyed length after RFQ installation and final alignment

Coax routing and alignment scheme 14

Parallel work 15 There is lots of other work to do to prepare for RFQ conditioning To a large extent, it can proceed in parallel with the steps I’ve highlighted Cabling Instrumentation Interlocks LLRF Etc.

RFQ Installation Plan Planning and documentation Critical Activities Schedule 16

17 RFQ Delivery: Assume 8/17 RFQ in cave and rough aligned 8/31 Couplers installed RFQ under vacuum 9/11 Cooling system work complete 10/16 Last piece of coax installed 10/22 RFQ ready for conditioning

RFQ Installation Plan Questions/Discussion? 18