1 2/19/2009 PHENIX WEEKLY PLANNING 2/19/2009 Don Lynch.

Slides:



Advertisements
Similar presentations
1 4/9/2009 PHENIX WEEKLY PLANNING 4/9/2009 Don Lynch.
Advertisements

2/6/ PHENIX WEEKLY PLANNING Feb. 6, 2014 Don Lynch.
1 12/3/2009 PHENIX WEEKLY PLANNING 12/3/2009 Don Lynch.
1 05/14/2009 PHENIX WEEKLY PLANNING 5/14/2009 Don Lynch.
PHENIX WEEKLY PLANNING 1/4/2007 Don Lynch. 1/4/207 Weekly Planning Meeting 2.
2/2/20121 PHENIX WEEKLY PLANNING 2/2/2012 Don Lynch.
1 3/19/2009 PHENIX WEEKLY PLANNING 3/19/2009 Don Lynch.
PHENIX WEEKLY PLANNING 2/15/2007 Don Lynch. 2/15/207 Weekly Planning Meeting 2 Remaining Schedule StartComplete Cosmic Ray Run (Run 6.9)In Progress All.
2/9/20121 PHENIX WEEKLY PLANNING 2/9/2012 Don Lynch.
PHENIX WEEKLY PLANNING 5/17/2007 Don Lynch. 5/17/2007 Weekly Planning Meeting 2.
PHENIX WEEKLY PLANNING 5/31/2007 Don Lynch. 5/31/2007 Weekly Planning Meeting 2 Schedule End of Run Party 6/29/07 Next Maintenance Day 6/6 or 6/13/07?
1 7/02/2009 PHENIX WEEKLY PLANNING 7/2/2009 Don Lynch No Meeting this week due to July 4 th holidays. Slides have been updated. Next planning meeting will.
1 3/12/2009 PHENIX WEEKLY PLANNING 3/12/2009 Don Lynch.
1 2/12/2009 PHENIX WEEKLY PLANNING 2/12/2009 Don Lynch.
1 1/22/2009 PHENIX WEEKLY PLANNING 1/22/2009 Don Lynch.
PHENIX WEEKLY PLANNING 2/21/2008 Don Lynch. 2/21/2008 Weekly Planning Meeting2 Run 8 Task Schedule ItemStartFinish RPC supportOn GoingOn Going CM Crane.
1 1/13/2011 PHENIX WEEKLY PLANNING 1/13/2011 Don Lynch No Meeting Today Due to snow shortened work week, today’s planning meeting has been cancelled. Slides.
1/5/20121 PHENIX WEEKLY PLANNING 1/5/2012 Don Lynch.
1 3/5/2009 PHENIX WEEKLY PLANNING 3/05/2009 Don Lynch.
PHENIX WEEKLY PLANNING 4/10/2008 Don Lynch. 04/10/08 Shutdown ’08 Schedule Purge Flammable Gas, Magnet & DAQ TestsDone Remove lock-out & open shield wallDone.
1 4/2/2009 PHENIX WEEKLY PLANNING 4/2/2009 Don Lynch.
1 3/3/2011 PHENIX WEEKLY PLANNING 3/3/2011 Don Lynch.
PHENIX WEEKLY PLANNING 3/8/2007 Don Lynch. 3/8/207 Weekly Planning Meeting 2 Schedule Cosmic Ray Run (Run 6.9) Continues…. All Up Commissioning In Progress.
12/29/20121 PHENIX WEEKLY PLANNING 12/29/2011 Don Lynch.
PHENIX WEEKLY PLANNING 2/14/2008 Don Lynch. 1/31/2008 Weekly Planning Meeting2 Run 8 Task Schedule ItemStartFinish RPC supportOn GoingOn Going CM Crane.
1 2/26/2009 PHENIX WEEKLY PLANNING 2/26/2009 Don Lynch.
1 4/16/2009 PHENIX WEEKLY PLANNING 4/16/2009 Don Lynch.
3/6/ PHENIX WEEKLY PLANNING March 6, 2014 Don Lynch.
PHENIX WEEKLY PLANNING 3/27/2008 Don Lynch. 3/27/2008 Weekly Planning Meeting2 Shutdown ’08 Schedule CM Crane ReviewMar Purge Flammable Gas, Magnet.
PHENIX WEEKLY PLANNING 3/22/2007 Don Lynch. 3/22/2007 Weekly Planning Meeting 2 Schedule Re-Start 5 man shifts 3/20/07 Beam: blue ring 3/8/07, in yellow.
PHENIX WEEKLY PLANNING 1/10/2008 Don Lynch. 1/10/2008 Weekly Planning Meeting2 Run 8 Task Schedule ItemStartFinish RPC Tent preparationOn Going1/18 Gas.
PHENIX WEEKLY PLANNING 2/9/06 Don Lynch. Prep Schedule for Run 6 BBC N&S dried, tested re-installed, final tested [DONE] MuTr FEE and anode purge lines.
PHENIX WEEKLY PLANNING 9/14/06 Don Lynch. 9/14/06 Weekly Planning Meeting 2 PHENIX Shutdown Overview Task_NameStart_DateFinish_Date PHENIX Shutdown '065/1/200612/8/2006.
PHENIX WEEKLY PLANNING 12/6/2007 Don Lynch. 12/6/2007 Weekly Planning Meeting2 Run 8 Task Schedule ItemStartFinish RPC Tent preparationOn GoingOn Going.
1 05/07/2009 PHENIX WEEKLY PLANNING 5/07/2009 Don Lynch.
1 3/10/2011 PHENIX WEEKLY PLANNING 3/10/2011 Don Lynch.
PHENIX WEEKLY PLANNING 10/4/2007 Don Lynch. 10/4/2007 Weekly Planning Meeting 2007 PHENIX Shutdown October 2007: Finish MPC South Installation, replace.
2/14/20131 PHENIX WEEKLY PLANNING 2/14/2013 Don Lynch.
PHENIX WEEKLY PLANNING 12/7/06 Don Lynch. 12/7/06 Weekly Planning Meeting 2.
1 12/30/2010 PHENIX WEEKLY PLANNING 12/30/2010 Don Lynch.
PHENIX WEEKLY PLANNING 10/18/2007 Don Lynch. 10/18/2007 Weekly Planning Meeting2 Run 8 Prep Schedule ItemStartFinish MPC South InstallationDoneDone Elec.
3/20/ PHENIX WEEKLY PLANNING March 20, 2014 Don Lynch.
1/26/20121 PHENIX WEEKLY PLANNING 1/26/2012 Don Lynch.
Technical Support /5/08 PHENIX WEEKLY PLANNING 12/5/2008 Don Lynch.
1 10/15/2009 PHENIX WEEKLY PLANNING 10/15/2009 Don Lynch.
PHENIX WEEKLY PLANNING 11/15/2007 Don Lynch. 11/8/2007 Weekly Planning Meeting2 Run 8 Task Schedule ItemStartFinish RPC Tent preparationOn Going11/30.
5/12/11 1 PHENIX WEEKLY PLANNING 5/12/2011 Don Lynch.
PHENIX WEEKLY PLANNING 3/15/2007 Don Lynch. 3/15/2007 Weekly Planning Meeting 2 Schedule Cosmic Ray Run (Run 6.9) Done All Up Commissioning On Going Re-Start.
1 1/8/2009 PHENIX WEEKLY PLANNING 1/8/2009 Don Lynch.
PHENIX WEEKLY PLANNING 3/02/06 Don Lynch. BLM Test.
Technical Support /15/08 PHENIX WEEKLY PLANNING 5/15/2008 Don Lynch.
Technical Support /18/08 PHENIX WEEKLY PLANNING 12/30/2008 Don Lynch.
PHENIX WEEKLY PLANNING 5/7/2007 Don Lynch (Thursday is Monday this week)
1 12/17/2009 PHENIX WEEKLY PLANNING 12/31/2009 Don Lynch.
1 12/17/2009 PHENIX WEEKLY PLANNING 12/17/2009 Don Lynch.
PHENIX WEEKLY PLANNING 5/3/2007 Don Lynch. 5/3/2007 Weekly Planning Meeting 2 Schedule HyTec CM vibration modes test5/23/07 End of Run Party 6/29/07 Next.
1 5/19/2011 PHENIX WEEKLY PLANNING 5/19/2011 Don Lynch.
1 1/29/2009 PHENIX WEEKLY PLANNING 1/29/2009 Don Lynch.
1 7/16/2009 PHENIX WEEKLY PLANNING 7/16/2009 Don Lynch.
3/7/20131 PHENIX WEEKLY PLANNING 3/7/2013 Don Lynch.
Technical Support /16/08 PHENIX WEEKLY PLANNING 10/16/2008 Don Lynch.
PHENIX WEEKLY PLANNING 3/1/2007 Don Lynch March: in like a lion Out like a lamb.
1 6/4/2009 PHENIX WEEKLY PLANNING 6/4/2009 Don Lynch.
1 7/9/2009 PHENIX WEEKLY PLANNING 7/9/2009 Don Lynch.
PHENIX WEEKLY PLANNING 11/8/2007 Don Lynch. 11/8/2007 Weekly Planning Meeting2 Run 8 Prep Schedule ItemStartFinish Elec. Cooling Water upgrade(CA) (under.
PHENIX WEEKLY PLANNING 6/8/06 Don Lynch. 6/8/2006 Weekly Planning Meeting 2 This Week Rec’d TOF West Access: move HBD to Dead Turtle Position Sec’y of.
1 8/20/2009 PHENIX WEEKLY PLANNING 8/20/2009 Don Lynch.
2/20/ PHENIX WEEKLY PLANNING Feb. 20, 2014 Don Lynch.
PHENIX WEEKLY PLANNING 2/14/2008 Don Lynch. 2/14/2008 Weekly Planning Meeting2 Run 8 Task Schedule ItemStartFinish RPC supportOn GoingOn Going CM Crane.
1 2/4/2010 PHENIX WEEKLY PLANNING 2/4/2010 Don Lynch.
Presentation transcript:

1 2/19/2009 PHENIX WEEKLY PLANNING 2/19/2009 Don Lynch

2 2/19/2009 Run Support & Other Ongoing Work Run Technical Support (mechanical, electrical and gas systems As needed  always takes priority RPC Factory Support (continuing) (see slides later) Prep for 2009 Shutdown Design PC1 East maintenance support fixtures design 3/31, fabrication 5/31 NCC prototype design support (on-going med. priority) VTX fabrication tooling design (on-going med. priority) VTX installation design (on-going med. priority) FVTX design/eng’g support (no support requested yet) MMS Scaffolding Design design 2/27, ordering/fabrication 5/1 New Beampipe supports (back logged) RPC3 North installation Prep Installation plan (including installation site prep plan) 2/27 Installation fixture design 4/3 Installation fixture fabrication 6/26 Maintenance & Overhead Tasks Procedure Review/Updates (ongoing) Rack Room, AH, Trailer, Mixing House, etc. (ongoing) ’09 Technical Support

3 2/19/2009 Roof leak in utility bathroom at northwest corner behind tech offices. Roof leak over door between rack room and assembly hall. Trailer bathroom slop sink (for Custodians). Heat wrap tape for trailer bathroom toilet drains to prevent freeze/clogging in winter. New duct heater (This item is in progress and should be completed soon) Improved Rack Room AC performance (This item has been addressed time and again but unsatisfactorily. Currently the AC fails periodically and is repaired only to fail again. On-condition maintenance is not adequate…an engineered solution is needed.) 2009 Building Maintenance Issues

4 2/19/2009 New Beampipe PHENIX SCD Brush- Wellman CAP Still Waiting for new CAP

5 2/19/2009 RPC Factory Support RPC Factory Change in Scope Remaining Action Items:  Review the mechanical design of the burn-in assembly and the dolly system to be used in moving the ½ octant units. Design In Progress, Review to follow  Update the RPC high voltage and gas procedures if necessary (Giannotti, Pisani Jan 30, 2009) In progress  Add individual output valves to the burn-in unit gas schematics (Pisani, Jan 30, 2009) In progress  Get a permit for the R134 added consumption (Pisani, Van Essendelft, Jan 30, 2009) In Progress  Review the flammable compressed gas system piping ( Gaffney, Pisani Jan 30, 2009) To Be Scheduled

6 2/19/2009 RPC Factory Support Tasks: Complete the Dark Current Test Stand (2/27) Order materials for Burn-in Test Stand (2/20) Complete design of Tilting Transport Table (2/13) Done Review needed Order materials for the Tilting Transport Table (2/20) Order additional shelf units for gap, module and RPCstructural component storage (2/20) Design and order environmental control system for Burn-In Test Stand (2/27) Assemble gap & module storage with humidity control existing shelves (2/27), full complement of shelves (3/13) Extend N2 supply to storage shelves (not required) Assemble structural component storage existing shelves (2/27), full complement of shelves (3/13) Assemble tilting transport table 3/6 Assemble burn-in test stand (bike rack) 3/27 Extend gas, electric and safety systems to Burn-In Test Stand (4/3)

7 2/19/2009 RPC Factory Module and Gap Storage with humidity Control Burn-in test stand (bicycle rack) Tilt Tables (2) for Assembly and Handling Gaps modules and ½- octants Detail parts storage for Module and ½ octant structural parts

8 2/19/2009 RPC Factory Dark Current Test Stand under construction Also working on: - a burn-in test stand for ½ octants - additional storage for gaps modules and structural detail parts - transport table/cart

9 2/19/2009 RPC Factory Half-Octant Assembly Tilt Table

10 2/19/2009 Shutdown ’09 Major tasks (expect 5 month shutdown): 2009 shutdown Begins April 10, or July 1, 2009 or July 15 or ????? End run, remove wall, MuID collars down, EC to AH (3 weeks) Install Station 1 South scaffolding (1 week) Install Station 2/3 scaffolding (2 weeks) PC1 East repair (4 weeks) Install stations 1, 2 and 3 south MuTrigger FEE’s (12 weeks) MuTr decapacitations: station 3 south (3 weeks) RPC Station 3 North (12 weeks) Prep for future upgrades/existing equipment maintenance & Repair (as necessary) Shutdown ’09

11 2/19/2009 Safety, Security, etc. 1. PHENIX Annual Safety Review Remaining Action Items: Settle the CM magnet ladder railings (Lynch, Pearson Phillips Feb 4, 2009) Don and Dave to resolve Update the documented work procedures. (Lynch) Ongoing Add HSSD to the 1008 Assembly Hall (Phillips/ Levesque Mar 1, 2009) This is a C-A issue. 2. ICE = In Case of Emergency Add emergency contact(s) to your cell 3. PHENIX AWARENESS is updated. May not be updated on web yet. ODH addressed Contact list changed to web reference If in doubt about planning contact any PHENIX work coordinator

12 2/19/2009 Where To Find PHENIX Engineering Info Links for the weekly planning meeting slides, long term planning, pictures, videos and other technical info can be found on the web site: It’s going to be busy during the run, Then busier still during the ’09 shutdown