10 December 2015 1 Summary: Updating of the activities carried out on-site (Done) in NOVEMBER List activities on going (Next steps) and scheduled for DECEMBER.

Slides:



Advertisements
Similar presentations
IX- CONSTRUCTION PLANNING
Advertisements

CFS TIME SCHEDULE EDR - CFS Europe – Kick-Off Meetings Kick-Off Meetings, CERN, 3, 4, 5 September ILC PROJECT ENGINEERING DESIGN REPORT CFS Europe.
Public Information Meeting #6 City of Fargo Flood Risk Reduction Projects Rose Creek Coulee October 9, 2012.
Nov. 19, 2008 ILC08 Global Design Effort 1 Status Report Alternative Siting and Tunnel Design Tom Lackowski.
Cassidy Elementary – Renovation Architect: Tate.Hill.Jacobs: Architects General Contractor: D.W. Wilburn, Inc. Substantial Completion Date:August, 2010.
1 BROOKHAVEN SCIENCE ASSOCIATES Central Chilled Water Facility – Phase II Alan Raphael MPO Project Manager CFAC Committee Review November 9, 2009 Sub-basement/Pipe.
Plasma Wakefield (AWAKE) Project Meeting 18 October 2012 Civil Engineering Feasibility Issues for the West Area EDMS : John Osborne GS-SE.
SNOLAB Facility Status Fraser Duncan SNOLAB Workshop 27 August 2009.
Breaching the Mahar Regional School Dam Presentation to Ralph C. Mahar Regional School Committee GZA GeoEnvironmental, Inc. February 9, 2011.
CENF – Civil Engineering Extension B887 CERN: An accelerator complex unique in the world -Prevessin site complex- -EHN1 Extension Area- EHN1 Extension.
Industry information day INDUSTRY INFORMATION DAY Assembly & Installation Laurent Schmieder Buildings Infrastructure and Power Supplies Project.
Jess Albino Facility Advisory October 29, 2007 FACILITY ADVISORY COMMITTEE PLENARY CONVENTIONAL FACILITIES UPDATE October.
John Osborne GS/SE March 2013
Chapter 2b Foundations Shallow & Deep Foundations.
IFR End Door Enhancement Mechanical Engineering Status & Installation Issues H. James Krebs June 23, 2001.
National Energy Technology Laboratory U. S. Department of Energy Project Kickoff Presentation December 16, 2003 Ken H. Green Principal Investigator Development.
1 BROOKHAVEN SCIENCE ASSOCIATES Ring Building Construction Status Michael P. Bromfield Construction Engineer NSLS II Conventional Facilities Advisory Committee.
Villanova University Dept. of Civil & Environmental Engineering CEE Capstone II Structural Engineering 1 CEE Capstone II Structural Engineering.
19 February Summary: Updating on the activities completed (Done) since the last meeting List activities on going (Next steps) and related Actions.
1 CV4902- Construction Methods Dr David Chew. 2 Construction Considerations Site layout plan Outline of entire construction process Details of temporary.
Specification & Quantities Estimating Lecturer Maha Muhaisen College of Applied Engineering& Urban Planning.
CLIC Implementation Studies Ph. Lebrun & J. Osborne CERN CLIC Collaboration Meeting addressing the Work Packages CERN, 3-4 November 2011.
09 July EHN1 civil engineering project status (JUNE) Summary: Updating of the activities carried out on-site (Done) in JUNE List activities on going.
06 August EHN1 civil engineering project status (JULY) Summary: Updating of the activities carried out on-site (Done) in JULY List activities on.
GIF in EHN1- layout, construction and schedule Adrian Fabich, EN-MEF-LE GIF users meeting, 12 th February 2014.
1 1. Some recent views ( ) 2 Linac tunnel
PROJECT PLANNING AND SCHEDULLING
P ROJECT M ANAGEMENT. Case study Assumptions Methodology Discussion.
East Area, M2, K12 Lau Gatignon / EN-MEF, EATM
CENF – Civil Engineering Extension B887 Status – 02 October 2014 Done: (1/2) Preliminary civil engineering drawing and Functional specification approved.
Geodetic Monitoring of the Deformation of a 50,000 t Sugar Storage Tank Founded on 124 Long Bored Piles P. Savvaidis and I. Ifadis Laboratory of Geodesy.
Summary of the WA104, T600 overhauling programme C. Montanari – INFN-PV, Italy M. Nessi – CERN, Switzerland weekly meeting, December 18,
The Building 180 Cryogenic infrastructure water cooling system Status Update Stefano Moccia, EN-CV Coordination meeting 14/10/15.
The four basic types of structures are :
EHN1 Roof consolidation EATM F. Magnin – GS/SE/CEB.
Consolidation activities for GS-SE Luigi Scibile GS-SE Accelerator Consolidation Workshop, EDMS:
G. Carboni - Muon Meeting – Muon Meeting 12/ Agenda IntroductionGiovanni (30’) GEM and TDR AddendumWalter (20’) Update on M1 ratesAlessia.
Pine Integrated Network: Education, Mitigation, and Adaptation project (PINEMAP) is a Coordinated Agricultural Project funded by the USDA National Institute.
22 October Summary: Updating of the activities carried out on-site (Done) in SEPTEMBER List activities on going (Next steps) and scheduled for OCTOBER.
15 January Extension of Building Neutrino Platform General Meetings N.Lopez – M.Manfredi EHN1 civil engineering project status Summary: Updating.
Cassidy Elementary – Renovation Architect: Tate.Hill.Jacobs: Architects General Contractor: D.W. Wilburn, Inc. Substantial Completion Date:August, 2010.
CENF – Civil Engineering Extension B887 Status – 18 September 2014 Done: (1/2) Preliminary civil engineering drawing and Functional specification approved.
1 UK PM Report Costs & Schedule Alan Grant, STFC.
General Infrastructures Services Department Civil Engineering planning for LSS4 Option, presented at review workshop 30/7/ months Planning and Resources:
CENF meeting 5 th February STATUS CE engineering contract running : – phase 1 : tender drawings – phase 2 : execution drawings – Phase 3 (option)
EGEE is a project funded by the European Union under contract INFSO-RI NA5 M. Heikkurinen NA5 Activity Manager All Activity Meeting, 13 th September.
ILC-HiGrade annual meeting - 12 October 2011 ILC-HiGrade Meeting Cavity-Treatment at CEA Saclay (WP6) F. Eozénou.
EN-CV Progress EHN1 Extension Project Jérôme Rodary EN-CV-PJ 2016/01/21.
CENF CIVIL ENGINEERING UPDATE : - SITE INVESTIGATION - CALL FOR TENDER FOR DESIGN & CONTRACT ADMINISTRATION SERVICES - 3D VISUALS FOR SURFACE STRUCTURES.
CENF CIVIL ENGINEERING UPDATE : - SITE INVESTIGATION - CALL FOR TENDER FOR DESIGN & CONTRACT ADMINISTRATION SERVICES John Osborne GS/SE 16 May 2013.
OsC mtg 15/10/2014 MICE Step IV Alan Grant. Content Step IV – Construction Status – Finances – Schedule – Risks – Summary 2.
HiRadMat : Coordination meeting 02 October S. Evrard 1 News from project team General information : access,... PR532 repair : plans Existing services.
19 February Extension of Building Neutrino Platform General Meetings N.Lopez – M.Manfredi EHN1 civil engineering project status Summary: Updating.
Sale of material salvaged from the LEP experiments 4 large experiments ALEPH DELPHI L3 OPAL The 4 detectors are situated in caverns (100 m under ground.
EHN1 – EN/EL Progress update J. Devine 25/02/16. Integration – Jura Substation Position updated to avoid clash with door. Meeting next week for Civil.
WP 17.1 Civil Engineering Platform height / vs option Status on M. Manfredi on behalf of WP17.1 team.
Infrastructure EHN1 extension Lau Gatignon, 7 March 2016.
21 January Summary: Updating of the activities carried out on-site (Done) in DEC + ½JAN List activities on going (Next steps) and scheduled till.
Miller Driscoll Building Committee Construction Update Thursday April 7, :00 PM - 7:00 PM Presented by: Turner Construction, CMA 1 Additions & Alterations.
WP 17.1 Civil Engineering Point 1 - Networks LS2 COMMITTEE – CERN – Pieter Mattelaer (SMB-DI)
25 June EHN1 civil engineering project status (MAY) Summary: Updating of the activities carried out on-site (Done) in MAY List activities on going.
CERN Steve Kettell DUNE Collaboration Meeting January 12, 2016.
September 5, Burkhard Schmidt Integration and Installation Outline: Integration and Infrastructure issues -Suspended platforms -Cable chains -Beam.
22/09/2011 ADO-PO section meeting ADO : Atlas Detector Operation PO : Project Office R. Vuillermet.
The LBNF cryostats Marzio Nessi, CERN 16 March 2017.
SMR 21/09/2017 P. Fessia.
CE Status: Activities executed until 03/08 and ongoing
EHN1: CE Integration process updating
Organics Waste Processing Facility Construction Progress Update December 15, 2010
How to perform Time Impact Analysis / Window Analysis in Primavera P6
Presentation transcript:

10 December Summary: Updating of the activities carried out on-site (Done) in NOVEMBER List activities on going (Next steps) and scheduled for DECEMBER Final consideration EHN1 civil engineering project status (NOVEMBER) 40 th EHN1 extension coordination & 10th EHN1 Detector integration meeting N.Lopez – M.Manfredi

Done (1/2): (1) PITS EXECUTION Excavation/Execution first ties level: (100% completed). Both pits done and in tension. Excavation/Execution second ties level: (0%=>100% completed). Pit B and in tension Internal DW surface Leveling / Reparation: (20%=>50% completed). Both pits ongoing. - Phase 4: step by step - (...). PIT A PIT B Pits ground excavation: (0%=>60% completed). Pit A done. Pit B ongoing. Pits’ lower drainage system: (0%=>40% completed). Pit A done. Pit B after excavation Pits’ slab system: (0% completed). Pit A first. 10 December EHN1 civil engineering project status (NOVEMBER) 40 th EHN1 extension coordination & 10th EHN1 Detector integration meeting N.Lopez – M.Manfredi

Done (2/2): (4) SLAB SYSTEM Swallow trenches execution: (0% completed). Jura side to start S1 S2 S3 S4 S5 -S4, S5 start in December after access ramp diplacement -S1, S2, S3, S6 ongoing - -S1, S2, S3, S6 - Backfilling between slabs: (0% completed). Upper slab concreting process: (0% completed). Earthworks allowing site preparation: (80%=>100% completed). Walls above DW’s crown beam, around pits: (0%=>50% completed). S6 Double slab and trenches drainage system: (0%=>50% completed). Lower slab concreting process: (80%=>90% completed). Remains part of S1&S3 10 December EHN1 civil engineering project status (NOVEMBER) 40 th EHN1 extension coordination & 10th EHN1 Detector integration meeting N.Lopez – M.Manfredi

Next Steps: Activities scheduled for December (3) PITS:  (B) Excavation up to the bottom level by mid-December. Levelling/Reparation follows until end-December.  (B) Installation lower drainage system by end-December + line concrete.  (A) Levelling/Reparation by mid-December. Execution slab system follows until end-December. (4) SLAB SYSTEM:  S4, S5 to start following pits’ access ramp displacement. Lower slab and drainage system by end-December.  Trenches on S2, S3 to start. Formworks and concreting process.. 07/12/201505/11/ December EHN1 civil engineering project status (NOVEMBER) 40 th EHN1 extension coordination & 10th EHN1 Detector integration meeting N.Lopez – M.Manfredi

Final Consideration: CE planning still in line with the 9 weeks of delay announced in November for the WP1 activity. Planning has been reviewed given priority to the execution of the pits (critical path). Following re-organization of some tasks and possibility of several superimpositions, contractors estimate to potentially retrieve 3 weeks at most. Thus, CE Handover is shifted by 6 weeks (half-August 2016), according to the new planning. Work site situation normalized after execution and defects reparation of the DWs complex. Minor reparation are expected now within the last portion to be excavated. Coordination of the CE integration issues (3D Catia model updating, ECR drafting/circulation, EL/CV services in the TG/Pumping station, etc..) will be finalized. Technical and on-site support to the MOE, coordination with CERN group, analysis/review of technical documents/drawings, weekly and monthly reports on-going. Next status of the works end-December. 10 December EHN1 civil engineering project status (NOVEMBER) 40 th EHN1 extension coordination & 10th EHN1 Detector integration meeting N.Lopez – M.Manfredi