LBNE Reconfiguration Engineering/Cost Working Group Report Jim Strait Fermilab LBNE Project Manager Deputy Chair, Cost and Engineering Working Group Fermilab.

Slides:



Advertisements
Similar presentations
J. Strait Fermilab October 21, 2005 The Neutrino Detector of the Future: A Massive Liquid Argon TPC.
Advertisements

LBNE Reconfiguration Jim Strait, LBNE Project Director Fermilab Community Advisory Board August 23, 2012.
J. Strait LBNE Status and Issues Jim Strait LBNE Project Director US-EU Meeting on SBN Program 4 April 2014 LBNE-doc-8762.
An accelerator beam of muon neutrinos is manufactured at the Fermi Laboratory in Illinois, USA. The neutrino beam spectrum is sampled by two detectors:
NuMI Offaxis Costs and Whither Next Stanley Wojcicki Stanford University Cambridge Offaxis workshop January 12, 2004.
Experimental hall in Japanese mountain site Y. Sugimoto ILD MDI/Integration 1.
Long-Baseline Neutrino Experiment James Strait LBNE Project Director Public Information Meeting May 23, 2013 LBNE-doc-7321.
LBNE Status 1 Jim Strait, Fermilab LBNE Project Director 2 nd ESSnuSB Open Meeting May 2014 LBNE-doc-9102.
July 19, 2003 HEP03, Aachen P. Shanahan MINOS Collaboration 1 STATUS of the MINOS Experiment Argonne Athens Brookhaven Caltech Cambridge Campinas Dubna.
Fermilab Implementation of DOE Critical Decision Process FRA Project Management System Presentation by L Edward Temple Jr Head, Office of Project Management.
LBNE Reconfiguration Workshop – April 2012 FD Assumptions and Cost Estimate 1 Bruce Baller.
Fermilab Neutrino Beamline to DUSEL Mike Martens Fermilab PAC November 3, 2009.
David Finley / LArTPC Group Meeting / June 13, Fermilab Slide 1 LArTPC Detector Costs Context History Next (perhaps) steps.
NuMI NuMI Overview NBI 2002 S. Childress (FNAL) 14 March ‘02 NuMI / MINOS Overview.
LBNF Neutrino Beam Jim Strait, Fermilab For the LBNF/DUNE Team
Greetings to Veljko from Fermilab December 9, 2010.
WP2 Superbeam Work Breakdown Structure Version 2 Chris Densham (after Marco Zito version 1 )
Executive Session Director’s CD-1 Review of the Mu2e Project April 3, 2012 Elaine McCluskey.
Mu2e Cost and Schedule Ron Ray Mu2e Project manager Fermilab PAC Meeting November 3-4, 2008.
Executive Session Director’s CD-1 Review of the LBNE Project September 25, 2012 Jim Yeck.
Long-Baseline Neutrino Facility LBNF LBNF/DUNE Logistics Workshop Summary Mike Headley August 19, 2015.
Long Baseline Experiments at Fermilab Maury Goodman.
Future Neutrino Physics Mitch Soderberg Fermilab Institutional Review June 6-9, 2011.
Cost and Engineering Working Group Introduction Jim Strait Fermilab LBNE Project Manager Deputy Chair, Cost and Engineering Working Group LBNE Reconfiguration.
Fermilab Neutrino Program Jim Strait Neutrino Discussion at CERN 26 November 2013.
1 Global Design Effort TILC08 - WG1 Summary WG-1: Cost Reduction Studies J. Carwardine, T. Shidara, N. Walker (For WG-1 participants)
TILC08 - WG1 Summary Global Design Effort 1 TILC08 仙台 GDE 会議 WG-1 活動報告 GDE 活動報告会 3月11日10:00- 3号館7階会議室 設楽
Global Design Effort - CFS ILC Accelerator Design and Integration Meeting 1 ILC AD&I MEETING CONVENTIONAL FACILITIES AND SITING GROUP UPDATE V.
Neutrino Physics Opportunities for Fermilab Steering Group 6/12/07 Andy Lankford UC Irvine.
Overlap of Project X and Beamline to DUSEL June 2, 2008.
F NuMI Beamline Accelerator Advisory Committee Presentation May 10, 2006 Mike Martens Fermilab Beams Division.
PIP-II: Why a new accelerator? Paul Derwent Fermilab Community Advisory Board 23 July 2015.
International Design Study for a Neutrino Factory in the 5 Year Plan A. Bross NFMCC CM January 15, A. Bross NFMCC CM January 15, 2009.
LAr1 Plans at FNAL Bruce Baller - Fermilab. Outline LAGUNA Meeting - Mar  LBNE LAr detector overview  Prototyping plan  1 kton prototype.
News Y2K June 25, Summary of June 12 Face-to-Face Meeting.
Plan to go forward Peter Wilson SBN Program Coordinator 27 September 2014.
Low Background Studies at the Soudan Underground Laboratory-9/20/ Low Background Studies at the Soudan Underground Laboratory The Soudan Underground.
4/27/06 1 US LHC ACCELERATOR RESEARCH PROGRAM brookhaven - fermilab – berkeley - slac US LARP Inner Triplet Cryogenics and Heat Transfer LARP Collaboration.
2 July 2002 S. Kahn BNL Homestake Long Baseline1 A Super-Neutrino Beam from BNL to Homestake Steve Kahn For the BNL-Homestake Collaboration Presented at.
Long-Baseline Neutrino Facility LBNF Cryostats Systems Requirements on FSCF Marzio Nessi LBNF/DUNE DOE/SC CD-3a Director’s Review October 27-29, 2015.
NUMI NUMI/MINOS Status J. Musser for the MINOS Collatoration 2002 FNAL Users Meeting.
More material for P5 Milind Diwan for the Homestake neutrino detector group 3/1/2008.
Conventional Facilities for the Far Detector Options Assumptions and Cost Estimates T. Lundin April 25, 2012 LBNE Reconfiguration Workshop - 25, 26 - April-2012.
LBNE Project 1 Jim Strait, Fermilab LBNE Project Director LAGUNA-LBNO General Meeting 10 February 2014.
Long-Baseline Neutrino Facility LBNF LBNF/DUNE Project 29 September 2015.
News from LBNF C. J. Mossey, LBNF Project Director DUNE Collaboration Meeting - South Dakota School of Mines and Technology 19 May 2016.
Mike Andrews May 10, Week 54 NuMI Activities Initial test controls on the MI65 RAW exchange skid Complete hydrostatic test of the MI65 exchange.
Long-Baseline Neutrino Facility LBNF Far Site Conventional Facilities (FSCF) Scope and Interface Overview Tracy Lundin as borrowed from Headley & Willhite.
Long-Baseline Neutrino Facility LBNF Beamline optimization schedule Vaia Papadimitriou LBNF Beamline Manager Accelerator and Beam Interface Group Meeting.
MARS15 Studies of Impact of LBNF Target/Horn Optimization on the Hadron Absorber 6 th High Power Targetry Workshop Merton College, Oxford April 12, 2016.
Neutrino Beamline Scaling Robert Zwaska Fermilab June 4, 2014 PIP-II Collaboration Meeting.
Neutrinos from Stored Muons STORM physics with a μ storage ring.
Long-Baseline Neutrino Facility LBNF Update: LBNF EVMS Implementation for CD-3a Elaine McCluskey, LBNF Project Manager Bob O’Sullivan, Project Controls.
K. Long, R. Roser, 23 July 2014 Report from the Neutrino Summit.
Long-Baseline Neutrino Facility LBNF LBNF Project C. J. Mossey, LBNF Project Director 49 th Annual Fermilab Users Meeting 16 June 2016.
Beamline for the LBNE Project Heidi Schellman for the LBNE collaboration.
Long-Baseline Neutrino Facility LBNF LBNC: Far Site Update and Planning Mike Headley LBNF Far Site Facilities Project Manager January 11, 2016.
DUNE-UK Mark Thomson University of Cambridge DUNE-UK Meeting, UCL May 15, 2015.
Long-Baseline Neutrino Facility LBNF News and brief overview of Beamline plans for the next few months Vaia Papadimitriou Beamline Technical Board Meeting.
ICARUS-LBNE project A. Guglielmi 1.LBNE-ICARUS Padova meeting 2.SPS-C C. Rubbia presentation.
1 DOE Independent Project Review Critical Decision-3a Long-Baseline Neutrino Facility/ Deep Underground Neutrino Experiment (LBNF/DUNE) Project DOE Executive.
IEFIG update Joe Lykken | iEFIG Chair ELBNF IB phone meeting | 6 March 2015.
1 Sam Childress. 2 S. Childress NNN11 Existing Fermilab Neutrino Beams 120 GeV NuMI 8 GeV BNB 2 J. Strait.
Long-Baseline Neutrino Facility LBNF Elaine McCluskey, LBNF Project Manager Fermilab PAC Meeting 23 June 2015.
LBNE Project Scope, Cost, Schedule and International Involvement 1 Jim Strait, Fermilab LBNE Project Director P5 Meeting 3 November 2013.
Experimental Hall in Mountain Regions
Head, Office of Project Management Oversight (OPMO)
J. Musser for the MINOS Collatoration 2002 FNAL Users Meeting
News and brief overview of Beamline plans for the next few months
Fermilab Proton Beams: Program Perspectives Greg Bock Fermilab Science and Engineering at Henderson-DUSEL Capstone Workshop Stony Brook May 5,
Presentation transcript:

LBNE Reconfiguration Engineering/Cost Working Group Report Jim Strait Fermilab LBNE Project Manager Deputy Chair, Cost and Engineering Working Group Fermilab PAC 20 June 2012 LBNE-doc-6300

Cost and Engineering Working Group Cost and Steering Working Group members Mark Reichanadter (SLAC COO), Chair Jim Strait (FNAL, LBNE Project Manager), Deputy Chair Bruce Baller (FNAL, LAr Far Detector Project Manager) Mike Headley (SURF Director) Marvin Marshak (U of MN, Director of Soudan and Ash River Labs) Christopher Mauger (LANL, LBNE Near Detector Project Manager) Elaine McCluskey (FNAL, LBNE Project Engineer) Bob O’Sullivan (FNAL, LBNE Project Controls Lead) Vaia Papadimitriou (FNAL, LBNE Beamline Project Manager) Jeff Sims (ANL, APS Upgrade Project Managment) Jeffrey Appel (FNAL Directorate), Scientific Secretary Invited to work with the Working Group Tracy Lundin (FNAL, LBNE Conventional Facilities Project Manager) Jeff Dolph (BNL, LBNE Project Systems Engineer) Jim Stewart (BNL, LBNE Water Detector Project Manager) Joel Sefcovic (FNAL, LBNE Project Controls for Conventional Facilities) Plus the support of the full LBNE Team Fermilab PAC, 20 June

Neutrino Beam Design: MI-10 Extraction, Shallow Beam 3 Fermilab PAC, 20 June 2012

Near Detector Design: Liquid Argon TPC LAr Secondary Containment Magnet Coils Muon Detectors Beam  BooNE-type LAr TPC 4 Fermilab PAC, 20 June 2012 Plus an Alternate Design: Straw-Tube Tracker with embedded argon targets

Far Detector Design: LAr TPC Detector Two detectors in a common cavern at 4850 ft. depth Active volume of each detector: 22.4 x 14 x 45.6 m  33 kt fiducial mass TPC design: o 3.7 m drift length o 5 mm wire spacing o three stereo views Beam 5 Fermilab PAC, 20 June 2012

LBNE Project Cost Estimates LBNE has developed a complete Conceptual Design and cost estimate, which has been reviewed many times and found to be sound. Recent Director’s Review stated: Fermilab PAC, 20 June

Reconfiguration Process: Constraints and Assumptions Designs and cost estimates based as much as possible on the reviewed Reference Design. Cost of each phase should be no more than $ M. Cost range (CD-1 level) for first phase should be consistent with CD-0 range of $ M. Annual expenditures should not exceed ~$120M Sanford Lab (SURF), Soudan Lab and Ash River sites all will be operated independently of LBNE. =>Operating costs are not the responsibility of the LBNE Project during its construction. Fermilab PAC, 20 June

System Options Considered LAr Far Detectors of 5, 17 and 34 kt fiducial mass. -Simplified cryo system for underground installations => Drives significant cost reduction in CF as well. Conventional Facilities (CF) to support the 3 detector sizes at -Homestake underground (4850L ≈ 4300 mwe) -Soudan underground (27 th level ≈ 2100 mwe) -On surface at Homestake, Soudan, Ash River LBNE beamline to Homestake -Simplifications to lower cost without loss of functionality -Staging of some aspects for initial 700 kW operation NuMI beamline -Upgraded for 700 kW operation in low energy configuration -Upgraded for operation well beyond design lifetime Fermilab PAC, 20 June

System Options Considered Near Detector – Homestake options -Full LBNE Near Detector -Phase 1 mini Near Detector in 6.7 m diameter “man hole” - Tertiary muon monitors only in phase 1 Near Detector – NuMI options -LBNE-type Near Detector modified to fit in MINOS cavern -Use existing detectors (MINOS, MINERvA, NOvA) in phase 1 Fermilab PAC, 20 June

LAr Cryogenic System Simplification Simplifications in the underground design Move refrigerator compressors to the surface. Argon delivery underground as cold gas rather than liquid => significantly simplified plumbing down the shaft. Cryo pipes down the Ross Shaft rather than Oro Hondo Shaft => shorter piping runs. Net reduction in estimated cost of technical systems ~$40M. Larger reduction in conventional facilities (see next slide) Fermilab PAC, 20 June

Far Detector Underground at Homestake Fermilab PAC, 20 June X X Eliminate Simplify Scale with detector mass General simplification of underground infrastructure Cost reduction ~$320M for full-size 34 kt detector

Far Detector Underground at Soudan Design and cost estimates developed by contractors to U of MN. Two new shafts for safe access and control of ventilation. Requires development of surface facilities at each of the two new shafts. Fermilab PAC, 20 June

Potential locations of new shafts Fermilab PAC, 20 June Existing Shaft

Potential Surface Detector Locations at Soudan Fermilab PAC, 20 June

Candidate Surface Detector Site at Ash River Fermilab PAC, 20 June

Candidate Surface Detector Site at Homestake Fermilab PAC, 20 June

LBNE Neutrino Beam 17 Fermilab PAC, 20 June 2012 Shorten primary beamline, Reduce hill height Simplified target hall and target hall systems

LBNE Beam Cost Reductions (FY2010 $M, estimate uncertainty contingency) Fermilab PAC, 20 June Including all contingency and escalation$110M

NuMI Beamline Need a redesign of target-horn system to operate at 700 kW in low-energy configuration. This and other system modifications ≈ $13M. Radiological / lifetime issues for extended running -Tritium buildup in ground and surface water, either just from integrated running or from possible drainage system problems. -Water cooling system in decay pipe and absorber -Decay pipe window Include allowance of ~$30M for possible preventive mitigation. Fundamental limitations: -Cannot be upgraded to beam power much above 1 MW -Cannot run proton beam much below 120 GeV The only mitigation would be to build a new beamline. Fermilab PAC, 20 June

LBNE Near Detector Fermilab PAC, 20 June Mini Near Detector: Excavate main shaft only

Mini Near Detector in Shaft Fermilab PAC, 20 June Beam

Modified LBNE Near Detector in NuMI Near Hall Fermilab PAC, 20 June

Cost Estimate Methodology To the greatest extent possible, base estimates on well- reviewed LBNE cost estimates. New cost estimates developed for Soudan underground construction using U of MN A/E consultants. CF for surface construction based on actual NOvA costs. Value Engineering applied by reducing scope – simplifying or eliminating items not absolutely necessary – but utilizing the same fixed and unit costs developed for the reference design. Contingency applied at the same rates as in the reference design. Escalation estimated from the escalation tables used for the reference design and an assumed completion in FY2022. CD-1-type cost range estimated as same percentage range as for reference design. Fermilab PAC, 20 June

Summary Cost Estimate Tables - Homestake Fermilab PAC, 20 June

Summary Cost Estimate Tables - Soudan Fermilab PAC, 20 June

Summary Cost Estimate Tables – Ash River Fermilab PAC, 20 June

Cost vs. Detector Mass Fermilab PAC, 20 June At-Year $M, including contingency

Phasing Possibilities: An Example* Project X Physics Workshop 28 1)LBNE Phase 1: 10 kt LAr detector on surface at Homestake + LBNE beamline (700 kW) 2)Project X Phase 1  1.2 MW LBNE beam 3)LBNE Phase 2: a) Near Detector, b) ~20 kt underground far detector LBNE Stage 1 Project X Stage 1 LBNE Stage 2... *A little beyond what is in the Eng/Cost WG report

Phasing Possibilities: Another Example* Project X Physics Workshop 29 1)LBNE Phase 1: 10 kt LAr detector on surface at Homestake + LBNE beamline (700 kW) 2)Project X Phase 1  1.2 MW LBNE beam 3)LBNE Phase 2a: Near Detector 4)Project X Phase 2 5) LBNE Phase 2b: ~25 kt underground far detector Expanded collaboration could allow part or all of Phase 2a or 2b into Phase 1. *A little beyond what is in the Eng/Cost WG report

Work in Progress For the final Steering Committee report: Add discussion on the relative risks of each of the scenarios.. Add a chapter comparing the scope and cost estimates presented here with those of the LBNE reference design. For the final Steering Committee report and beyond: Study physics reach without near neutrino detector – at what exposure must we have a near detector to limit systematic errors and is this consistent with phase 2a? Develop mitigation of cosmic ray background in surface detector and update designs as new understanding develops. Fermilab PAC, 20 June

Plan Towards CD-1 Complete Final Report of the Steering CommitteeJun 2012 Update conceptual designs and sub-project cost and schedule estimatesJun-Sep 2012 Update integrated resource loaded schedule and complete other project documentsOct-Nov 2012 Director’s pre-CD-1 ReviewDec 2012 DOE (Lehman) CD-1 ReviewFeb 2013 CD-1 ApprovalApr 2013 Fermilab PAC, 20 June

Summary The Engineering/Cost Working Group has developed designs and cost estimates for many options for far detectors, near detectors and neutrino beamlines. From these, three viable options for Phase 1 of a reconfigured LBNE have been identified by the Steering Committee. LBNE is adapting its design and project plan based on the preferred Phase 1 option of a 10 kt detector at Homestake with a new neutrino beam. The LBNE Project is working towards a CD-1 decision in spring We are exploring how to expand the LBNE collaboration to allow us to come closer to the original LBNE plan in Phase 1. Fermilab PAC, 20 June