OVERVIEW Review of completed projects Update on large construction projects Update on miscellaneous projects
COMPLETED PROJECTS Athletic Complexes $12M Mat-Su Day School $12.4M Valley Pathways $22.5M Big Lake ES Reno Ph I $2.2M Houston/Palmer Jr MS Lockers $335K Flooring Replacements Ph I $2M Palmer HS Mechanical Upgrades $5.5M Trapper Creek ES Roof $1M Swanson ES Ext Upgrades $200K Willow ES Roof $1.3M Joe Redington Sr MS/HS $65M CTHS Addition $16M Houston HS Exterior Siding $600K ADA Upgrades District Wide $1.5M Washroom Upgrade District Wide $800K Palmer HS, Palmer Jr MS, Cottonwood Creek ES, Pioneer Peak ES Roofs $3.8M
DENA’INA ES $26.5M Design: Bettisworth N. Construction: FE Const 44,224 SF K through 5 school Work started April 2015, approx. 92% complete On schedule to occupy summer 2016
DENA’INA ES Playground Gymnasium
IDITAROD ES $25.2M Design: MCG Construction: Collins 50,605 SF replacement school. Pre-K thru 5 Approx. 98% complete Substantial insp. today On schedule to occupy spring/summer 2016 Carpenter Circle paved by the city
IDITAROD ES Second Floor Railing First Floor Hall
FRONTERAS CHARTER SCHOOL $6.9M Contractor: Howdie Const. Funded by USDA loan and $500K from MSB Access road from Seward Meridian is in place Work started July 2015, approx. 90% complete On schedule to occupy summer 2016
FRONTERAS CHARTER SCHOOL Classroom Corridor
ATHLETIC FIELD IMPROVEMENTS $6.4M Play court upgrades at Finger Lake, Snowshoe, Larson, Glacier View and Houston High completed in 2014 All summer 2015 work complete with the exception of Iditarod softball/baseball turf in-fields Work on turf fields will start this month
ADDITIONAL PROJECTS Back-Up Generators, District Wide $2.6M - Scope includes base bid - Wasilla MS, Wasilla HS, Palmer HS -- Awarded alternates - Big Lake ES, Butte ES, Snowshoe ES, Willow ES and the Operations & Maintenance Building - Contract awarded March 1 with work in progress Big Lake ES Renovation Ph II $800K, and ADA Parking Upgrades $200K - Remaining work involves new corridor lighting and ceiling tiles - Work in progress and will be complete prior to school start District Wide HVAC Upgrades $7.1M - Design: PDC Engineers, Contractor: Wirtanen Construction (Ph I) -- Work at Butte ES, Pioneer Peak ES, and Snowshoe ES are complete -- Cottonwood ES, Finger Lk ES, Willow ES (new boiler), Goose bay ES, Tanaina MS scheduled for summer Phase II awarded to FE Contracting with work at Wasilla MS this summer and a new boiler install at Palmer JMS in summer 2017
ADDITIONAL PROJECTS cont. District Wide Energy Upgrades $3.1M (Gym Lighting and Windows) - New LED Gym lighting project is complete - Partial window replacements district wide delayed due to hazardous materials investigation. Work will occur summer 2017 Flooring Replacements $900K (2010 and 2011 flooring bond balances) - Carpet scope includes Butte, Cottonwood, Finger Lake, Goose Bay, Sherrod, Swanson, Trapper Creek, and Willow Elementary Schools for a total of 108,000 SF of new flooring -- CYS Enterprises has started carpet install - New gym floors at Big Lake ES and Willow ES awarded May 17 with work scheduled this summer Roof Bond Balance $800K - Project includes Sutton ES roof replacement and Tanaina ES roof mods - Work in progress and will be complete prior to school start