INSTALL INSULATION IN BOILER PLANT PROJECT SECTIONS: 1.VALVE JACKETS 2.BOILER REFRACTOR JACKETS 3.PIPING INSULATION / PVC
VALVE JACKET SECTION REMOVABLE Quantity = 8 Each
Area 1A
Area 1C 6 Each – Valve Jackets to be installed
Area 1C
Area 1D
BOILER REFRACTOR JACKET SECTION REMOVABLE Quantity = 3 Each
Boiler Refractor Jacket 3 Each – Boiler refractor jackets to be installed
Removable Refractor Jacket SIGHT GLASS SHALL REMAIN OPERATIONAL
Refractor Jacket 12” JACKET OVERLAP ONTO BOILER TANK
PIPING INSULATION / PVC SECTION
TYPICAL SPOT WHERE PVC WRAP CAN BE INSTALLED OVER EXISTING INSULATION
TYPICAL AREA WHERE INSULATION NEEDS TO BE INSTALLED PRIOR TO PVC WRAP. MATCH EXISTING THICKNESS TYPICAL AREA THAT WILL NEED PVC INSTALLED OVER EXISTING INSULATION
TYPICAL AREA WHERE INSULATION NEEDS TO BE REPLACED PRIOR TO PVC WRAP
TYPICAL SPOT WHERE INSULATION NEEDS TO BE REPLACED PRIOR TO PVC WRAP
TYPICAL SPOT WHERE ONLY PVC IS REQUIRED OVER EXISTING INSULATION
TYPICAL BARE PIPE LOCATION WHERE INSULATION IS REQUIRED PRIOR TO PVC WRAP TYPICAL LOCATION WHERE PVC WRAP IS REQUIRED. INSULATION IS IN GOOD CONDITION TYPICAL LOCATION WHERE EXISTING INSULATION NEEDS TO BE REPLACED PRIOR TO PVC WRAP
TYPICAL BARE PIPE LOCATION WHERE INSULATION NEEDS TO BE INSTALLED PRIOR TO PVC WRAP TYPICAL LOCATION WHERE ONLY PVC WRAP IS REQUIRED
TYPICAL AREA WHERE INSULATION NEEDS TO BE REMOVED AND REPLACED WITH NEW AND THEN PVC WRAP INSTALLED
Area where at least 8 feet of insulation shall be replaced as it is damaged on top