Schedule to completion, Risk and Critical Interfaces Roy Preece STFC RAL RLSR 16 th April 2015.

Slides:



Advertisements
Similar presentations
1 UK Project Alan Grant, STFC. Finance How savings are made Update on stepIV position Milestones Critical Path - stepIV Concerns 2.
Advertisements

Project Managers Update Roy Preece Particle Physics Department, STFC MICE Video Conference, 18 th September 2014.
Project Update for the Muon Ionization Cooling Experiment (RAL) Mark Palmer Fermilab December 15, 2014.
1 MICE CM31 Key schedule drivers for Step IV Schedule table Milestone summary Comment on Step V Step VI Andy Nichols, STFC, 3/11/11.
Step IV Infrastructure update STFC Tim Hayler Eddie Holtom Norbert Collomb Graham Stokes 14 th December 2011 MICO170 meeting 1Tim Hayler.
1 MICE PM Report General Update –Phase I civil engineering –R5.2 in June –Phase II design work –Phase II hardware –A few questions –Schedule, milestones.
Global Magnet Systems including Field Mapping MICE Project Board 28 th June 2011 M Courthold – RAL R Preece - RAL.
Update Hardware for conductive cooling of the quench resistors has been fabricated at LBNL. Preparation for installation to start this week. Installation.
Electrical & Control CM40 Daresbury Laboratory. CM40 Electrical Infrastructure Update RRM2 Latest Latest on Installation Progress Rack Allocations Racks.
Project Managers Report Video Conference 172 Roy Preece 11 th December 2014.
Alan Grant OsC 30/4/ UK Project Finance & Schedule.
MICE - UK Project Progress Roy Preece 30 th April 2013.
MICE: overview K. Long, 18 March, Contents ► Introduction ► Beam line ► Infrastructure ► MICE steps ► Phase II (comment) ► Conclusions.
MICE Magnetic Field Mitigation Review Potential impact on ISIS of MICE Stray Magnetic Fields 24 th September 2013 Martin Hughes.
1 UK PM Report Costs & Schedule Alan Grant, STFC.
Magnetic Shielding Issues Roy Preece STFC - RAL. Overview Issues Items in harms way – Step IV Step IV mitigation plan –Racks –Compressors Current / Future.
RSLR mtg 28/3/2014 RLSR mtg Alan Grant. 2 RLSR mtg 28/3/ MICE Finances - Forward Look.
The status of the construction of MICE Step IV K. Long, on behalf of the MICE collaboration.
Executive Board Meeting Roy Preece 23rd May 2014
Electrical Integration CM38 Steve Griffiths & Ian Mullacrane.
Schedule and Work We are moving into a very intensive 4 months with a lot of work to be carried out Electrical services to the devices – after the South.
Hydrogen system R&D. R&D programme – general points Hydrogen absorber system incorporates 2 novel aspects Hydrogen storage using a hydride bed Hydrogen.
January LEReC Review 12 – 13 January 2015 Low Energy RHIC electron Cooling Kerry Mirabella Cost, Schedule, Personnel.
Magnetic Mitigation - Contents l Magnetic Mitigation General l West Wall Compressors l Rack Room 2 l Magnetic Shielding Yoke Jason Tarrant – Integration.
Status of the MICE Project & Dashboard MICE Project Board 14 th November 2013 Roy Preece.
Hydrogen Delivery System Schedule MICE Schedule Review 23 rd -25 th May 2011 M Hills STFC.
1 MICE Hall construction status Richard Apsimon MICE VC meeting 29th Nov 2007.
PRY Base - Contents l PRY Support/Base/Platform in the MICE Hall l History l Requirements l Environment l Design l Structural Integrity l Preparation l.
RLSR 16/4/2015 UK Financial Plan & Risks. Content Finances – Cost to Completion Risks – Top level to completion – R9 working space – Summary 2 RLSR 24/11/2014.
1 MICE Hall and Infrastructure - Progress since CM18 Chris Nelson MICE CM19 Oct 2007.
MICE Status & Plans MICE-UK paul drumm 15 th September 2004.
Project Managers Report CM40 Collaboration Board – Rome Roy Preece 28 th October 2014.
Spectrometer Solenoid Schedule MICE Schedule Review May 23 rd 2011 Roy Preece (STFC RAL, LBNL)
UK Update Package Managers Meeting 001 Roy Preece 13 th January 2014.
MICE Oversight Committee Meeting RAL, 24 April 2014 Paul Soler on behalf of the MICE Collaboration Status of MICE and Spectrometer Solenoids.
Paul Drumm, cm10, 27 Oct 2004 MICE Project Report Paul Drumm Collaboration Meeting 10 Rutherford Appleton Laboratory October 2004.
MICE Project Report Alan Bross (for Paul Drumm). Project Issues ● Key dates: – ISIS Synchrotron start-up scheduled for 1st August ● Shielded area around.
CM27 – 8 th July 2010 LH2 System Progress and Future Plans M Hills T Bradshaw M Courthold I Mullacrane P Warburton.
US Project Plan for MICE Mark Palmer Peter Garbincius, Alan Bross, Rich Krull Fermilab November 24, 2014.
OsC mtg 24/4/2014 OsC mtg Alan Grant. 2 OsC mtg 24/4/ MICE Finances - Forward Look.
1 Mice Collaboration Meeting CM33 Glasgow University 25 th – 29 th June 2012 STFC Daresbury Laboratory Electrical Infrastructure Report Authors : Ian Mullacrane.
1 UK PM Report Costs & Schedule Alan Grant, STFC.
Status of the MICE Construction Project Resource Loaded Schedule Review 29 th April 2014 Roy Preece.
OsC mtg 15/10/2014 MICE Step IV Alan Grant. Content Step IV – Construction Status – Finances – Schedule – Risks – Summary 2.
Finance Roy Preece STFC RAL Oversight Committee Meeting 27 th November 2015.
MICE – UK Plan Roy Preece STFC RAL DOE Review of MAP Brookhaven National Laboratory 13 th August 2014.
1 UK Project Roy Preece – STFC Alan Grant, STFC. Finance Staffing Update on stepIV position Milestones Critical Path – stepIV Magnetic field mitigation.
MICE Construction Project Update: SSs, PRY, Cavities, Tracker… 1MAP Friday Meeting – January 30, 2015 Alan Bross.
MICE RF – Installation at RAL Tim Stanley RAL 7 November 2013.
RLSR 16/4/2015 UK Financial Plan & Risks. Content Finances – FY 2014/15 – Cost to Completion Risks – Top level to completion – R9 working space – Summary.
1 MICE Hydrogen system Working group mtg – 01/09/14.
RF Module Integration Colin Whyte University of Strathclyde on behalf of the MICE collaboration 1RF Review 9th & 10th Sept '15 Abingdon.
UK Project Plan (Finance & Risk) Alan Grant STFC DL RLSR 5 th April 2016.
US Construction Project: SSs, PRY, Cavities and test program 1.
Schedule and Milestones Roy Preece STFC RAL FAC 17 th April 2015.
1 UK Project Finance & Schedule. Overview Finance  Budget Setting 2013/14  June Finance  Forward look to complete stepVI Schedule  Overview 2.
Schedule and Milestones Colin Whyte STFC RAL Resource Loaded Schedule Review 5 th April 2016.
UK Project Plan Roy Preece STFC RAL RLSR 26 th October 2015.
Radiation Shutter Re-Purposing Roy Preece STFC RAL 18 th December 2014.
S A Griffiths CM42 June 2015 Electrical & Control.
Project Managers Report CM38 – Napa Roy Preece 24th February 2014.
Step IV Step IV extended through 2016 QP/QD – in progress at FNAL Target dates SSU ECE for Feb now only 20% probability – no-field Feb Remainder for April/March.
Reported by Ron Prwivo for Ian Robson. Overview Response to Recommendations from the RLSR of November 2014 – very good, RF staffing remains an issue Very.
Muon Ionisation Cooling Experiment Overview
Resource Loaded Schedule and Budget Profile
Status of the MICE Construction Project
UK Financial Plan & Risks
MICE CM31 Schedule summary
MICE PM Report Progress with the Infrastructure A few problems
Introduction Jason Tarrant – Integration Engineering Step IV Removal
Presentation transcript:

Schedule to completion, Risk and Critical Interfaces Roy Preece STFC RAL RLSR 16 th April 2015

Content Schedule – To Completion – Current Status Finance – Top level overview Risk – Changes and Updates Interfaces – For the Cooling Demonstration Summary 2

To Completion Schedule 3

To Completion Schedule to Completion 4 The baseline schedule has been created joining the Step IV and Cooling Demonstration construction schedules Data taking periods for both Step IV and Cooling Demonstration have been included Critical Path for the project to completion has been found The RF Amplifier installation is a driving item due to the highly skilled resource required for much of the activity. Work is on-going to interact with the senior management of AsTEC and Daresbury TD to gain significant staff involvement. Installation of the first RF amplification system in the hall as early as possible will enable off line testing of the RF modules The Step IV data taking period is used as construction slack Hard milestone for end of data taking established – 1 st June 2016 This does mean that any slippage of the Step IV construction has an impact on data taking period If data taking is complete or no ISIS user runs are available at the 1 st June timescale, early re-configuration of the hall will commence. The data taking period for the Cooling Demonstration has an end date of March 2018 coinciding with the end of the UK FY UK Proposal required for 16/17 FY and will be prepared for submission toward the end of the this summer. Analysis and exploitation will continue after the the March 2018 set point and has not at the moment been fixed. Software and Computing schedule included in the master and will be monitored for progress and resource during the normal management of the project.

To Completion Schedule to Completion 5 During re-configuration the Upstream Spectrometer Solenoid can stay in place. We are planning to keep the magnet to at least Nitrogen temperatures to remove the need to retrain, time and cost mitigation. Cooler compressors on the North Messanine extension. The PRY materials surrounding the Upstream Spectrometer Solenoid can also stay in place and will be re-used for the Cooling Demonstration. The intension is to have the RF Module test area next to the Solenoid. In this position work for re-configuration can continue. Installation of waveguide and other required equipment can start during ISIS down time during the Step IV running period. RF Amplifier Area RF Module

To Completion Critical and Near 6 Critical and Near Critical path items Orange – <15 days total slack Yellow - >15 days < 30 days total slack Green are milestones Step IV Data Taking period starting 18 th August 2015 Hard end date of 1 st June 2016 Decommissioning Step IV RF System 2 Installation Rolling platforms and floor Cavity testing Parallel operations have been planned into the schedule ISIS beam off times will be utilised to advance work for the offline RF module testing – Installations behind the North wall and waveguide installations to test position.

To Completion Critical Path 7 Dates:- Step IV Construction Complete – 9 th June 2015 (26 th June 2015) Step IV Commissioning Complete – 18 th August 2015 (14 th October 2015) Step IV Data taking complete – 1 st June 2016 (19 th August 2016) Cooling Demonstration Construction Complete – 31 st March 2017 (25 th August 2017) Cooling Demonstration Commissioning complete – 9 th May 2017 (22 nd November 2017) End of Cooling Demonstration – 31 st March 2018 (13 th October 2018 if funding in place for addition operations) Blue trace – baseline schedule (inclusive of time contingency) Red trace – Risk loaded schedule (loaded onto the baseline)

To Completion Milestones 8 Hydrogen absorber decision that has been made following the recommendations from the Hydrogen review where :- Testing of the safety windows is required. Changes to the exhaust line to decrease back pressure generated within the safety window volume. Lithium Hydride will be used for the first data run. Install the Hydrogen Absorber to the Focus Coil bore during the current Step IV construction schedule Before mid May – North PRY installation scheduled to begin on the 12 th May All equipment is available for the installation Instrumentation and pipework to be installed. All design and working group sign off of exhaust line can be done during final construction and initial commissioning period. Data can be taken during the initial commissioning phase with an empty absorber Effect of the windows to be confirmed by analysis team. Benefit – Vacuum and cooler testing can be carried out for the Hydrogen turret and absorber body.

Current Status Schedule 9

Current Status Dashboard and Slip Chart Project dashboard showing the milestone slip chart and current critical path items. South side materials were delivered South PRY installation complete Racks have been installed to Rack room 2 Compressors are ready for use North side PRY materials have been packed and will be shipped very soon From the experience gained with the South side PRY frames and plates the North installation has been streamline. 10

Current Status Dashboard and Slip Chart 11 All items now on the critical path are tasks that are sequential activities culminating in the completion of the Step IV construction. The South side PRY frames were used to setup and gain experience for the installation of the North side and there is a high probability that the installation will progress ahead of schedule.

Financial Summary 12

Financial Summary Top Level Finance 13 UK FY April – March US FY October – September US Figures normalised to the UK FY period UK Project Proposal for final two years Analysis / Exploitation after this period will be required

Risk 14

Risk Following the recommendations from the Hydrogen System Review panel further testing and signoff is required May not be ready for the Step IV operations Lithium Hydride will be used for first absorber data runs The Absorber will be installed and will be in place during the commissioning period to reduce future work Leak testing Cooler testing Lithium Hydride secondary discs Un-reasonable cost Mitigation is to replace with plastic at the bore of the solenoid Design and manufacturing required RF amplification expert personnel risk Associated with this risk the availability of the electrical / mechanical for the build up due to pressures from external projects Interactions with the senior management of AsTEC and TD to mitigate the impact and gain the expert personnel required. 15

Interfaces 16

Interfaces To ensure that equipment is not forgotten and to let the teams know as to what they are responsible for. The major sub-projects have been called out and the envelope for each being produced and agreed. RF Module RF Amplification Radiation Shutter / Secondary Absorber Vacuum Rolling Platforms Partial Return Yoke Central Absorber Volume Electrical Installation Hall Infrastructure 17 What is required Vacuum Support Cooling Air etc…… Who owns the item Is it new or existing equipment The effect on other elements of the cooling demonstration Estimates of cost Associated with the Assumptions document Specification for the Cooling channel

Interfaces 18 The RF Amplifier and RF Module interface points RF Amplification up to the end of the trombone sections RF Module up to the end of the coupler Vacuum package up to the valve downstream of the getter pump provided by the RF Module. Connections to the floor defined in association with Rolling Platform team Connection to the Bellows Lifting arrangements – Hall infrastructure PRY protrusions Air, water, instrumentation

Summary 19

Summary Step IV Highlight dates Construction Completed 9 th June 2015 Commissioning Complete 18 th August 2015 Data taking period Complete 1 st June 2016 Cooling Demonstration Highlight dates Step IV De-Commissioning Complete – 8 th July 2016 PRY, Magnet and Cavity Installation Complete – 25 th January 2017 Cooling Demonstration Installation Complete – 31 st March 2017 Cooling Demonstration Commissioning Complete - 9 th May 2017 Remaining Cost to complete for the UK FY15/16 - FY17/18 - £9.26M (Proposal 16/17 onward) Remaining Cost to complete for the US FY15/16 – FY17/18- $11.73M Technical risk for the Hydrogen system for Step IV operations Labour risk for RF Amplifier assembly and test Support for Data and Exploitation after the construction and initial data period is required 20