Peter Spiller MAC meeting 10.10.2011 Time Schedule SIS100 1.

Slides:



Advertisements
Similar presentations
FAIR Synchrotrons SIS100/300
Advertisements

Wednesday July 19 GDE Plenary Global Design Effort 1 Instrumentation Technical System Review Marc Ross.
Peter Spiller, IHEP, Protvino GSI, Peter Spiller IHEP FAIR in kind Contributions.
UNILAC SIS 18 SIS 100/300 HESR Super FRS NESR CR RESR Sergey Kozub Institute for High Energy Physics Protvino, Russia SIS300 meeting 19 March, 2009 Sergey.
CEA DSM Irfu - Bernard GASTINEAU - R3B Technical Board Meeting -April 4, Reactions with Relativistic Radioactive ions Beams GSI Large Acceptance.
FAC, 10/12/06 D. Schultz 1 e-Beams Systems Update Linac Injector Undulator Production MMF commissioning ARR David Schultz.
Possible Assembly and Test of the Crab cryomodule in SM18 at CERN P. Maesen LHC Crab Cav meeting, 17 Sep’ 09 LHC-CC09Cryomodule Assembly & Test Stand.
The HiLumi LHC Design Study (a sub-system of HL-LHC) is co-funded by the European Commission within the Framework Programme 7 Capacities Specific Programme,
ITS Subsystems Availability MACS Week, June 2011 E. Sargsyan PP a-ESA_ITS_MACS_Week_June2011.pptm E. Sargsyan ITS Subsystems Availability 1.
1 Warm Magnets Work Package Status J. Bauche, TE-MSC Technical Meeting, 9th January 2014.
Question 27: Outline the key steps for industrialization of machine components and the likely remaining vulnerabilities in achieving them. Achieving industrialization.
The ESS vacuum team has overall responsibility for all technical vacuum systems used on the: Accelerator, Target and Neutron Scattering Instruments and.
Prospects of SC Quadrupole Production at IHEP-Protvino The 2nd Institutes Meeting on International Construction of the FAIR Accelerator Complex Protvino,
Linac Front-End R&D --- Systems Integration and Meson Lab Setup
LINAC 4 Project L4T/L4Z Design Status J.Humbert / B.Riffaud on behalf of EN-MME design team 1 st September 2011 LINAC4 – BEAM COORDINATION COMMITTEE B.Riffaud.
HIE-ISOLDE contribution packages M. Pasini BE/RF.
IHEP participation in SIS300 production UNILAC SIS 18 SIS 100/300 HESR Super FRS NESR CR RESR Institute for High Energy Physics Protvino, Russia FAIR meeting.
Peter Hülsmann, GSI RF-Group, Tel: Task SIS18-1: h=2 Cavity P. Hülsmann GSI, Gesellschaft für Schwerionenforschung.
P. Spiller, SIS18upgrade, Peter Spiller GSI, Darmstadt Kick off Meeting - EU Construction DIRAC Phase SIS18 upgrade.
1 Status of EMMA Shinji Machida CCLRC/RAL/ASTeC 23 April, ffag/machida_ ppt & pdf.
1 BROOKHAVEN SCIENCE ASSOCIATES ASD Procurements Gregory Fries Liaison/Manufacturing Engineer NSLS-II ASAC October 22-23, 2009.
Peter Spiller, DIRAC Kick-off meeting Peter Spiller Design Study Group DIRAC kick-off meeting SIS100.
Project Management Mark Palmer Cornell Laboratory for Accelerator-Based Sciences and Education.
Peter Spiller, COLMAT-Kick off meeting, Cryo-Collimator, CERN, COLMAT Kick-off meeting CERN Peter Spiller Cryo-Collimator (Catcher) for.
GSI Helmholtzzentrum für Schwerionenforschung GmbH LINK EXISTING FACILITY I n order to prepare the existing GSI accelerator facility (mainly the SIS18)
Booster and Collider SC magnets. Design & prototyping of UHV and cryostat systems for Booster and Collider A.Smirnov JINR, Dubna, Russia NICA Machine Advisory.
Workshop Chamonix XV27-January-2006 DivonneMassimiliano Ferro-Luzzi 1 State of LHCb for the Sector Test  Overview  Agreement  Status of –VELO –exit.
BDS: 1 October 13, 2007 BDS KOM EDR planning discussion Andrei Seryi October 13, 2007.
Medium Beta Cavities Paolo Michelato, Paolo Pierini, and Carlo Pagani INFN Milano - LASA.
Medium beta cavities Paolo Michelato, Paolo Pierini, Carlo Pagani INFN Milano - LASA.
Commissioning of REX Jose Alberto Rodriguez, BE-OP-PSB (167538) on behalf of the ISOLDE operations team.
11 T Dipole Project Cold mass integration status & plan F. Savary / TE-MSC-LMF.
High Intensity Neutrino Source Program Overview for CD Controls Management Meeting Bob Webber October 6, 2006.
Interface of FP420 to LHC FP420 meeting 28-Sep-2006.
1 CTF3 CLEX day July 2006 CLEX day 2006 Introduction G.Geschonke CERN.
Date 2007/Sept./12-14 EDR kick-off-meeting Global Design Effort 1 Cryomodule Interface definition N. Ohuchi.
H. Weick, 8 th MAC meeting, GSI, Super-FRS Status Target Area H. Weick / M. Winkler 8th FAIR - Machine Advisory Committee Meeting
LHC Beampipes Ray Veness / AT-VAC FP XII 08Beam Vacuum- R.Veness.
Udo Blell - Synchrotrons 1 Udo Blell GSI, Darmstadt MAC – 7 April 2 th - 3 th, 2012 FZ - Jülich SIS 100 Injection / Extraction systems.
O. Kester, NuSTAR annual meeting, 27/02/2013
Contents: -GSI organization structures -Tasks of GSI (accelerator) -Status of evaluations / technical developments -Overview -Note : (only) accelerator.
Delivery of FAIR In-kind items (feedback from India) Subhasis Chattopadhyay VECC-Kolkata & BI-Kolkata.
Wish list from ESS Christine Darve H-ECCTD Kick-off meeting 16 March
Development of Cryo-Module Test Stand (CMTS) for Fermi Lab (R.L.Suthar, Head,CDM, BARC) Cryo-Module Test stand (CMTS) is a very sophisticated equipment.
Programme for the Physics Start-up Stable and radioactive beams Jose Alberto Rodriguez, BE-OP-PSB (167538)
Readiness for RF capture Cavities – all 16 cavities commissioned with RF feedback loops closed klystron polar loop still to commission on 2 cavities 2.
Tests on production cryomodules Bob Kephart Sept 30, 2006.
Common Systems – Holger Kollmus Holger Kollmus FAIR - Machine Advisory Committee Meeting Common Systems and Controls.
H-ECCTD KICK-OFF DEVELOPMENT PLAN AND SCHEDULE 16/03/2016.
ESS Cryomodule Status Meeting – Introduction | | Christine Darve Introduction to Cryomodules for the ESS 2013 January, 9 th Christine Darve.
ELENA installation progress F. Butin / ELENA collaboration.
Peter Spiller, November 2012, Structure and Tasks of the Project Division Primary Beams Peter Spiller Machine Advisory Committee Meeting.
Report Technical Director Storage-Ring-Installation Completed
High energy beam transport.
Oleksiy Dolinskyy December 1st, 2014
Schedule for the FAIR Antiproton Target
Beam diagnostics from GSI
Status of HESR 18th March Gießen Dieter Prasuhn.
Testing of SC Magnets Status - November 2010
FAIR ACCELERATORS Peter Spiller EMMI workshop
(Procurement, testing of magnets)
On behalf of the Accelerator Project Phase II Team
ESS RF Development at Uppsala University
UK RFD Pre-Series cryomodule
TEST PLANS for HL LHC IT STRING
Petra Schütt Operateurs-Schulung
Advanced Research Electron Accelerator Laboratory
Daresbury ESS In-Kind Contributions
LTU/Undulator Installation Status
Status of the ESS High Power RF Systems
Presentation transcript:

Peter Spiller MAC meeting Time Schedule SIS100 1

General – Status of Planning  First planning approach via the machine project leaders.  Discussion and agreements with technical departments.  Identification of (time) critical components and interconnetions between work packages.  Agreements on procedure, procurement strategy and boundary conditions for each main subsystem with technical departments.

Agreed Boundary Conditions  The required man power is available.  The milestone „building readiness“ must be met by each technical subsystems needed for machine commissioning.  The installation phase for the machine components is assumed to be one year.  The device status after the installation phase allows a commissioning with beam.  Rather than trying to complete ALL technical subsystems before comissioning, with the risk that commissioning is delayed, completion of the machine with an equipment which allows commissioning.  Depending on the device status beam comissioning may be done with reduced machine performance (e.g. lower ramp rate, lower beam intensities etc.)  If needed, the completion of the technical equipment (devices) can be made in dedicated shut downs in the following year.

Procurement Strategies – General Statements  In most cases, GSI does not provide specifications on the level of blueprints.  In such cases, the completion of the design has to be taken over by the contractor - accompanied by a number of design and integration reviews with GSI (defines time required before production can be started).  There are several technological risks which require in several cases the demonstration of the functionality of devices by means of pre-series components.  However, in order to save time, the preparation for series production must be performed in parallel to the production of pre-series components.  In the final phase of prdouction process of critical items, in order to meet the milestone „building readiness“ (plus installation phase), several work packages have to be excecuted in parallel (e.g. FAT, SAT, installation and commissioning without beam).  Focusing of resources on devices needed for beam commissioning.

Cryomagnetic Units Dipole Modules  Tendering started of 112 units – still ongoing.  Detailed specs., procurement strategy, time schedule and Werksvertrag (contract) prepared and completed.  Contracting of series production, including pre-series module for testing  Procurement strategy very similar to my last MAC presentation.  Production rate had to be increased to one unit per week (probably 2 shifts production).

Cryomagnetic Units Quadrupole Modules  Critical workpackage (84 units) – no inkind proposal  Procurement strategy similar to dipole module: Contracting of series including one pre-series module (of the arc) for testing the individual devices and the integration.  Completion of detailed specification until April 2011 (contracting in June)  Contract comprises: 1. completion of the design of all modules based on the existing pre-design (about 3 My) 2. design and production of one preseries module, including all components (quadrupole chambers and BPM will by supplied by GSI/FAIR) 3. production of series and FAT  Challenging: no 3 turn quadrupole, no s.c. steerer, no s.c. sextupole, no insulated s.c. wire has been built before  Allowed production time about 2 years (one module of 84 moduls per week) (two or three shift production > higher costs)

Example Quadrupole Modules

Power Converter - Substructure  Main Dipole Power Converter (1 unit) (german EOI)  Main Quadrupole Power Converter (3 unit)  Corrector Magnet Power Converter (about 200 units) Two procurement groups formed: Group 1: 168 Steerer PCs Group 2: Chrom. sext. PCs (6 units), Resonance sext. PCs (11 units), warm and fast Quadrupoles (4 units), s.c. inj./extr. Quadrupoles (4 units)  Septa Power Converter (6 units) (inclusing lambertson) – planning not yet made

Main Dipole and Quadrupole Power Converters: Commissioning without completion of load, the cryomagnetic system is not possible. Delivery with direct installation in the supply buildings. SAT only after complete assembly of the machine. Consequently, taking the prodcution time into account the contracting and delivery must start „delayed. Corrector Power Converters (partly inkind contribution by India) s.c. magnets FAT with dummy load SAT and comissioning with assembled machine – two per day > 80 days in total. > Contracting and delivery postponed. n.c. magnets SAT may be performed with final load Power Converter Procurement Strategies and Boundary Conditions

Example Dipole Power Converter

Rf Systems - Substructure Devices needed for SIS100 commissioning:  Acceleration Systems (critical) (14 units)  Bunch Compression Systems (critical) (9 units) Devices with potential delayed installation and commissioning:  Barrier Bucket Systems (2 units)  Longitudinal feed-back systems (still ongoing beam physics discussion wether needed or not) Contracting  Design, integration, manufacturing of cavity, power amplifier, control (amplitude, eigenfrequency)  Power supply units (incl. PLC) supplied by GSI  Driver accelerator supplied by GSI (standardized)  Cavity synchronization and control system interfacing (EOI GSI)

Rf: Agreed procedure and boundary conditions  Contracting of the acceleration and bunch compression systems is needed around April 2012 (early start !). (if not a copy of the SIS18 system is build)  For the acceleration systems, an uncertainty is the availability of Ferrit discs with the desired properties (consequence e.g. reduced Rf voltage) (Test discs shall be orders immediatly from the former Philips Ferroxcube – now in poland)  It is required to postpone the series production after successful testing of the preseries system. In case of the barrier bucket system, both cavities will be built in parallel.  For the main production phase, two years can be accepted for each subsystem. This is a precondition for participation in the tendering process.  In case of any delayes: The beam commissioning can be performed with only a fraction of the acceleration systems and basically without bunch compression systems.

Example Acceleration Cavity

BI: Focusing on Devices needed for Commissioning Devices required for SIS100 commissioning:  BPM  BLM  Transformers (DCT, ACT)  Schottky pick-up  Profile grids + stopper („first turn diagnostics)  Catcher current measurement  Chambers and manipulators Devices with potential delayed installation and commissioning:  Field controle loop  CO feed back  Tune feed back  IPM  High current transformer DCT (Device with delayed installation and commissioning within years. ) Each item substructured as:  Detector  Chamber  Manipulator  Electronics  DAQ (incl. Software)

Beam Instrumentation Procurement Strategies: BPM: Design and integration studies well developed. Will be tendered by FAIR/GSI and supplied to the contractor of the quadrupole modules. Contracting as series production with one pre- series BPM in advance for integration tests in the pre-series quadrupole module. Series components will be supplied piece by piece for integration into the quadrupole module. Begin of contracting not critical (middle of 2013). Transformers: Transformers (3 pieces) will be tendered and industrially produced. Integration into vacuum chamber with ceramic gap (etc.) at GSI or at external subcontractor. One special (novel) high current transformer will be „built“ and assembled at GSI. Begin of contracting not critical. BLM: Tendering or direct contracting with IHEP. Begin of contracting not critical. Grid + stopper (first turn diagnostics): Grid re-design and matching to new apertures of existing design solutions. Running process in the design office. However, may be taken over by industrial contractor for series production. Stopper: FLUKA calculation for design optimization planned. DAQ: Most of the DAQ systems will be supplied as inkind delivery from Sloweni for all machines.

Example: BPMs

UHV - Substructure  S.c. thin wall, ripped magnet chambers (inkind dipole and EOI quadrupole Dipole chamber tendering is started. Quadrupole chambe in parallel to the quadrupole module production.  Warm magnet chambers, bellows, straight pipes etc. (bakeble) Pumps (turbo, IZ etc.), roughing station (common schedule 1)  Adorption pumps (between dipoles)  Valves (common schedule 1)  Diagnostics (pressure gauges, mass spectrometer etc.) (common schedule 1)  Equipment insulation vaccuum (common schedule 1)  UHV components of cryomoduls is part of the cryomodule contracts

Common time schedule 1: Duration of procur. 1 year - Begin procurement in 2015 Dipole chambers: time schedule exists, tendering is started (two years production) Quadrupole chambers: tendering in parallel to quadrupole moduls (two years) Adsorption pumps (coating at KIT) (84 units) (production time 2 years), Begin 2014 Warm UHV components: Begin procurement in 2015 UHV System Procurement

Local Cryogenics - Substructure 1.Bypass lines 2.Connectiong boxes and feed-in boxes 3.Feed box 4.End box 5.Cold link 6.Cryostat end caps 7.Current lead box 8.Reference magnets Red: Polish EOI, potentially inkind contribution Detailing of bypass lines based on GSI predesign has already been started. Time schedule will be set-up in agreement with the polish partners and in consistence with the schedule of linked devices.