US Army Corps of Engineers BUILDING STRONG ® Inner Harbor Navigation Canal Lock 2016 Dewatering Marine Industry Day USACE - New Orleans District 20 May 2016
Agenda IHNC Lock overview, history, current condition Dewatering scope of work Dewatering sequence and schedule Constraints: River stage, hurricane season, availability of Baptiste Collette Alternate Route Contingency plans 2
BUILDING STRONG ® IHNC Lock Overview Sole access from Mississippi River to eastern GIWW 640 ft. long x 75 ft. wide x 31.5 ft. deep Averages 10,000 lockages and 16M tons of cargo annually 3
BUILDING STRONG ® IHNC Lock History Constructed by Port of New Orleans to provide access between Lake Pontchartrain and the Mississippi River Assumed into the Federal, GIWW project in 1944 Leased by the Corps from the Port from ; purchased in fee from the Port in
BUILDING STRONG ® IHNC Lock – Vicinity Map 5
BUILDING STRONG ® 95-year old miter gates in state of failure - passing ~80 cfs during high water Current conditions: Miter Gates 6
BUILDING STRONG ® Original 52 HP electric motor and reduction gear Current Conditions: Gate machinery 7
BUILDING STRONG ® Electric motor patent plate: Dated February 1911 Current Conditions: Gate machinery 8
BUILDING STRONG ® Failed Bull Gear – January
BUILDING STRONG ® Concrete Damage at Strut Arm Opening January
BUILDING STRONG ® Emergency Repairs – January 2014 IHNC lock closed 11 days for repair of failed bull gear 11
BUILDING STRONG ® IHNC Lock Dewatering 2016 Scope of Work ► Replace 4 main operating miter gates, hinges and seals, and original electrical/mechanical gate operating machinery with new hydraulic machinery; replace sluice valve seal strips ► Sequence of work requires 4 separate dewaterings of the lock chamber ► Estimated 120-day duration, commencing on or about 1 Aug 16 12
BUILDING STRONG ® IHNC Lock Dewatering 2016 Sequence of work within low water window 13 Dewatering may only occur when river levels are below 6-ft. on Carrollton gage due to uplift of the lock chamber (Aug to Dec timeframe). Schedule coincides with Hurricane Season
BUILDING STRONG ® IHNC Lock Dewatering 2016 Miter gate configuration 14
BUILDING STRONG ® 15
BUILDING STRONG ® IHNC Lock Dewatering 2016 Upper hinge turnbuckles being machined at Acme Machine, Franklinton, LA 16
BUILDING STRONG ® IHNC Lock Dewatering 2016 Gate operating hydraulic machinery under assembly at Hydradyne, Harvey, LA 17
BUILDING STRONG ® IHNC Lock Dewatering 2016 MVD Regional Resources ► MVN Floating maintenance Units A, B & C Shops Section Crafts/trades from Operations Division field sites ► MVR Heavy lift floating derrick “Quad Cities” and crew ► MVS Expert technical assistance to tension and adjust new miter gates 18
BUILDING STRONG ® IHNC Lock Dewatering 2016 Constraints ► Dewatering may only occur when river levels are below 6-ft. on Carrollton gage due to uplift of the lock chamber (Aug to Dec timeframe). Dewatering schedule coincides with Hurricane Season ► Alternate route through Breton Sound, via Baptiste Collette currently shoaled in: controlling depth < 8-ft. Funding secured to provide 12-ft. X 200-ft. channel for GIWW barge traffic US Coast Guard to mark alternate route across open water reaches 19
BUILDING STRONG ® GIWW – Baptiste Collette Alternate Route 20
BUILDING STRONG ® 21 GIWW - Alternate Route absent Baptiste Collette
BUILDING STRONG ® IHNC Lock Dewatering 2016 Contingency plans for late high river and/or interruption of work by hurricanes ► Scenario 1: River recedes by 1-31 Aug: Perform full scope of work ► Scenario 2: River recedes not before 1 Sep, or work interrupted by hurricanes: Replace canal end gates and operating machinery for all 4 gates (70 day work duration) Defer river end gate replacement to 2017 low water (60 day work duration) ► Scenario 3: River remains >6 ft. beyond 30 Sep Defer dewatering to 2017 low water Hurricane contingencies include USCG approved mooring plan for floating plant to be secured within the IHNC - Regulated Navigation Area. 22
BUILDING STRONG ® 23 DISCUSSION