WP 17.1 Civil Engineering Point 1 - Networks LS2 COMMITTEE – CERN – 01.04.2016 Pieter Mattelaer (SMB-DI)

Slides:



Advertisements
Similar presentations
Earthwork Operations & Equipments
Advertisements

ENVIRONMENTAL ASPECTS EDR - CFS Europe – Kick-Off Meetings Kick-Off Meetings, CERN, 3, 4, 5 September ILC PROJECT ENGINEERING DESIGN REPORT CFS Europe.
Plasma Wakefield (AWAKE) Project Meeting 18 October 2012 Civil Engineering Feasibility Issues for the West Area EDMS : John Osborne GS-SE.
CONSTRUCTION BEST MANAGEMENT PRACTICES (BMPs) CONSTRUCTION GUIDE TO CLEANER WATER Information compliments of: WaterWorks! WaterWorks! Center for Environmental.
ESTIMATING EARTHWORK Prof Awad S. Hanna.
CENF – Civil Engineering Extension B887 CERN: An accelerator complex unique in the world -Prevessin site complex- -EHN1 Extension Area- EHN1 Extension.
Dr. José Miguel JIMENEZ LS2 Coordinator LHC Performance Workshop (Chamonix 2014) Session 8 - Long Shutdown 2 Strategy and Preparation Chair: José Miguel.
The HiLumi LHC Design Study is included in the High Luminosity LHC project and is partly funded by the European Commission within the Framework Programme.
1 ELEMENTS OF AN EFFECTIVE SEDIMENT CONTROL PLAN PLANNING APPROACH Issued May 2009 Level II: Introduction to Design Education and Certification for Persons.
Broadway Street Viaduct Improvement, Pre-Load Testing and Geotech Report Workshop Consultant Presentation Iowa DOT 2 nd April 2007.
Topic B2 Sub-structure groundworks
1 7. R EPETITIVE C ONSTRUCTION Objective: To understand how production and production rates are affected by repetition of tasks, and to learn how to plan.
The HiLumi LHC Design Study is included in the High Luminosity LHC project and is partly funded by the European Commission within the Framework Programme.
1 Project Planning Faculty of Applied Engineering and Urban Planning Civil Engineering Department Week 4 2 nd Semester 2008/2009 UP Copyrights 2008 Construction.
19 February Summary: Updating on the activities completed (Done) since the last meeting List activities on going (Next steps) and related Actions.
Preparing Foundations for Cylinders & ASME Tanks
Soil and Earth Works Faculty of Applied Engineering and Urban Planning Civil Engineering Department Lecture 3 - Week 2 2 nd Semester 2008/2009 UP Copyrights.
LS1 : EL Upgrades & Consolidation Chamonix– February 8 th 2012 F. Duval on behalf of EN/EL The goal of LS1 is to implement everything needed for a safe.
The HiLumi LHC Design Study is included in the High Luminosity LHC project and is partly funded by the European Commission within the Framework Programme.
STRATEGIC ENVIRONMENTAL ASSESSMENT METHODOLOGY AND TECHNIQUES.
1 Global Design Effort TILC08 - WG1 Summary WG-1: Cost Reduction Studies J. Carwardine, T. Shidara, N. Walker (For WG-1 participants)
09 July EHN1 civil engineering project status (JUNE) Summary: Updating of the activities carried out on-site (Done) in JUNE List activities on going.
06 August EHN1 civil engineering project status (JULY) Summary: Updating of the activities carried out on-site (Done) in JULY List activities on.
Consultation seminar on the preparation of full Application Form for LSP 6 December 2011, Tartu Consultation seminar on the preparation of full Application.
ESTIMATING EARTHWORK DR. Nabil Dmaidi.
CENF – Civil Engineering Extension B887 Status – 02 October 2014 Done: (1/2) Preliminary civil engineering drawing and Functional specification approved.
R2E Mitigation Project P5 Relocation Options - Discussion R2E Mitigation Project CMS Relocation Options Towards An R2E Baseline 1 M. Brugger for the R2E.
Professional Practice Building Surveyors contribution.
ISOLDE Activities for LS2 Richard Catherall EN-STI ISOLDE Technical Coordinator.
Consolidation activities for GS-SE Luigi Scibile GS-SE Accelerator Consolidation Workshop, EDMS:
22 October Summary: Updating of the activities carried out on-site (Done) in SEPTEMBER List activities on going (Next steps) and scheduled for OCTOBER.
CENF – Civil Engineering Extension B887 Status – 18 September 2014 Done: (1/2) Preliminary civil engineering drawing and Functional specification approved.
Last but not least : LS2 General Safety 1 Thomas Otto, LS2 Safety Coordinator for LHC Ana-Paula Bernardes, LS2 Safety Coordinator for Injectors.
Survey Meeting John Osborne, CERN 8 February 2016
28 th January LHC Performance Workshop Session 8: (E)YETS and Long Shutdown 2 Strategy and Preparation. Long.
28 th January LHC Performance Workshop Session 8: (E)YETS and Long Shutdown 2 Strategy and Preparation. General.
Each converter 3 racks (fighting for 2?) Access from front and rear of each rack! 56 racks total + 6 racks Ethernet/control Existing RF equipment to be.
19 February Extension of Building Neutrino Platform General Meetings N.Lopez – M.Manfredi EHN1 civil engineering project status Summary: Updating.
Dr. José Miguel JIMENEZ LS2 Project Leader, CERN 1 LS2 Days 30 th September2015.
D.Macina TS/LEATOTEM Meeting25/02/2004 Roman Pot test at the SPS Test of the Roman Pot prototype in the SPS proposed in December 2003 (CERN/LHCC ):
© Awad S. Hanna, PhD, P.E.1 Estimating and Scheduling CEE 492 Lecture 5 ESTIMATING EARTHWORK.
1 st of April st LS2C LS2 Committee Mandate and Organization 2 Chairman:Jose Miguel JIMENEZ Deputy:Jean-Philippe.
Work by contractors And Safety Coordination CONTRACTORS ’ ACTIVITIES What is the role of TSOs when contractors are working in their area? HSE Unit - Olivier.
Proposal for rerouting of buried electrical networks and optical fibres at Point 1 LS2 Committee meeting S. Bertolasi on behalf on EN/EL WP17.2 HL-LHC.
WP 17.1 Civil Engineering Platform height / vs option Status on M. Manfredi on behalf of WP17.1 team.
DIAPHRAGM WALLS.
Pieter Mattelaer (SMB-DI)
21 January Summary: Updating of the activities carried out on-site (Done) in DEC + ½JAN List activities on going (Next steps) and scheduled till.
10 December Summary: Updating of the activities carried out on-site (Done) in NOVEMBER List activities on going (Next steps) and scheduled for DECEMBER.
Deep Residential Basement, Chelsea. Toureen Plant Toureen Plant Toureen Contractors City Basements Groundworks RC Frames Groundworks RC Frames Petrol.
25 June EHN1 civil engineering project status (MAY) Summary: Updating of the activities carried out on-site (Done) in MAY List activities on going.
Multnomah County Central Courthouse Site Due Diligence Update April 9, 2015 JD Deschamps Mike Pullen Mike Day.
LS2 Safety Preparation Thomas Otto, LS2 Safety Support Officer for LHC
Civil Engineering for FCC-eh and LHeC
Substructure Groundworks - Hazards
Marco Oriunno (SLAC), March 12, 2014 MDI WG
Safety in Construction and Upgrade Phases
Types of Protection Introduce the module. Trenching & Excavations Continuing Education Third Quarter 2017 Session 2.
Background B513 built in early 1970’s for mainframe era.
Accelerator and Experiment Interface Session: LS2, LS3
RWTCS Steering Commitee
Civil Engineering for FCC-eh IR
CLIC Civil Engineering Update
East Hall under construction
CT Reinforced Earth Structures
4th Annual Construction Law Summit
Project Aerial Site Plan
ESTIMATING EARTHWORK Prof Awad S. Hanna.
ESTIMATING EARTHWORK Prof Awad S. Hanna.
Presentation transcript:

WP 17.1 Civil Engineering Point 1 - Networks LS2 COMMITTEE – CERN – Pieter Mattelaer (SMB-DI)

HiLumi site at Point 1 - ATLAS LS2 Committee - Point 1 Networks2 Worksite Area (approx. 20% increase in ATLAS surface area )

HiLumi site at Point 1 - ATLAS LS2 Committee - Point 1 Networks3

HiLumi site at Point 1 - ATLAS LS2 Committee - Point 1 Networks4

HiLumi & existing networks at Point 1  Compatibility btwn HiLumi infrastructure & existing networks at Point 1 is problematic;  HiLumi site at Point 1 is small & constrained (CERN land, border, networks, footpaths);  GE authorities require re-use of excavation spoils on site; create platform at level of existing ATLAS site;  Existing networks follow natural terrain slope; expose networks when regrading site;  Difficult to construct buildings close to existing networks; high risk of accidental damage; → proposal to reroute existing networks LS2 Committee - Point 1 Networks5

Base case: Platform at 442.0m LS2 Committee - Point 1 Networks6

Base case: Platform at 442.0m  Existing HV + fiber networks are diverted;  Retaining wall to create physical barrier btwn site and networks;  Platform elevation at ≈ elevation of ATLAS site; ease of access;  Minimal interface btwn networks & HiLumi civil works;  Risk of accidental damage to networks minimized; LS2 Committee - Point 1 Networks7

Alternate: Raised platform at 443.5m LS2 Committee - Point 1 Networks8

Alternate: Raised platform at 443.5m  Existing HV + fiber networks remain in place;  Long 5% ramp btwn HiLumi & ATLAS sites;  Additional costs for deeper foundations;  Building permit issues; spacing btwn buildings;  5 years of civil works adjacent to live lines;  Accidental damage to networks is likely; LS2 Committee - Point 1 Networks9 1.5m deep 443.5m Strategic HV Power lines and Optical fibers for LHC machine Burried 1.5m deep, during 5 year worksite

10 Alternate: Raised platform at 443.5m Cost (*) : Related to raising the level of all HiLumi buildings  Earthworks and filling w/ on-site material up to level:  Cost reduction for reduced soil volume exported from CERN site:  Earthworks and filling w/ compacted material up to level:  Excavation w/ temporary soil support system (Δ=1.5m):  Execution of higher concrete foundations (Δ=1.5m):  Final backfilling along foundations and galleries: TOTAL (*) : 160 KCHF -270 KCHF 235 KCHF 395 KCHF 695 KCHF 100 KCHF ≈ 1’315 KCHF LS2 Committee - Point 1 Networks (*) Lowest possible cost, based on the foundation scheme considered. Costs can easily being much higher if deep foundations need to be executed instead. Consultant will determine whether or not deep foundations are required.

Required distance btwn buildings  Legally required distance between buildings depends on building height calculated relative to original terrain altitude;  Increase in platform elevation = increase in required distance btwn buildings; impacts SR, SF, HSE; LS2 Committee - Point 1 Networks11

Comparison: platform at 442.0m vs m Topic442.0 platform443.5 platform Scope of civil works More limitedMore significant Interface riskDiversion of networks before civil works start, no overlap or interface Complicated interface, e.g. existing networks need to be protected when HiLumi buildings are constructed very nearby (≈2m) Extent of riskLocalized (the places where lines will be cut & jointed) Along entire length of SD17 and partially SHM17 Duration of riskFew days (only during cutting & jointing of networks) Years (during the civil works on HiLumi site ) Risk managementRelatively easy - limited interface between networks and civil works Very difficult - impossible to ensure ‘precision’ with heavy CE equipment Risk levelRelatively controlled risks associated to re-routing of existing networks Uncontrolled risks related to contractor’s care on site ≈ network damage is likely Impact on building permitBase caseAdditional platform may negatively impact application; required space btwn SF and SR will increase, SHE needs to be repositioned Cost (SMB + EN-EL)≈ 585 KCHF (see EN-EL)MIN. ≈ 1315 KCHF LS2 Committee - Point 1 Networks12 → CE recommends 442.0m & rerouting of networks

Time windows to reroute networks  The LS2 PERIOD includes: -Extended Year End Technical Stop (EYETS) (19wks) -Year End Technical Stop (YETS) (13wks) -Long Shutdown 2 (LS2) LS2 Committee - Point 1 Networks13 Source: ‘Framework Schedule from EYETS 2016 to LS2’, Chamonix on Current planning of civil works: Q1 / 2018: site installation; : start of shaft excavation; start of excavation

Planning of HiLumi civil works LS2 Committee - Point 1 Networks14 EYETS (no overlap w/ CE) YETS (no or minimal overlap w/ CE) start LS2 (overlap w/ CE)

Conclusions  Compatibility btwn HiLumi infrastructure & existing networks at Point 1 is problematic;  Main objective is to avoid accidental damage to existing networks during 5 year civil construction site (while LHC is in operation);  WP17.1 recommends HiLumi platform at 442.0m, which requires rerouting of (some) existing networks;  Preferred time window: YETS (or EYETS); to avoid overlap with excavation work during LS2; LS2 Committee - Point 1 Networks15