Global Design Effort Close-Out Points EDR time-scale (2010) –No demonstrations to ILC-like RF unit –3(?) CMs constructed at FNAL – not RDR baseline –2(?)

Slides:



Advertisements
Similar presentations
CFS TIME SCHEDULE EDR - CFS Europe – Kick-Off Meetings Kick-Off Meetings, CERN, 3, 4, 5 September ILC PROJECT ENGINEERING DESIGN REPORT CFS Europe.
Advertisements

April SCRF Meeting FNAL08 S.Fukuda 1 HLRF Summary and Work Assignment S. FUKUDA KEK.
BDS GDE context LC-ABD2 : WP4 - Beam Line Design 12 th April 2007, LC-ABD Plenary, RHUL Deepa Angal-Kalinin ASTeC, The Cockcroft Institute.
Systems Engineering Management
Global Design Effort - CFS TILC09 and GDE AAP Review Meeting - Tsukuba, Japan 1 GDE ACCELERATOR ADVISORY PANEL REVIEW CONVENTIONAL FACILITIES.
Global Design Effort BDS KOM Opening remarks/comments from EDR Project Management SLAC Marc Ross / Nick Walker.
Akira Yamamoto Project Manager, SCRF To be presented, April 19, 2009 AAP Review – SCRF Introduction AAP-SCRF-Introduction.
Global Design Effort U.S. ILC Cost Translation R. Stanek, et al. Vic Kuchler 1/26/07.
ISM 5316 Week 3 Learning Objectives You should be able to: u Define and list issues and steps in Project Integration u List and describe the components.
Nick Walker, Brian Foster LAL, Orsay WP2: Coordination with the GDE.
April 1, 2007 Global Design Effort 1 Materials for S4 meeting Discussion of risks in BDS WP April 1, 2007.
HLRF DRAFT Global Design Effort 1 Defining EDR* Work Packages [Engineering Design Report] Ray Larsen SLAC ILC Division for HLRF Team DRAFT April.
Summary of WG1 K. Kubo, D. Schulte, P. Tenenbaum.
Cryomodule Design and R&D during the EDR phase Robert Kephart With input from the T4 CM Collaboration.
OFFICE OF SCIENCE 2.3 Infrastructure and Installation Sims, Edwards 1.Does the conceptual design and planned implementation satisfy the performance specifications.
M. Ross, N. Walker, A. Yamamoto ILC Cost Review, (updated for TB) and Cost Drivers  Future R & D ILC Cost Review (M. Ross,
Nick Walker Marc Ross Akira Yamamoto 2010 (and beyond) Plans & Milestones.
RDR Report Writing Nan Phinney SLAC. 7/20/06 VLCW06 Global Design Effort 2 GLC Report Working model is the 2003 GLC Report ch 4-7
Hall 180 Cryogenic test facility: Project management: Project Change Request, EVM and Interface Sheet L. Serio.
Date Event Global Design Effort 1 ILC Engineering Design Phase - Status & Plans Mike Harrison GDE/BNL.
1 Global Design Effort TILC08 - WG1 Summary WG-1: Cost Reduction Studies J. Carwardine, T. Shidara, N. Walker (For WG-1 participants)
24-Aug-11 ILCSC -Mumbai Global Design Effort 1 ILC: Future after 2012 preserving GDE assets post-TDR pre-construction program.
ML Planning for ILC08 First Pass + SCRF agenda Chris Adolphsen Hitoshi Hayano.
ML Planning for ILC08 First Pass Chris Adolphsen Hitoshi Hayano.
The fourth Baseline Technical Review (BTR) - Conventional Facilities and Siting March 2012 All changes made to the CFS 2007 Reference Design during.
Global Design Effort Accelerator System Kick-off Meeting e- source SLAC Marc Ross.
ALCPG/GDE Meeting FNAL Global Design Effort 1 Cavity Work Packages Lutz Lilje GDE.
AD & I 15 August 2012 Marc Ross R&D for TDR Summary of TDP R&D items and baseline changes to RDR – to be included and highlighted in TDR text
October 23, 2007 GDE EDR Meeting 1 EDR Strategy and Timeline Cavities and Cryomodules Rich Stanek October 23, 2007.
Date 2007/Oct./25 FNAL-GDE-Meeting Global Design Effort 1 Cryomodule Report N. Ohuchi KEK 1.Cryomodule & Cryogenics KOM 2.GDE-meeting discussion I.Interface.
SCRF Parallel Sessions at TILC09 GDE 活動報告 3月30日(月)10時~ 3号館7階会議 室 設楽 哲夫.
Global Design Effort - CFS Damping Ring Baseline Technical Review 1 DAMPING RING BASELINE TECHNICAL REVIEW CONVENTIONAL FACILITIES AND SITING.
1 Global Design Effort: Controls & LLRF Controls & LLRF Working Group: Tuesday Session (29 May 07) John Carwardine Kay Rehlich.
Industrial Participation & SRF Infrastructure at Fermilab Phil Pfund with input from Harry Carter, Rich Stanek, Mike Foley, Dan Olis, and others.
SCRF Cavity WebEx Meeting May 17, 2010 Reports from PM (10 min.) – Brief report from ILC-PAC – Industrialization workshop as IPAC satellite meeting, Kyoto,
Global Design Effort: Controls & LLRF Americas Region Team WBS x.2 Global Systems Program Overview for FY08/09.
Carlo Pagani University of Milano INFN Milano-LASA & GDE ILC and XFEL Cryomodules Preliminary thoughts for convergence ILC EDR Kick-off Meeting DESY,
ILC Cryogenic Systems Status and EDR Plans Tom Peterson 25 October 2007.
Tor Raubenheimer KEK Mtg Goals KEK January 19 th, 2006.
M. Ross, N. Walker, A. Yamamoto th ATF2 Project Meeting Accelerator Design and Integration – New Baseline Proposal for ILC – ‘Strawman Baseline.
Global Design Effort Main Linac Technology System Kick-off Meeting Cavity Summary 20 Sept 2007 DESY Marc Ross.
24-July-10 ICHEP-10 Paris Global Design Effort 1 Barry Barish Paris ICHEP 24-July-10 ILC Global Design Effort.
Accelerator Systems TAG Leaders’ Meeting PM Report –Planning for ALCPG –TDR preparations: Area System Baseline Technical Reviews –Recent e+ workshop experience.
Global Design Effort Accelerator Systems EDR Kick-Off Meetings Preparation Nick Walker.
ILC 2007 Global Design Effort 1 Planning Damping Rings Activities in the Engineering Design Phase Andy Wolski Cockcroft Institute/University of Liverpool.
Global Design Effort1 September 20-22, 2006 MAC Review Response to 1 st MAC Mtg Barry Barish GDE.
PM Report AS ILC PAC (19-20 May) Agenda: –Akira, Rongli, Hitoshi H, Marc, Nick, Toshiaki, Mark P., Peter G. –Nick will report on Design –Marc.
Summary: Site Discussion Jonathan Dorfan SLAC Plenary Session, June 6, 2008.
Summary of SCRF Meeting Fermilab, April 21-25, 2008 April 25, 2008 General Summary and Further Plan: 4/21: Cavity: Gradient R&D, performance, diagnostics.
February 4, 2007 Global Design Effort 1. February 4, 07 Global Design Effort IR&MDI: 2 Tuesday’s discussion EDR organization Work Package distribution.
Report of HLRF KOM/ALCPG07 S. Fukuda(KEK) R. Larsen(SLAC)
TLCC Themes BAW-2, SLAC, 19 January 2011 Ross Walker Yamamoto 1.
CFS / Global – 09 June, 2010 PM Report: SB2009: –4 two-day workshops form the core of ‘TOP LEVEL CHANGE CONTROL’ –  as advised by AAP, PAC and etc –Written.
Main Linac Technology (MLT) Meeting To be held through WebEx July 13, 2007.
Global Design Effort Accelerator System Kick-off Meeting e- Summary Day 1 25 Sept 2007 SLAC Marc Ross.
1 Comments concerning DESY and TESLA Albrecht Wagner Comments for the 5th meeting of the ITRP at Caltech 28 June 2004 DESY and the LC What could DESY contribute.
Global Design Effort RTML KOM Close-out Ross, Walker.
LARP Crab Cavities Cryomodule Integration Meeting Final Notes A.Ratti LBNL.
Saclay / Orsay visit – (GDE Project Managers) 1 R&D Plan: ‘Engineering Design’ Phase - presentation to Saclay / Orsay Marc Ross, Akira Yamamoto,
Global Design Effort Controls LLRF EDR Kick Off Meeting View from the Project Management Office Fermilab / ANL August 20, 2007.
1 AS TAG Leaders Meeting Webex - Friday S. Guiducci, M. Palmer.
PM Report CFS /Gbl ILC PAC (19-20 May) Agenda: –Akira, Rongli, Hitoshi H, Marc, Nick, Toshiaki, Mark P., Peter G. –Nick will report on Design.
July 11, 2008M Ross for PM - ILC GDE - ILCDR08 closeout 1 GDE Program for the ILC Technical Design Phase Marc Ross for: Akira Yamamoto, Nick Walker GDE.
Oct 22 Group Leaders Planning meeting
Meeting for S1-Global module design Cryomodule and Cryogenics
ILC Project Management Status
Yamamoto WG3: ML-SCRF Parallel Session,
Nick Walker (DESY) EU GDE Meeting Oxford
ILC Cryogenics -- Technical Design Report Planning
RF System (HLRF, LLRF, Controls) EDR Plan Overview
Presentation transcript:

Global Design Effort Close-Out Points EDR time-scale (2010) –No demonstrations to ILC-like RF unit –3(?) CMs constructed at FNAL – not RDR baseline –2(?) CM constructed – not RDR baseline –XFEL mass-production ~20-30 XFEL CMs mass-produced and high-power tested What to put into the EDR? –Must be a construction-ready or near construction-ready technology –Gradient is still an issue (~independent of CM design/DFM S0 remains GDE highest-priority) –Plug-compatibility concept for alternative designs (R&D) needs refinement (on-going) –NB coupler kicks clearly mandate some modifications: minimum intervention? NB: beyond EDR equally important –We want to construct machine with best (cost effective) and mature state- of-art technology VERY IMPORTANT for EDR: show that US/Asia have attained core competency in SC ML technology

Global Design Effort Work Packages WP (for EDR!) need clearer definition –Template coming International resource situation must be taken into account –At level-3 –Certainly at PM level For SC magnets, cold BPM, coupler, etc. known resources from Europe and Asia have to be included –They bring much needed money to the table, and strengthen the global collaboration –Presentations where FNAL-centric Resource balancing will happen at some level –WP allocation not yet a done deal Discussion on “alternative” down select very useful –Plug compatibility avoids the ‘down-select’ issue to some level –For the EDR (!) status and maturity of ‘plug compatible’ components will still need to be evaluated –New VALUE estimate must reflect most mature designs (minimum risk) (side comment: find down-select an ugly concept – need a better word)

Global Design Effort What are the MLI responsibilities / WPs Cavity package - no Cryomodule - no HLRF development - no Specifying performance parameters – yes! Optimisation (cost/performance) of complete system – yes! Integration layout issues – yes! Beam dynamics (performance issues) – yes! Lattice design – yes! CFS interfaces – yes! … WPs should reflect milestones in producing a fully integrated design for the ML

Global Design Effort Other critical issues HP/HOM coupler wakes –Mandates modification to CM/Cavity ? Waveguide heat-loss issues –And operational issues  LLRF LLRF required overhead and operation (gradient spread) –  consider experiments at TTF Coupler design –IMO only issue is possibility of cost reduction for mass-production –Again, many ‘variants’: relationship with EDR needs to be understood and quantified Reliability often mentioned –Need plan and ‘definition of success’. CFS requirements, interfaces, derivatives (performance/cost) THESE (and others) should appear as WPs in the WBS. –Should also devise WPs covering possible experiments to do at TTF (for example)

Global Design Effort VALUE estimate (EDR policy) We have not discussed directly costs! –Perhaps implicitly The CURRENT VALUE RDR estimate will be linked with the BASELINED definition, and both will be put under change control Changes to the VALUE estimate will be reviewed (formal change request) –As part of a technical change request to the baseline (cost impact) –Or as an update VALUE estimate for the existing baseline. PM considers this critical for maintaining costs –VALUE estimate will evolve continuously as EDR progresses –(Should consider scheduled reviews/re-estimates for key systems) –Hopefully avoid last minute panic and “sticker shock” at end of ED phase WE are looking for actions that reduce the cost, not increase it (“better” performance)

Global Design Effort Recap: immediate goal for GDE meeting WP definitions must be documented and available by GDE meetings –For this group this is Chris’ responsibility –(template next week) Open WP allocation process: all international interest and available resources must be considered FNAL meeting will have parallel sessions for refining WP definitions and continued discussions on critical technical issues. Formally establish EDR baseline –Plug compatibility design parameter specifications for cavity and cryomodule We need a plan, Gentlemen!

Global Design Effort Finally… Thanks for a great and extremely interesting meeting! –Presenters! –Special thanks to Chris for orchestrating