1 Yagmur Torun, IIT Katsuya Yonehara, Fermilab Dec 16, 2010 – MAP PMG Meeting.

Slides:



Advertisements
Similar presentations
High pressure RF cavity project Katsuya Yonehara APC, Fermilab 2/28/11 - 3/4/111.
Advertisements

Beam Test of a High-Pressure GH 2 -Filled RF Cavity (for efficient muon beam cooling for a MC or NF, since the low-Z ionization energy-loss absorber and.
MuCool Outlook and Plans  Over the past year we have had a very successful program that will be detailed in the next two sessions: u MuCool Test Area.
BEPCII RF POWER SYSTEM RF group, IHEP Sep ~ April 1.The 1 st transmitter had finished installing,commissioning and SAT (Site Acceptance Test).
Muon g-2 Muon g-2 Experiment Quarterly Report Aria Soha All Experimenter’s Meeting March 2, 2015.
Progress of High Pressure Hydrogen Gas Filled RF Cavity Test Katsuya Yonehara Accelerator Physics Center, Fermilab MTA RF workshop Fermilab, November 15-16,
FAC, 10/12/06 D. Schultz 1 e-Beams Systems Update Linac Injector Undulator Production MMF commissioning ARR David Schultz.
All Experimenters’ Meeting January 09, Accelerator Operation Summary Calendar Week # 51 NuMI Weekly Integrated Intensity 8.81E18 protons BNB Weekly.
MUTAC Review 3/16/06 A. Bross MuCool Overview and Plans Muon Cooling R&D MUTAC Review March 16, 2006 A. Bross.
MuCool RF Status MICE Collaboration Meeting June 7-10, 2006, Fermilab A. Moretti June 9, 2006.
Update Hardware for conductive cooling of the quench resistors has been fabricated at LBNL. Preparation for installation to start this week. Installation.
Automation of the 805MHz cavity conditioning procedure Ajit Kurup MuCool Test Area RF Workshop, Fermilab 22 nd August 2007.
Scientific Goals: V. Litvinenko’s RHIC retreat talk Commissioning Goals: I. Pinayev presentation last week Run 14 Goals: Complete assembly of 112 MHz SCRF.
NOvA meeting PIP Update W. Pellico. PIP Goals and Scope (Provided in 2011 – Directorate S. H. / DOE Talk ) Goals: Specific to the issues surrounding the.
GlueX Solenoid Update George Biallas May 12, 2010 GlueX Collaboration Meeting.
Single-Cavity Module Installation at MuCool Test Area Yağmur Torun MICE Collaboration Meeting February 15, 2013.
Linac Front-End R&D --- Systems Integration and Meson Lab Setup
MCTF C. Johnstone All Exp. Meeting 14 Mar First Beam to Muon Test Area Description and commissioning of beam to MTA Experimental Hall C. Johnstone,
MICE - UK Project Progress Roy Preece 30 th April 2013.
ILCTA_NML Progress at Fermilab Jerry Leibfritz September 10, 2007.
Summary of the AWAKE Technical Board Meeting September 2014 – March 2015.
PIP Update Aug 6 th Agenda Summary Update – Current Activities/Updates – New Tuner Test Result: Reid & Slabaugh – Anode Supplies: Crawford.
09/28/07Shutdown’07 Week 8 F.G. Garcia1 MTA beam line installation Weekly Report September 28, 2007 Period covered: September 24 th September 28 th (Week.
Installation and Commissioning Planning Leslie Camilleri Calorimeter Commissioning Meeting 5 th September 2006.
Schedule and Work We are moving into a very intensive 4 months with a lot of work to be carried out Electrical services to the devices – after the South.
Electron Spectrometer Work Package Simon Jolly 19 th May 2014.
Global Design Effort Beam Delivery System => EDR LCWS07 June 2, 2007 at DESY Andrei Seryi for BDS Area leaders Deepa Angal-Kalinin, A.S., Hitoshi Yamamoto.
Status of Beam loss Monitoring on CTF3 Results of Tests on LINAC and PETS as R&D for TBL Anne Dabrowski Northwestern University Thibaut Lefevre CERN CTF3.
UKNF OsC RAL – 31 st January 2011 UKNF - Status, high lights, plans J. Pozimski.
805 MHz Status IIT NFMCC Meeting March 12-15, 2006 A. Moretti March 12, 2006.
08/31/07Shutdown’07 Week 4 F.G. Garcia1 MTA beam line installation Weekly Report August 31, 2007 Period covered: August 24 th to August 31 st (Week 4)
Report of High Pressurizing gaseous Hydrogen filled RF cavity experiment K. Yonehara on behalf of HPRF working group APC, Fermilab 1/13/101 NFMCC meeting.
MCTF 8/17/06 A. Bross MTA Activities and Plans MCTF August 17, 2006 A. Bross.
MICE Status & Plans MICE-UK paul drumm 15 th September 2004.
Proton Improvement Plan Keith Gollwitzer January 5th, 2015 All Experimenters’ Meeting 11/5/2015Gollwitzer AEM.
Forward Muon Installation and Commissioning Dmitri Denisov Fermilab Director’s review 7/12/1999 Plan Forward muon detectors Mini-drift tubes installation.
The Stripping Foil Test Stand in the Linac4 Transfer Line
Recent progress of RF cavity study at Mucool Test Area Katsuya Yonehara APC, Fermilab 1.
MTA RF Status 01/31/ 2007 NF&MCC Meeting UCLA A. Moretti.
Target Commissioning Target installed in ISIS “Demonstrator” target in R78 Initial commissioning plans Chris Booth Sheffield 11 th February 2008.
A. Bross MICE CM17 February MuCool RF Program 805 and 201 MHz Studies.
Updated Overview of Run II Upgrade Plan Beam Instrumentation Bob Webber Run II Luminosity Upgrade Review February 2004.
1 Alan Bross AEC March 31, 2008 MuCool RF Program Muon Cooling R&D Alan Bross.
YETS activities in n_TOF O. Aberle, S. Montesano (EN/STI)
High Intensity Neutrino Source Program Overview for CD Controls Management Meeting Bob Webber October 6, 2006.
August 12, Machine Status: 2013  Proton Source Commissioning and Studies RFQ Injector Line (RIL) Linac : Roof hatch installed Booster : Magnet.
Date 2007/Sept./12-14 EDR kick-off-meeting Global Design Effort 1 Cryomodule Interface definition N. Ohuchi.
ALBA RF System Paco Sanchez - 13th ESLS RF - DESY, 30 September Paco Sanchez, RF Group, CELLS (Consortium for the Exploitation of the Synchrotron.
Status of high pressure RF cavity project K. Yonehara Accelerator Physics Center, Fermilab 10/08/20101MAP Friday meeting.
Progress of high pressure hydrogen gas filled RF cavity K. Yonehara APC, Fermilab 11/02/111 Joint MAP & High Gradient RF Workshop, K. Yonehara.
Booster Status, September 4, 2003 – E. Prebys 1 Frantic Shutdown Preparations Continue…
Measurement of 400 MeV Proton Beam Intensity and Transmission Through Collimator of HPRF Cavity at Fermilab MuCool Test Area M. R. Jana 1, M. Chung 1,
Progress of High Pressure Hydrogen Gas Filled RF Cavity Test Katsuya Yonehara Accelerator Physics Center, Fermilab Muon Accelerator Program Review Fermilab,
Proton PMG September 3 rd 2015 Cons Gattuso AD Shutdown Manager.
ILCTA_NML Progress at Fermilab Jerry Leibfritz August 16, 2007.
Schedule to completion, Risk and Critical Interfaces Roy Preece STFC RAL RLSR 16 th April 2015.
Schedule and Milestones Roy Preece STFC RAL FAC 17 th April 2015.
MTA Data Acquisition System K. Yonehara APC, Fermilab 1/14/15MTA DAQ, K. Yonehara1.
Mike Andrews January 31, Weeks Activities Target Pile Fan Upgrades Install piping for new cooling coil units Install controls for new coil.
Proton PMG May 7 th 2015 Cons Gattuso AD Shutdown Manager.
Areal RF Station A. Vardanyan
CBETA Technical Review
MuCool Test Area Dedicated facility built at the end of the Linac to address MuCool needs RF power 805MHz, 201MHz)
LERF as Cryomodule Testing Facility Set-Up and Installation Logistics
ELENA installation and commissioning status
Summary of MuCool/MTA RF workshop
Advanced Research Electron Accelerator Laboratory
Injector/Linac Design Status C. E
LCLS e- Beams Systems Manager
Polarized 3He target installation
Presentation transcript:

1 Yagmur Torun, IIT Katsuya Yonehara, Fermilab Dec 16, 2010 – MAP PMG Meeting

MTA Status: Detectors & DAQ Scintillation counters in the hall being retested this week and next Preparing for DAQ infrastructure to support 2 nd RF station extra electronics rack installed in Linac Gallery new patch panels in hall and Linac new signal cables to be terminated some parts in the machine shop Part of the DAQ (CAMAC) that reads out scintillators being debugged The other part (LabView) that controls the RF is stable Both will be tested with a common external trigger next week during pillbox cavity commissioning Expect all this to be ready by the end of December Also want to install some sensors for monitoring the environment in the hall (temp/humidity, air flow and quality, water on floor) parts mostly in hand, will proceed when other jobs complete 2

MTA Status: Shielding, Cryo, Beamline Bead installation in penetrations mostly complete Hand-stack blocks for refrigerator room delivered Cryo system stable but we have some work to be scheduled need to replace 2 leaking valves 2 weeks of downtime required for reconfiguration (to address condensation in the hall) preferable to do both at the same time 2nd compressor hooked up, still to be powered (coordination with Booster) and commissioned Water from the hall to be dumped outside or moved to MI65 for evaporation/disposal as necessary Expect to have cryo manpower by mid-January New core for 2nd beam stop is ready, 3 days of work left in the hall to replace the core and install the multiwire Beam pipe extension to be complete late January Stability test for beamline magnets carried out last night 3

MTA Status: RF 805 pillbox is installed and under vacuum Calibration tomorrow after which we'll be ready to power it Will also get the surveyors to align it Instrumentation should be complete next week Analysis of magnetic field data for the solenoid (needed for box cavity data analysis) in progress 2 nd 805 MHz RF station set up RF switch installed lift table assembled in the hall waveguide parts available directional couplers on order can install HPRF cavity this month 4

MTA Status: Urgent items & issues We could use help with the following minor issues Machine shop priority for electronics rack door modifications Same for beam pipe extension Tech effort for connector installation on cables in the MTA Hall Recent retirement program will affect operations Wickenberg (MTA building manager) Mau (AD/Operations) Misek (AD/Mechanical) Longer term Preparing for coupling coil installation (early 2012?) major task that will require resources 5

Prospect of High Pressurized H2 gas filled RF cavity project Short term (~ FY12) Demonstrate thecavity under high radiation condition Investigate beam induced plasma in the cavity Figure out beam loadingmechanismand suppress it Make a new cavity to test the modification technology Provide information to high level management group for RF technology selection (including with safety issue) Long term (FY13 ~) If the HPRF cavity is chosen as the RF technology Make a realistic RF cavity - Test in cryogenic condition - Test in cooling channel fields - Test gas regulation system - etc 6

Time table of HPRF beam test Nov, 2010Dec, 2010Jan, 2011 RF modification, assemble & calibration Wave Guide & Circulator Beam line Detector & DAQ Timing Calibration RF test without beam RF beam test 805 MHz button cavity test Time duration: 3~4 months Beam will be available in January 7

MTA beam line MTA experimental hall MTA solenoid magnet Final beam absorber 400 MeV H - beam Beam profile: Deliver 400 MeVH - beam in the MTA exp. hall to H - /pulse Tune beam intensity by using collimator and triplet Reduce factor from full linac int. down to 1/40 or less MTA exp hall 400 MeV H - beam 8

Apparatus for beam test 400 MeV H - beam Elastic scattered proton from vacuum window (100~1000 events/pulse) No energized device within 15 feet from HP cavity due to hydrogen safety issue Beam must be stopped in the magnet due to radiation safety New apparatus: New HPRF cavity Beam extension line Collimator+Beam absorber Luminescence screen+CCD Beam counter RF circulator + damper etc… (Ti) Bound electrons of negative Hydrogen will be fully stripped in the vacuum window Ex) Thickness = 4.5 g/cm 3 × 0.1 = 0.45 g/cm 2 Stripping cross section ~ cm /47.9 × = =

New RF cavity& collimator 10 Current status New RF test cellis ready New rail systemis ready New collimatoris ready Final check and modification Collimator HPRF cell RF coax line beam Gas inlet RF inlet Support rail Luminescence screen 10

Beam extension line 400 MeV H - beam Elastic scattered proton from vacuum window (Ti) Current status Discussed with engineer Final drawing will come out soon They expected two weeksforconstruction period 11 5 meter 1 meter

New beam diagnosticsystem 400 MeV H - beam Elastic scattered proton from vacuum window (Ti) Current status Luminescence screen+ CCDare ready Prepare a telescope beam counter tomake a beam trigger signal Make a small toroidcoilto measure beam intensity 12

Data flow and acquisition 13

Data acquisition system 14 SiPM/PMT RF Pickup 1 2 RF Forward 1 RF Return 1 Beam counter RF Klystron trigger System trigger Gate NameDiagnostic signal ADC input SiPM/PMT1Top plate Light trig. Fast Osc1 SiPM/PMT2Top plate Spectroscopic Fast Osc1 SiPM/PMT3Topl plate TPB/spare SiPM/PMT4Side wall Light trig. SiPM/PMT5Side wall Spectroscopic SiPM/PMT6Side wall TPB/spare RF Pickup1Electric signalFast Osc1 RF Pickup2Magnetic signalSlow Osc RF Forward1Upstream of Circulator RF Return1Upstream of Circulator Slow Osc RF Forward2Between Circulator&cavity RF Return2Between Circulator&cavity Slow Osc Toroid1In front of cavityFast Osc1 Toroid2MTA beamlineFast Osc2 Beam counterTelescopeFast Osc2 RF KlystronTTL From MCRFast Osc2 14

Fine timing calibration ps Laser HPRF Optical feedthrough SiPM/PMT Digital Oscilloscope ½” Heliax for RF pickup signal ½” Heliax for Optical signal Current status All devices is ready Goal: Timing calibration < 100 ps 15

Summary 16 Beam test will be ready in January, 2010!! Study beam induced plasma physics - Made model and simulate RF Q factor reduction due to plasma - Made analysis tool to investigate plasma in the cavity New RF cavity, collimator system, and beam absorber are ready - Need final check and small modification - Need to build beam extension and vacuum window - Need to extend 800 MHz waveguide - Need to assemble RF power dumper Diagnostic system - Need to work on beam counter and toroid coil - Luminescence screen and CCD are ready Data acquisition system -LabView system is ready - Need to work on logic signal (CAMAC) system Documentation for safety assessment - Hydrogen safety document is ready - Preparation of radiation shielding assessment is on going

17

18