ORNL is managed by UT-Battelle for the US Department of Energy Commissioning experience of SNS Ring By M. Plum ICFA mini-workshop on beam commissioning.

Slides:



Advertisements
Similar presentations
Machine Physics at ISIS Proton Meeting 24 th March 11 Dean Adams (On behalf of ISIS Accelerator Groups)
Advertisements

Experience with Bunch Shape Monitors at SNS A. Aleksandrov Spallation Neutron Source, Oak Ridge, USA.
Masahito TOMIZAWA and Satoshi MIHARA Accelerator and proton beam.
1 Proton Upgrades at Fermilab Robert Zwaska Fermilab March 12, 2007 Midwest Accelerator Physics Collaboration Meeting Indiana University Cyclotron Facility.
Alexandr Drozhdin March 16, 2005 MI-10 Injection.
Paul Emma LCLS FAC April 16, Initial Experience with Injector Commissioning P. Emma, et al. Facilities Advisory Committee.
Space Charge Issues in the SNS Linac and Ring
Sergey Antipov, University of Chicago Fermilab Mentor: Sergei Nagaitsev Injection to IOTA ring.
Managed by UT-Battelle for the Department of Energy SNS MEBT : Beam Dynamics, Diagnostics, Performance. Alexander Aleksandrov Oak Ridge National Laboratory.
Review on PSB 160 MeV H- Injection Nov 9-10, 2011 Closeout by P. Cruikshank, M. Giovannozzi, D. Johnson, B. Jones, B. Pine, M. Plum, D. Tommasini.
Eric Prebys USPAS, Knoxville, TN, Jan , 2014.
Tuning an Accelerator for 1 MW C. Peters WAO 12 August 8 th, 2012.
3 GeV,1.2 MW, Booster for Proton Driver G H Rees, RAL.
A U.S. Department of Energy Office of Science Laboratory Operated by The University of Chicago Argonne National Laboratory Office of Science U.S. Department.
Recycler Status and Plans Shekhar Mishra MID/Beams Division Fermilab AAC Review 2/4/03 Introduction to the Recycler Ring Recycler Improvements and status.
Advanced Accelerator Design/Development Proton Accelerator Research and Development at RAL Shinji Machida ASTeC/STFC/RAL 24 March 2011.
J-PARC Accelerators Masahito Tomizawa KEK Acc. Lab. Outline, Status, Schedule of J-PARC accelerator MR Beam Power Upgrade.
ATF2 beam commissioning status and beam time request Toshiyuki Okugi 2008 / 11 / 12 ATF2 Commissioning Meeting.
RHIC Status: Startup Run 12 V. Schoefer RHIC Spin Collaboration Meeting 1/13/12.
Managed by UT-Battelle for the Department of Energy Analysis of 2008 Beam Instability Data S. Cousineau, V. Danilov, M. Plum HB2008.
F Proton Plan Eric Prebys, FNAL Accelerator Division.
1 BROOKHAVEN SCIENCE ASSOCIATES Storage Ring Commissioning Samuel Krinsky-Accelerator Physics Group Leader NSLS-II ASAC Meeting October 14-15, 2010.
Alexander Aleksandrov Oak Ridge National Laboratory
PROTON LINAC FOR INDIAN SNS Vinod Bharadwaj, SLAC (reporting for the Indian SNS Design Team)
Managed by UT-Battelle for the Department of Energy Using Online Single Particle Model for SNS Accelerator Tuning Andrei Shishlo, Alexander Aleksandrov.
ATF2 Commissioning Toshiyuki Okugi 2008 / 7 /9 ATF2 beam commissioning meeting, KEK.
Overview of Booster PIP II upgrades and plans C.Y. Tan for Proton Source group PIP II Collaboration Meeting 03 June 2014.
Managed by UT-Battelle for the Department of Energy SNS Injection and Extraction Systems Issues and Solutions by M. Plum for the SNS team and our BNL collaborators.
AP2 Line & Debuncher Studies Status Keith Gollwitzer Antiproton Source January 9, 2006 Many people involved with providing the hardware and software that.
Radioactive Ion Beams CW 0.5 MW (for protons) 1 GeV (for protons) p to U Chiara, Manuel, Adam, HuiMay 2011, CAS, Bilbao.
RHIC Run11 Summary May 6, 2011 RSC Meeting Haixin Huang Luminosity Availability Polarization RHIC setup issues.
ICFA-HB 2004 Commissioning Experience for the SNS Linac A. Aleksandrov, S. Assadi, I. Campisi, P. Chu, S. Cousineau, V. Danilov, G. Dodson, J. Galambos,
Project X RD&D Plan Beam Transfer Line and Recycler Injection David Johnson AAC Meeting February 3, 2009.
1 Question to the 50GeV group 3GeV からの 54π と 81π 、 6.1π の関係 fast extraction 部の acceptance (81π?) Comments on neutrino beamline optics?
Recent Work Towards Increasing the AP2 & Debuncher Aperture – Keith Gollwitzer – May 9, Recent Work Towards Increasing the AP2 & Debuncher Aperture.
Accelerator Systems DivisionOak Ridge National Laboratory March 10-12, 2003 ORBIT SIMULATIONS AND RESULTS Jeff Holmes Accelerator Physicist September 30,
Booster Losses Keith Gollwitzer PIP and MI 700 kW review January 2015.
Y. R. Roblin Hall A beamline and accelerator status.
Dave Johnson July 12, 2010 NOvA/ANU Recycler Upgrades Review Optics, Apertures, and Operations Nova-doc 4930.
Commissioning of REX Jose Alberto Rodriguez, BE-OP-PSB (167538) on behalf of the ISOLDE operations team.
Task Lists of ATF2 commissioning Toshiyuki Okugi ATF2 Project Meeting 12 / 17 / 2008.
K.Hanke / TDR Meeting / 13 June 2006 Linac 4 Diagnostics L4: K. Hanke, M.Pasini (requirements, specifications, integration) AB/BI: U.Raich et al. (technical.
Proton Plan PMG 2/22/07 E Prebys 1 Proton Plan Status January Eric Prebys.
The Introduction to CSNS Accelerators Oct. 5, 2010 Sheng Wang AP group, Accelerator Centre,IHEP, CAS.
Proton Planning Eric Prebys FNAL Accelerator Division.
Dave Johnson July 12, 2010 NOvA/ANU Recycler Upgrades Review Optics, Apertures, and Operations Nova-doc 4930.
PSB H- injection concept J.Borburgh, C.Bracco, C.Carli, B.Goddard, M.Hourican, B.Mikulec, W.Weterings,
The SNS Power Upgrade Project Building on the Success of the SNS Accelerator Deployment Kevin Jones Research Accelerator Division Director.
August 12, Machine Status: 2013  Proton Source Commissioning and Studies RFQ Injector Line (RIL) Linac : Roof hatch installed Booster : Magnet.
SNS Beam Diagnostics A. Aleksandrov Spallation Neutron Source, Oak Ridge, USA.
Beam losses and collimation at the Oak Ridge Spallation Neutron Source by Mike Plum Beam losses and collimators in transfer lines workshop Lund May 13-14,
ORNL is managed by UT-Battelle for the US Department of Energy SNS beam loss and control By M. Plum ICFA mini-workshop on beam commissioning for high intensity.
SNS linac beam commissioning By Michael Plum Spallation Neutron Source Oak Ridge National Laboratory ESS Workshop on beam commissioning April 8-9, 2014.
HEBT Design Considerations Jingyu Tang, Xiangqi Wang, Hao Hao, Jiajia Tian IHEP, USTC International Review Meeting on Accelerator Physics Design of C-ADS,
Managed by UT-Battelle for the Department of Energy Experience on SNS Beam Instrumentation Collaborations Willem Blokland Beam Instrumentation Group Spallation.
HB2008 – WG F: 27 Aug. S. Childress – Diagnostics_2MW 1 NuMI Beam Diagnostics and Control Steps to 2 MW S. Childress Fermilab.
M. Munoz April 2, 2014 Beam Commissioning at ESS.
J-Parc Neutrino Facility Primary Proton Beam Design A. K. Ichikawa(KEK), Y.Iwamoto(KEK) and K.Tanabe(Tokyo) et.al. 7 th Nov. 2003,
The Preparation for CSNS Accelerator Commissioning Sheng Wang June 8, 2015, Dongguan.
ELENA installation progress F. Butin / ELENA collaboration.
ESLS Workshop Nov 2015 MAX IV 3 GeV Ring Commissioning Pedro F. Tavares & Åke Andersson, on behalf of the whole MAX IV team.
Managed by UT-Battelle for the Department of Energy SNS Ring TiN Coating Experience CERN Anti E-Cloud Coating Workshop Oct 12-13, 2009 by M. Plum, Ring.
Report Technical Director Storage-Ring-Installation Completed
Status of HESR 18th March Gießen Dieter Prasuhn.
A.Lachaize CNRS/IN2P3 IPN Orsay
High Intensity Challenges
ELENA Overview and Layout Start of ELENA Commissioning Next Steps
CNGS Proton beam line: news since NBI2002 OUTLINE 1. Overview
Linac/BC1 Commissioning P
SNS Commissioning Mike Plum
Presentation transcript:

ORNL is managed by UT-Battelle for the US Department of Energy Commissioning experience of SNS Ring By M. Plum ICFA mini-workshop on beam commissioning for high intensity accelerators, Dongguan June 8-10, 2015

2 CSNS Comm Wkshp June 2015 Accumulator Ring and Transport Lines Circumference248 m Energy1 GeV f rev 1 MHz Q x, Q y 6.23, 6.20 Accum turns1060 Final Intensity1.5x10 14 Peak Current52 A Rep rate 60 Hz HEBT RTBT Injection Collimation RF Extraction Target Linac dump (7.5 kW) Injection dump (150 kW) Extraction dump (7.5 kW) HEBT Ring

3 CSNS Comm Wkshp June 2015 The shrinking commissioning time Early in the project, before the inevitable schedule delays, there was plenty of time reserved for commissioning July 2002: –98 days for HEBT, Ring, RTBT –22 days for RTBT to TARGET November 2005: –34 days for HEBT, Ring, and RTBT –20 days for RTBT to TARGET Actual (Jan – May 2006) –32 days for HEBT, Ring, and RTBT –27 days for RTBT to TARGET

4 CSNS Comm Wkshp June 2015 Commissioning Timeline DTL Tanks 1-3 Front-End DTL Tank 1 DTL/CCL SCL Ring Target

5 CSNS Comm Wkshp June Ring/RTBT/Target Commissioning Timeline 2006: Jan. 12:Received approval for beam to Extraction Dump Jan. 13:First beam to Injection Dump Jan. 14:First beam circulating in ring Jan. 15:Beam circulating in ring for >1000 turns Jan. 16:First beam to Extraction Dump Jan. 26:Reached 1.26x10 13 ppp to Extraction Dump Feb. 13:End of Ring commissioning run April 3-7: Readiness Review for RTBT/Target April 27: Received approval for Beam on Target April 28: First beam on target and CD4 beam demonstration Nov 17: 23.5 kW at 5 Hz to target 2007: Mar. 28:90 kW at 15 Hz Apr. 12: First time 30 Hz beam to target Aug. 28: First time 60 Hz beam to target 13 days to reach initial commissioning goals

6 CSNS Comm Wkshp June MW Beam Power at SNS  First neutron production at 1.4 MW: June 29, 2014  Almost 8 years after start of low power operations 1.4 MW, Sept day operation, June MW Power savings Target issues 1.0 MW 1 MW, Sept. 2009

7 CSNS Comm Wkshp June 2015 Low power commissioning issues Ring injection chicane did not function as designed High beam loss in injection dump beam line Tilted beam on target

8 CSNS Comm Wkshp June 2015 Issue: Ring injection chicane In 2000 a design change was made in the injection chicane magnet bend angles that was not fully accounted for in the ring injection orbit or in the injection dump beam line optics –One consequence is a large closed orbit distortion, corrected by optimizing the chicane magnet set points and operating nearby dipole corrector magnets near their maximum values –Another consequence is that we did not have good transmission of the H 0 and H − waste beams. This led to several modifications of the injection dump beam line.

9 CSNS Comm Wkshp June 2015 Inj. dump beam line modifications to date Oversize primary stripper foil Thinner, wider secondary stripper foil Increase septum magnet gap by 2 cm New C-magnet New WS, BPM, NCD (high sens. BCM) Shift 8 cm beam left Electron catcher IR video (now removed) Aperture increase, added BPM Ring Injection dump

10 CSNS Comm Wkshp June 2015 Tilted beam on target Tilted beam on the target view screen horizontal vertical RTBT20 wire scanner for 3 different horizontal injection kicker amplitudes (S. Cousineau) Problem traced to large skew quad component in Lambertson extraction septum magnet. Solution was to replace pole tip shims.

11 CSNS Comm Wkshp June 2015 High power commissioning issues Stripper foil failures, two occasions Momentum dump Target failures

12 CSNS Comm Wkshp June 2015 Stripper foil issues at med. & high power Used for 1.1 to 1.4 MW for 3 months 2009 foil bracket failures at ~850 kW. Cured with new foil bracket design, change of material Al to Ti foil bracket issue at >1.2 MW. Final solution in progress. Arcing damage Foil was here before it fell off Bracket softening and distortion due to reflected convoy electrons

13 CSNS Comm Wkshp June 2015 Momentum dump failure Purpose of momentum scraper / dump is to scrape off high & low momentum tails of beam. Located about halfway along HEBT arc. Momentum dump failed April 2008 due to a combination of too much beam power (8-10 kW vs. 2 kW rated power) and inability of system to vent gas created by radiolysis (beam passing through cooling water) Dump replaced with 5 kW rated air-cooled design

14 CSNS Comm Wkshp June 2015 Most important beam instrumentation Most important / minimum set –BPMs needed to steer the beam, fine-tune the achromat –Current monitors to measure beam transmission in transport lines, to measure beam accumulation in ring –View screen at ring injection to check beam steering and focus –BLMs for beam loss control, check on beam transmission –Target imaging system (first temporary view screen mounted to target nose, then permanent coating system developed) Second most important –Wire scanners to check transport line optics

15 CSNS Comm Wkshp June 2015 Most important applications Orbit correction app – automates steering in transport lines, only way to correct ring closed orbit Ring BPM app – measure ring first turn, turn-by-turn, closed orbit (average of ~30 turns), ring tune Ring injection app – measure and control injected beam position and angle w.r.t. closed orbit, at foil Energy Manager app – to set magnets to design values for a given beam energy SCORE – Save COmpare REstore – saves and restores equipment set points RTBT Wizard – calculates beam size, position, and density on target based on upstream diagnostics Loss monitor app to display BLMs

16 CSNS Comm Wkshp June 2015 Lessons learned The pace of the commissioning is determined by equipment issues. If all the equipment worked as designed from day one it would only take a few days to commission. Need to closely involve hardware experts, thoroughly test hardware as much as practically possible before commissioning Need to prioritize equipment readiness in event of limited resources (e.g. don’t need multipole corrector magnets for initial commissioning) Low power commissioning is relatively easy. High power operations brings unexpected surprises.

17 CSNS Comm Wkshp June 2015 What worked well for us Thorough magnet measurement program allowed “dialing- in” magnet currents and immediately transporting beam – first shot through HEBT hit view screen in ring injection section Physics apps were integrated with the on-line model and the control system, and well developed before start of commissioning Physics apps written by commissioning team members. Allows rapid troubleshooting and development. Commissioning the machine in 7 stages Good set of beam instrumentation (lots of beam position, beam profile, and beam loss monitors)

18 CSNS Comm Wkshp June 2015 Summary The first part of SNS Ring commissioning was faster than expected – 3 days to get beam from exit of linac to ring extraction dump The ramp to high power, reliable operations took longer than expected – 8 years to 1.4 MW demonstration, and we still have more work to deliver 1.4 MW routinely The pace of commissioning and beam power ramp was determined by the hardware (RF modulators, target, RFQ, ion source) Accelerator physics worked 24/7, with support from technical experts as needed. Sometimes this was not very efficient because equipment limited the rate of progress.

19 CSNS Comm Wkshp June 2015 Thank you for your attention!

20 CSNS Comm Wkshp June 2015 Back up slides

21 CSNS Comm Wkshp June 2015 Tilted beam caused by skew quad component in extraction septum magnet Tilted beam on the target view screen horizontal vertical RTBT20 wire scanner for 3 different horizontal injection kicker amplitudes Beam distribution at BPM25 in the extraction line, reconstructed using single minipulse injection and varying extraction time (S. Cousineau & T. Pelaia) (S. Cousineau) X (mm) Y (mm)

22 CSNS Comm Wkshp June 2015 Harmonics calculation Integrated skew quad component 0.26 – 0.28 T at 1 GeV beam energy ~75% due end effects ~5% due to proximity of quad

23 CSNS Comm Wkshp June 2015 Extraction septum shim replacement OLD NEW

24 CSNS Comm Wkshp June 2015 Stripper foil system failure at ~840 kW (Failed May 3, 2009) Material deposition (Failed June 15, 2009) (Failed May 3, 2009) (Failed June 12)