October 15, 2012 PV & Storage Workshop ERCOT’s Interconnection Process John Adams Principal Engineer.

Slides:



Advertisements
Similar presentations
NREL Wind Integration Workshop By Electric Power Systems, Inc. June 28-29, 2010.
Advertisements

Distributed Generation (DG)
Public Service Company of New Mexico
NREL Wind Integration Workshop By Electric Power Systems, Inc. June 28-29, 2010.
Challenge of Large Scale Wind Power Integration - Introduction to the Workshop Pradeep Perera Principal Energy Specialist Asian Development Bank.
System Strength Discussion
Available Transfer Capability Determination Chen-Ching Liu and Guang Li University of Washington Third NSF Workshop on US-Africa Research and Education.
1 New Resource Qualification Testing Sandip Sharma Supervisor, Operations Analysis New Generation Information Forum ERCOT Public November 4, 2014.
Generation Interconnection Overview
A Partial Interim Report To WMS Guidance on Implementing Protocol Implementation Plan (PIP) 102 Reactive Power Task Force.
Topics to Cover Interconnection Process Overview
PLWG Report to ROS July 9, PGRRs needing vote PGRR043 – FIS Scoping Amendment – PGRR043 moves the Subsynchronous Resonance (SSR) Study out of the.
Determine Facility Ratings, SOLs and Transfer Capabilities Paul Johnson Chair of the Determine Facility Ratings Standard Drafting Team An Overview of the.
ERCOT John Adams September 14, 2012 Planning Guide concepts for dealing with Sub Synchronous Resonance in ERCOT & other issues.
ERCOT SOL Methodology for the Planning and Operations Horizons Stephen Solis 2014 OTS 1.
Houston Area Dynamic Reactive Project March 11,
Applying the Distribution System in Grid Restoration/NERC CIP-014 Risk Assessment Srijib Mukherjee, Ph.D., P.E. UC Synergetic.
Sai Moorty ERCOT Integration Options into ERCOT systems.
E x R E x R 1:a E x R/a 2. E j 2.0 j j 0.05 Generator terminal voltage maintained at pu j 0.08 V/a Load voltage (V) maintained at
RTWG Report to TAC August 5, 2010 Howard Daniels.
Black Sea Regional Transmission Planning Project By Predrag Mikša EKC - Electricity Coordinating Center Istanbul, March 2011.
RPG Meeting Five Year Plan Extension Brad Schwarz.
Engineering a sustainable future 1 ERCOT Voltage Ride-Through Study Workshop June 26 th, 2009.
1 TRANSMISSION SYSTEM OVERVIEW NETWORK OPERATING COMMITTEE April 17, 2007 New Mexico Transmission System Overview.
September 25, 2012 Planning Working Group - PLWG Sub-Synchronous Resonance Protection & Mitigation John Adams Principal Engineer.
PRR835 – Reactive Power Capability Requirement
August 17, 2012 Solar PV Inverters Anuj Dixit Planning Engineer Resource Integration RPG Meeting.
1 Compliance Update May Control Performance Highlights  NERC CPS1 Performance Performance further declined in March  March performance comparison.
VRT Study Update José Conto ERCOT System Planning.
August 30, 2012 Modeling Solar, Storage and Inverter based resources John Adams Resource Integration Planning Working Group.
WGR Ramp Rate in Nodal: “As High as Possible” Mike Grimes for QMWG Meeting 10 August 2009.
Resource Asset Registration Form Version 5.1 Update July 12, 2012.
DS2 – Grid Integration Dynamic Modelling of Wind Generation in Ireland
Managing a Power System with 40% Wind Dr Alan Rogers EirGrid.
ERCOT Wind Survey Leo Villanueva. Abilene Mc Camey Big Spring.
DREAM November Meeting. Agenda Introduction and Expectations Path to becoming a Resource Node – ERCOT Registration process for non-modeled resources –
October 15, 2012 PV & Storage Workshop PV and Storage Integration strawman proposals & discussion John Adams Principal Engineer.
1 Submitting a RARF Art Deller, P.E. Supervisor, Model Administration New Generation Workshop November 4, 2014.
May 11, 2012 RPG meeting YTP Scope and Process – RPG Comments.
ERCOT TAC11/2/ CREZ Study Update ERCOT TAC 11/2/2006.
Delivering for 2020 TSO Facilitation of Renewables Studies EirGrid Customer Conference Jonathan O’Sullivan October 2009.
TRANSMISSION CONSTRAINTS KENNETH A. DONOHOO, P.E. Manager of System Planning, Technical Operations
BAL-001-TRE-01 ERCOT CPS2 R2 Waiver Regional Variance April 16, 2009 Sydney Niemeyer.
Current Operational Challenges Computing the West – North Limits Potential IROLs Local Voltage & Thermal issue (OOME) High Voltage Outages.
Improving Primary Frequency Response Bob Green PDCWG August 3, 2011.
ROS July 10, 2008 Meeting WOTF Update on ROS Action Plan Summary: EECP Step #2 (Feb.26 th, 2008) Mark Garrott WOTF Chair.
Nodal Planning Model Process and Data Set A case use June 28, 2010 Planning Working Group.
ERCOT PUBLIC November RPG Meeting RTP – Study Scope November 20, 2015.
Panhandle Renewable Energy Zone (PREZ) Study
Estimating Available Capacity for New Generators Jonathan Rose Planning Engineer, Resource Integration Dept. Regional Planning Group September 24, 2013.
Oncor Transmission Service Provider Kenneth A. Donohoo Director – System Planning, Distribution and Transmission Oncor Electric Delivery Co LLC
Capacity, Demand and Reserves Report Bill Bojorquez May 4, 2007.
Capacity, Demand and Reserves Report Bill Bojorquez Board of Directors Meeting May 16, 2007.
ERCOT Transmission Planning Process Overview and Recommendations November 6, 2002.
Current Nodal OS Design 1.The NMMS database will have an OWNER and an OPERATOR designation for each piece of equipment in the model. The OWNER and OPERATOR.
Generation Adequacy Task Force Meeting April 10, 2014.
Voltage Control Brad Calhoun Consultant, Sr. Trainer Spring 2016.
1 EEA Workshop 3 April 2, /3/2015For the purpose of discussion only.
Congestion Management Work Group 2008 Overview CMWG Marguerite Wagner, Reliant Energy Inc.
Impact of not including proposed generators lacking RARF data in the planning models Planning Guide Section 6.9 Issues February 17, 2016.
Abilene Mc Camey Big Spring. Far West Abilene Area All the values are based on returned ERCOT survey results Total number of Wind Powered Generation.
Renewable Technology Working Group (RTWG) Report to TAC February 4, 2010 Henry Durrwachter.
February 17, 2012 Regional Planning Group CREZ Shunt Switching John Adams Principal Engineer.
Reliability Must Run Workshop RMR Study Process May 24, 2016.
Minnesota Renewable Energy Integration and Transmission
Freeport Area Master Plan Project -
PLWG Review 6.9 and the Interconnection process
ERCOT – Southern Cross Transmission ROS/WMS Working Group Assignments
Study Scope - Quarterly Stability Assessment
Compliance Report to ERCOT TAC February 2007
Presentation transcript:

October 15, 2012 PV & Storage Workshop ERCOT’s Interconnection Process John Adams Principal Engineer

2 Entities involved in the Generation Interconnection Process in ERCOT

3 For the ERCOT its ) Screening Study 2) Full Interconnection Studies 3) Interconnection agreement 4) Review design for protocol compliance November 14, 2011

4 Screening Study November 14, 2011

5 Full Interconnection Studies November 14, 2011

6 Interconnection Agreement signed November 14, 2011

7 Review Design for Protocol Compliance November 14, 2011

8 What is currently checked in 16.5 review Confirm design will produce ±0.95 Power factor reactive at all MW levels between LSL and HSL Protocol section Power System Stabilizer or equivalent is included in the design: Protocol section [4] Unit will provide frequency response: Protocol and Unit will dynamically provide voltage regulation: Protocol section 3.15 Breaker interruption capability is suitable to fault duty Transient voltage ride through per Protocols and operating guides: Operating Guide section 2.9 AVR is included in the design, and it can be operated in voltage control mode. Protocol section ( & 3.15 [5]) Unit can respond to changes in the voltage profile. Protocol 3.15 Reactive capability is based upon the ability to deliver to the HIGH side of the step-up transformer. Protocol section (3.15 [3]) Unit is able to receive control signals from its QSE in an upward and downward direction. (Normally referred to as AGC; Protocol section and (7-8)) Meeting Title (optional)Date

9 Timeline summary Time in Days As per ERCOT Planning Guide Section 5

10 Generation Interconnection Process in ERCOT Perform the Screening study (Steady State): Discuss possible Points of Interconnections with the Developer Model the system in PSSE using the latest Steady State Working Group Case TARA Contingency Analysis Complete the study in 90 days

11 Screening Study Approach First Contingency Incremental Transfer Capability (FCITC) approach, unit under study ramped up from % and constraint and associated violation listed Contingency analysis for thermal violations with nearby Natural Gas units ramped up (Base Case) Two standard dispatches executed, summer peak and low load with wind adjusted up on nearby generators Include all generation with signed Interconnection Agreements in the vicinity LoadWest WindCoast WindNearby Conventional Nearby Wind Sum Peak MaxSSWG* 100% 95% for Coastal 80% for West Low Load Min70%90%100%95% for Coastal 80% for West

12 Scheduling the Full Interconnection Study 180 days to evaluate completed Screening Study Results Notify all the Transmission Service Providers (TSP) (Transmission Owners Gen Interconnection List) of the project under study Include lead TSP and Developer to discuss the study results and chalk out the data requirements, timelines, protocols Draft a scope of the Steady State, Dynamic,Short Circuit and Facility studies to be performed

13 Full Interconnection Study (FIS) and timelines Approximately 300 days for the TSP to complete the FIS ERCOT provides comments and reviews to the completed studies (10 day review period) 180 days allowed for the Resource Entity (Developer) to sign a Interconnection Agreement after the completion of the comments period 60 days for ERCOT to perform compliance checks once the IA is signed (NPRR 408) Compliance tests to be performed by the unit before synchronization and energization (7 days)