EU Phase 2 Delivery & UK Link Programme; Impacts on Gemini Process European Workgroup 1 st May 2014.

Slides:



Advertisements
Similar presentations
15 November th SG meeting Enagás and REN Coordinated implementation of the Network Code on Capacity Allocation Mechanisms.
Advertisements

EU Developments Transmission Workgroup 3rd November 2011.
EU Implementation Programme Action TR1003: All to consider how to address EU developments going forward and send any identified issues to:
PN UNC Workgroup (Settlement topic) Allocations Overview 4 th December 2012.
15 November th SG meeting Enagás and TIGF Coordinated implementation of the Network Code on Capacity Allocation Mechanisms.
Gas Consumer Forum Project Nexus xoserve update 27th July 2009
Senior Stakeholder Forum 04/02/2014. Agenda UK-Link Programme Update –Including Data Cleansing Update Nexus Modification Update Faster Switching EU Reform.
Place your chosen image here. The four corners must just cover the arrow tips. For covers, the three pictures should be the same size and in a straight.
European Developments: Capacity Transmission Workgroup 6th October 2011.
Long Term Entry Capacity & User Commitment Transmission Workstream 7 th August 2008.
Project Nexus Workgroup 9 th September Background During detailed design a number of areas have been identified that require clarification with.
Project Nexus Workgroup Unique Sites 4 th November 2014.
CSEP Transportation Charges 11 th August Background Action NEX0604 from 18 th June PN UNC requested Xoserve to provide a presentation on how Supply.
How the Implementation of the Network Code Does Help Infrastructure Users Vasile FLOREA Director of Commercial Balancing SNTGN TRANSGAZ SA Medias.
Senior Stakeholder Forum Wednesday 19 th June 2013.
CMS Transition Overview 22 nd July Key Attributes CMS Consequential Change Project is scoping high level change requirements as a result of Project.
Proposer: Matthew Hatch Panel Date: 15 th May : EU Capacity Regulations – Capacity Allocation Mechanisms with Congestion Management Procedures.
Place your chosen image here. The four corners must just cover the arrow tips. For covers, the three pictures should be the same size and in a straight.
GEMINI incident contingency arrangements. Contents  Timeline of events  Shipper agent role  Logistical issues  Capacity auctions  Communications.
Capacity Release Processes and Investment Planning Transmission Planning Code Workshop 2 1 st May 2008.
EU Gas Balancing Code – Nomination Update [Revised to reflect action TX1002] Action TX1002: EU Balancing Code/Nominations: Provide an overview of what.
IGT Single Service Provision Requirements Update – 27 th March 2013.
UK Link Programme Dashboard Report Change Overview Board: 13/05/2014 Critical HLD activities complete enabling entry into Detailed Design Detailed Design.
UK Link Programme Update to PNUNC June 17 th 2013.
Overview Gemini 2008 Release (Summer). Gemini Release 2008 (Summer) In response to a request from National Grid Transmission a number of changes have.
UKL13950 UK Link Committee 14 th February 2008 COR880 Gemini 2008 Release (Summer)
Performance Assurance 21 st May Value Chain. Value Chain Xoserve would like to propose an approach to further aid the development of the Performance Assurance.
Place your chosen image here. The four corners must just cover the arrow tips. For covers, the three pictures should be the same size and in a straight.
February 2008 Gemini Incident Overview. Agenda Focus this part of the presentation is on the system elements of last year’s Gemini incident :-  Briefly.
UK Link Programme Dashboard Report Change Overview Board – 14/04/2015 RAG status for the full programme scope is RED Xoserve have confirmed the need to.
PNISG Update June Xoserve’s UKLP Assessment Principles 1.Maintain current delivery plans where possible and appropriate e.g. don’t just push all.
1 v1 iGT CSEP Billing Solution ScottishPower Proposals April 08.
Joint ACER-ENTSOG update on implementation of the Balancing NC 26 th Madrid Forum 16 October 2014.
Gas balancing interactions: Proposal for case studies Cemil Altin (Ofgem)
Cutover & Implementation Aggregated Programme RAG
All Island Single Electricity Market IWFA Update Laura Brien
MIPI European Transparency Project (ETP) Transmission Workstream 7 th October 2010.
Place your chosen image here. The four corners must just cover the arrow tips. For covers, the three pictures should be the same size and in a straight.
European Developments Transmission Workgroup 1 st December 2011.
Industry Dialogue on xoserve Services 14 th September 2007.
PN UNC Workgroup Invoicing 10 th January Objectives of the Workgroups To determine business principles for future Invoicing processes –Consider/review.
COR2789 – Measures to Address Unregistered and Shipperless Sites Implementation of MOD424, MOD410a & G
European Developments Transmission Workgroup 3 rd May 2012.
EU Phase 3 Customer communications
Congestion Management
Enagás and REN Coordinated implementation of the Network Code on Capacity Allocation Mechanisms 15 November th SG meeting.
Enagás and TIGF Coordinated implementation of the Network Code on Capacity Allocation Mechanisms 15 November th SG meeting.
Review of Demand Estimation Times for Modification Proposal 461
UK Link Programme Update to PNUNC August 13th, 2013
MIPI Energy – Daily Reports
Regulators’ update on Congestion Management and Balancing
Introduction of Code Contingency Guidelines Document
Gemini Re-platforming Project; External User Participation July 2012
Proposer: National Grid NTS Panel Date: 17th April 2014
Cutover & Implementation Aggregated Programme RAG
DSC Change Committee Summary – 7th November
2019 Release Planning Options inc Modification 0621 / GB Charging Project DSC Change Management Committee update July 2018.
UKLP Programme Plan End Stage Assessments
UK Link Programme Engagement Forum
COR1360 NTS Exit Reform (Mod 0195AV) UK-Link Committee 11th June 2009
Ofgem Switching Programme: Central Switching Service consequential change update 9th May 2018.
Modification 501 slides for Workgroup
Introduction of Code Contingency Guidelines Document
Ofgem Switching Programme: Central Switching Service consequential update 16th May 2018.
Transmission Workstream - EU 3rd Package Update
EU Codes: Implementation Issues
GRP Progress & Plans The GRP project was established to deliver an updated design utilising fully supported hardware and software for Gemini. GRP is replacing.
COR3007: UNC MOD 450B – Monthly revision of erroneous SSP AQs outside the User AQ Review Period Implementation UK Link Committee – May 2014.
Modification 0621 / GB Charging Project DSC Change Management Committee update June 2018.
EU Update Transmission Workgroup 3rd October 2019.
Presentation transcript:

EU Phase 2 Delivery & UK Link Programme; Impacts on Gemini Process European Workgroup 1 st May 2014

The principal areas of change to Gemini resulting from EU Code Phase 2 and UK Link Programme (UKLP) are as follows: EU Code Phase 2 Delivers the rules and processes for offering and allocating cross-border capacity at interconnector points. A joint booking platform (PRISMA) will be used to implement the rules meaning that Gemini will be integrated with PRISMA to manage the end-to-end commercial capacity processes at EU Interconnection Points (IPs) Delivers a new nominations matching process at IPs with new interfaces with adjacent TSO systems Implements changes to the UK market ‘Gas Day’ from – GMT to to UTC UK Link Programme Changes are required to parts of the Gemini System in order to deliver key Project Nexus requirements for the UKLP: Change NDM Demand Estimation to be a stand-alone calculation using actual weather data Introduce a new balancing figure in daily gas allocations; “Unidentified Gas” and share out across Gas Shippers in line with agreed industry rules Make necessary changes to screens and interfaces to make Unidentified Gas visible to Shippers and pass through to Gemini and UK Link billing processes Make necessary changes to both Nominations and Allocations Background

3 Programme Indicative Timeline - Overview Q1Q2Q3Q4Q1Q2Q3Q4Q1Q2Q3Q4Q1Q2 Build & Dev Test Logical Analysis System & User Test Data Cleansing Detailed Design HLD Stakeholder Engagement Cutover and go-live DBI Sourcing / Client Advisor Today Transition Arrangements

The indicative timelines of the Projects are shown below: Indicative Timelines

Indicative View of Areas of Impact EU Code Phase 2 Analysis on the EU Changes is just over half way through, initial indications are that External Users of Gemini will see change in the following areas: Bids for long term and short term auctions at interconnector points will be placed on PRISMA New screens will be required to support the nominations process at interconnector points New reporting screens and *APIs for Entry and Exit Entitlements at interconnector points and nominations Joint nomination procedure with Adjacent Transmission System Operators for TSO matching process Invoice file format changes due to the introduction of new charge types Once Design is complete the names of the screens, API’s and file format changes can be confirmed. Xoserve intend to share these at the July 2014 EU Transmission Work Group. * API means Application Programming Interface and is an automated mechanism for the shipper application to request and update data.

Indicative View of Areas of Impact UK Link Programme Initial analysis of Project Nexus requirements suggests that External Users of Gemini will see changes to: The existing ‘Maintain BA Total Energy Forecast’ screen that relates to the Demand Attribution and Nominations process The existing ‘LDZ WCF/SF’ screen that relates to the Allocations process A new screen for ‘Unidentified Gas by Shipper/LDZ’ relating to Allocations, Demand Attribution and Nominations processes An existing Energy Balancing API and the introduction of a new Energy Balancing API. Once Design is complete the number of changes and their names will be confirmed. Xoserve intend to share these at the August 2014 EU Transmission Work Group.

Next Steps Xoserve will attend the EU Working Group in July and August to confirm the names of the impacted screens, API’s and file formats. Further system updates will be given periodically to report progress and explain forthcoming key activities.