DTU 2013-09-30 A VISION OF SUPPORTING NEUTRON CHOPPER ESS PT 1 - BUNKER SYSTEMS Discussion Document.

Slides:



Advertisements
Similar presentations
Euratom Mechanical operation on the TPL sector E.Delmas – December 8th /13 Disassembly and reassembly of a sector of the Toroidal Pumped Limiter.
Advertisements

Gas Plant Operation and Maintenance Overview Presented by Geoff Vail.
Best Practices for Remote Assembly and Maintenance Keith Kershaw, Sources, Targets and Interactions Group Thanks to: Alessandro Tesini and Jim Palmer of.
FHM TRAINING TOOLS This training presentation is part of FHM’s commitment to creating and keeping safe workplaces. Be sure to check out all the training.
Be prepared before it happens!! Have procedures and policies in place before you have to respond to a retrieval. Training- Have personnel that are.
Contractor Safety Management
Muon g-2 Muon g-2 Experiment Quarterly Report Aria Soha All Experimenter’s Meeting March 2, 2015.
Instrument Space Requirements Rob Connatser Chief Instrument Project Engineer November 2014.
AMS-02 tracker mechanics status of assembly and integration Inner tracker integration completion: - Assembly and cabling - Temperature and magnetic field.
Interfaces with the SNS Project for the ARCS Instrument Doug Abernathy ARCS Hardware Project Manager ARCS Construction Project Review DOE Germantown Aug.
R. Rinaldesi, K. Kershaw – HE Group
Addendum to EDMS document “Instruction Manual for inserting the CMS ZDCs using the HXTC crane” In addition to the ZDC detectors in the TAN instrument.
GIF++ ACCESS SYSTEM Dorothea Pfeiffer GIF++ Project Meeting Thanks to: V. Martins De Sousa Dos Rios, D. Vaxelaire, D. Haasler.
1 Cryostat assembly, integration and commissioning procedures M.Olcese Version: 07 May 2008.
Lockout/Tagout for Affected Employees Understand the Basics.
Introduction and Charge to the Review of ESS Target building and Instrument Hall design requirements Roland Garoby November 2014, Lund
From Research Prototype to Production
NuMI NBI2006 September 9, 2006 NuMI Repairs for Hot Components Jim Hylen / FNAL Page 1 NuMI Repairs for Hot Components (1 sievert = 100 rem) Problem On.
PAUL SCHERRER INSTITUT CERN / Oct / P.A.Schmelzbach.
Highlights of RP activities in support of ISOLDE operation and projects Joachim Vollaire, Alexandre Dorsival and Christelle Saury with material from others.
1 BROOKHAVEN SCIENCE ASSOCIATES Redundancy Requirements for Critical Devices R. Casey August 8, 2007.
Conceptual Design Requirements for FIRE John A. Schmidt FIRE PVR March 31, 2004.
1 Target Station Design Dan Wilcox High Power Targets Group, Rutherford Appleton Laboratory EuroNu Annual Meeting 2012.
Review of the operation scenarios and required manning of the activities P. Schnizer and L. Serio.
1Page # Machine Assembly WBS 700 By: James H. Chrzanowski January 24, 2001.
Response to TAC8 and Annual Review Recommendations John Haines Head of Target Division April 2, 2014.
ISOLDE Activities for LS2 Richard Catherall EN-STI ISOLDE Technical Coordinator.
Progress on Remote Handling Systems TAC 12 Magnus Göhran – WPM 15 th October 2015.
CM27 – 8 th July 2010 LH2 System Progress and Future Plans M Hills T Bradshaw M Courthold I Mullacrane P Warburton.
Review of the operation scenarios and required manning of the activities P. Schnizer and L. Serio.
T2K Remote Handling T. Sekiguchi (KEK) on behalf of Tada (KEK) 2012/11/10.
ESS STRATEGY for supply of chopper systems to NSS project Science directorate Instrument technologies division Neutron chopper group leader --- DRAFT ----
Electrical Engineering for NSS - Status and Planning- Thomas Gahl Electrical Engineering Group Leader February 26, 2014.
Mu2e Mu2e Remote Handling Review Comparisons: Costs, Risks & Maintainability Ryan Schultz Deputy L3 Manager Target Station 3/3/2015.
LBNE Remote Handling Conceptual Design Issues for ORNL Collaboration Kick-off Meeting at ORNL 1/6/2010.
Personnel Safety Systems Stuart Birch Senior Engineer, Personnel Safety Systems November 6 th, 2014.
Rapid Change Technology The following is a presentation to aid Technicians in the replacement of the Rapid Change Technology Block.
Update on the ESS monolith design Rikard Linander Monolith and Handling Group ESS Target Division TAC 10, Lund, Nov 5,
SuperB Integration SuperB Experimental hall. Related topics of Slac D&D activities.
CONTROL OF HAZARDOUS ENERGY (LOCKOUT/TRYOUT). LOCKOUT/TRYOUT The OSHA Standard for the Control of Hazardous Energy (Lockout/Tryout) 29 CFR covers.
Task # 3 Task # kW Target Station Layout proposal Presented by L.Bruno CERN AB Experimental Areas, Targets and Secondary Beams Group.
LBNE Remote Handling Layout Options Adam Carroll Van Graves Tom Burgess FNAL/ORNL Videoconference March 11, 2010.
1 Interfaces, Engineering and Standards. 2 Interfaces LoKI Interface document description for deliverables Elements: PBS number, Deliverable description,
SAFE DIE HANDLING FOR STAMPING PRODUCTION OPERATIONS UAW-GM SAFE DIE HANDLING FOR STAMPING PRODUCTION OPERATIONS Copyright © UAW-GM Health & Safety.
SPHENIX Mechanical Don Lynch & Rich Ruggiero April 10, 2014.
SuperB Experimental hall General considerations on the Babar experimental area Preliminary space requirements hall proposal. A floor plan. Specification.
The ESS Target Station Eric Pitcher Head of Target Division February 19, 2016.
1 Target Station Design Dan Wilcox February 2012.
SAFE WORK INSTRUCTIONS
SAFE WORK INSTRUCTIONS
Fans & Heaters technical seminar
SAFE WORK INSTRUCTIONS
STO2 I&T at APL.
F&T Inc. OVERHEAD CRANE SAFETY.
Cryomodule Assembly Plan
Operations, Risks & Hazards
Location and Alignment devices
Remote Handling Workshop Introduction
Rad safety and activation
IKON 15 Talal Osman & Iain Sutton
Preliminary Hazard Analysis of Bunker
Bunker -Target interfaces
Bunker Wall Design Wall ESS
Technical Updates Gábor László NSS Lead Instrument Engineer
Bunker Project Operation aspects
Bunker Project Integration/Interfaces
Critical design review #1 for medium beta cavity cryomodules 3-4 APRIL SAFETY AND RAMI INPUTS - Franck Peauger OLIVIER KUSTER (INSTALLATION AND.
Test Beamline System Requirements and Charge to PDR Committee
CDS-EL IRR Closeout 28 March 2019 J.G. Weisend II, Chairman.
MRV system budget and scheduling Short overview installation
Presentation transcript:

DTU A VISION OF SUPPORTING NEUTRON CHOPPER ESS PT 1 - BUNKER SYSTEMS Discussion Document

DTU Chopper installation in the common shielding

DTU T - 48h: Anomaly detection Resources: Chopper Group Installed diagnostic systems detect that a chopper system is operating outside of normal parameters. The diagnostic data permit the evaluation of the progression of the anomaly and indicate that the system should be shut down within 24hs to avoid damage. Instrument responsible is notified – decision to intervene is taken jointly Intervention is signaled to Operations

DTU T -24H: Intervention planning Resources: Operations, Technical groups, Instrument. The operations & technical groups evaluate the scope of the intervention. –Crane –Group resources –Radiation team –Tooling –Duration The intervention is scheduled for a ‘beam off’ period with instrument and technical staff.

DTU T = 0h Chopper Shutdown Resources: Chopper group, Instrument resp, Operation group. A controlled shut down of installed chopper unit. Chopper group use data from diagnostics sensors to evaluate failure and repair strategy. When possible the chopper is parked ‘OPEN’ to permit continued operation of the instrument. INSTRUMENT 01 INSTRUMENT 03 INSTRUMENT 02 TARGET MONOLITH

DTU T = 0h Shutter closure Resources: Operations group, Instrument, H&S H&S authorizes the intervention. The Op’s group releases it’s resources preparation of the intervention –Crane –Heavy crew The beam line shutter upstream of components is closed to commence cool down period. The Shutter is ‘locked down’.

DTU T h Cool down Resources: Operations, Instrument, H&S, Technical Groups The activation of components obliges a delay before access is permitted (cool down period) All services in the area of the intervention are made safe. –Power –Fluids –Vacuum A site safety perimeter is established within which and shielding locks are removed. Use of remote handling equipment may permit a reduced cool down period.

DTU T h Shielding removal Required: Hall Crane(s) and or local cranes, Heavy Gang, HS&E The outer layers of shielding are removed (Not activated) The Inner layers of (activated) shielding are subject to cool down period. Removed shielding block moved to the temporary storage area. The chopper extraction tooling (pit lift) is brought to intervention site. SHEILDING BUNKER CRANE 20t HALL CRANE 30t HAND-OFF AREA

DTU T +30h: Equipment release Required: Local crane, Pit lift, Technical groups. Cranes are used to install the ‘Pit lift’ within the cavity. Local shielding for personnel is installed if required Cameras lowered into the pit Due to exposure to gamma radiation from activated components human access to the pit is not authorized. From the roof the shielding Equipment upstream and downstream (guides) are decoupled - remotely The fixations to base plates & supports are released - remotely.

DTU T +34h Extraction The motorised ‘Pit lift’ is used to perform the critical initial lift of equipment clear of neighbors (guides) The Pit lift raises equipment level with the top of the pit for disconnection of services ‘umbilical’ Pit lift raises equipment above the shielding permitting full access and is locked into position Additional local shielding may be installed if required. TRANSPORT CASK (?)

DTU T +36h Inspection The equipment is inspected to confirm the origin of anomalies and extent of work required. Equipment may be connected and test run ‘in local’ for diagnostics The repair / replacement strategy is confirmed and parts are brought to site.

DTU T +40h Hot Swap The Defective assemblies are decoupled (remotely) The defective assemblies(s) are removed using the local crane and casked if required. Activated components are removed to a ‘cool down’ pen. Additional normal maintenance operations may be conducted. Direct replacement assemblies are installed and coupled.

DTU T +48h Reconnection & Test The pit lift is unlocked The pit lift lowers equipment to an intermediate level for connection of services umbilical Connectivity tested Low speed equipment tests are conducted in local. Connectivity from remote is tested.

DTU T +50h: Run down - Lock down The Pit lift lowers equipment to near final position The lift cage engages with alignment pins for guidance on critical initial approach Cameras are used to oversee operations. The lift cage touches down on precision locating pins Equipment is Locked down

DTU T +52h Alignment & Test The alignment is checked from above. Realignment should not be required (but could be conducted remotely) Equipment pumped down and cooled/heated. Equipment is run to conduct functional & vibrational tests. Lock down is confirmed A 12hr equipment test cycle is started The Cameras and pit lift are removed.

DTU T +60h Shielding replacement Required: Hall Crane and local cranes Extraction tooling is removed from site. All shielding is brought to site by the hall crane. The Inner layers of activated shielding are reinstalled. The Outer layers of shielding are reinstalled.

DTU T +64h Chopper Tests At the end of the Test cycle Choppers are cleared for use and released to instrument control. MPS system is reactivated. Control of the chopper systems is transferred to remote.

DTU T +66h Evacuate Perimeter Required: Health physics, Technical teams The services on the instrument are reestablished. –Power –Fluids –Vacuum All locks are reinstalled. Beam line is declared secure for access. The safety perimeter is removed.

DTU T +72h Shutter release The Beam line shutter upstream of the components is opened for radiological tests. Neutrons are used to test and commission choppers. Radiation levels are controlled The beam line is declared radiologicaly safe for operation.

DTU CONCLUSIONS

DTU Important assumptions Hall crane 25t Bunker crane 10t Upstream shutters Remote tooling/shielding is available. Full spares are available on site. Sufficient NCG and Op’s staff for 24/7 call out. Choppers & bunker is designed for Serviceability Facility is in Steady state running Front end components will be Activated There is no or little exposure to activated shielding / neighbors No neighboring equipment requires removal.

DTU THE END