ATLAS Plenary, Feb. 18th, 05Commissioning1 Report on the commissioning activities G. Mornacchi, P. Perrodo and Sub-Systems Collaborators.

Slides:



Advertisements
Similar presentations
Preparation for ATLAS SCT/ID Endcap Completion at CERN Jo Pater Manchester, 4 January 2006.
Advertisements

André Augustinus 15 March 2003 DCS Workshop Safety Interlocks.
André Augustinus 16 June 2003 DCS Workshop Safety.
Peter Chochula, January 31, 2006  Motivation for this meeting: Get together experts from different fields See what do we know See what is missing See.
The LAr ROD Project and Online Activities Arno Straessner and Alain, Daniel, Annie, Manuel, Imma, Eric, Jean-Pierre,... Journée de réflexion du DPNC Centre.
Atlas SemiConductor Tracker Andrée Robichaud-Véronneau.
Uli Schäfer Discussions with H.B. after last meeting… All ATLAS standard racks and crates will be monitored. Helfrieds group will equip them with ELMBs.
19 March 2012Muon Week - Operations1 Muon Week Muon Operations Session Introduction Status and LHC Schedule Detector Readiness + Preparation for Physics.
1 Raw Event : ByteStream implementation Muon Workshop, April 2002 A. Nisati, for the Muon Trigger group.
From Olivier to commissioning team plans for the start-up of regular operations of LHCb 30/06 to 4/07 : Global commissioning week, all detectors, full.
June 2004 Andrea Gaddi, PH-CMI USC Installation Commissioning Task Force 1st Run Meeting, June 3rd, 2004.
CLAS12 CalCom Activity CLAS Collaboration Meeting, March 6 th 2014.
Summary DCS Workshop - L.Jirdén1 Summary of DCS Workshop 28/29 May 01 u Aim of workshop u Program u Summary of presentations u Conclusion.
06/03/06Calice TB preparation1 HCAL test beam monitoring - online plots & fast analysis - - what do we want to monitor - how do we want to store & communicate.
JCOP Workshop September 8th 1999 H.J.Burckhart 1 ATLAS DCS Organization of Detector and Controls Architecture Connection to DAQ Front-end System Practical.
M. Gilchriese ATLAS Upgrade Introduction January 2008.
V. Bobillier1 Long distance cable installation status Calorimeter commissioning meeting.
1 Control Room Model 4 Types of control rooms  Field Control Room (FCR): for example operating near the equipment in USA15. Expected to be needed throughout.
XXVI Workshop on Recent Developments in High Energy Physics and Cosmology Theodoros Argyropoulos NTUA DCS group Ancient Olympia 2008 ATLAS Cathode Strip.
André Augustinus 10 September 2001 DCS Architecture Issues Food for thoughts and discussion.
1 Responsibilities & Planning DCS WS L.Jirdén.
ATLAS Liquid Argon Calorimeter Monitoring & Data Quality Jessica Levêque Centre de Physique des Particules de Marseille ATLAS Liquid Argon Calorimeter.
CERN, Main challenges for the ATLAS upgrade project in the coming year.
108 Mar 2007L. Musa TPC Commissioning ALICE Technical Forum, CERN, 8 th March 2007 L. Musa Outline Pre-commissioning above ground (2006) Preparing for.
André Augustinus 21 June 2004 DCS Workshop Detector DCS overview Status and Progress.
ATLAS Muon System WBS 3.5 DoE/NSF M&O Evaluation Group Review BNL 19-Jan-06 Frank Taylor MIT V1.3.
Naming and Code Conventions for ALICE DCS (1st thoughts)
Roman Pot Engineering Design Review CERN, 14 February 2006 M.Oriunno, CERN PH-TOT Installation, Commissioning and Schedule.
Clara Gaspar, March 2005 LHCb Online & the Conditions DB.
M&O status and program for ATLAS LAr calorimeter R Stroynowski (on vacations)
Mobile DAQ Testbench ‘Mobi DAQ’ Paulo Vitor da Silva, Gerolf Schlager.
Technical Support Activities in PH-ADO-PO
G. Carboni – Muon Meeting – April 2002 Muon Meeting LHC schedule is now official (Council Committee) First protons (Pilot run) delayed to
Bruno Belbute, October 2006 Presentation Rehearsal for the Follow-up meeting of the Protocol between AdI and CERN.
CERN, O.Pinazza: ALICE TOF DCS1 ALICE TOF DCS Answers to DCS Commissioning and Installation related questions ALICE week at CERN O. Pinazza and.
Progress report Collaboration meeting 23-SEP-2009
Main priorities for the next years. Where do we stand Muon system in good shape (in my opinion) – Sub-systems hardware quite robust (see later for main.
TRT Offline Software DOE Visit, August 21 st 2008 Outline: oTRT Commissioning oTRT Offline Software Activities oTRT Alignment oTRT Efficiency and Noise.
U.S. ATLAS Executive Committee August 3, 2005 U.S. ATLAS TDAQ FY06 M&O Planning A.J. Lankford UC Irvine.
ATLAS and CERN/ST 2nd April 2003 Marzio Nessi. 02/04/2003 Today ATLAS project Detector Components Construction Detector Integration and Installation ATLAS.
All CMS 30 May07 TSV1 All CMS 3 30 May 2007 LHC machine CMS Progress Overall Schedule.
D0 Status: 04/01-04/08 u Week integrated luminosity –1.7pb -1 delivered –1.5pb -1 utilized (88%) –1.1pb -1 global runs u Data collection s global data.
2/4/2001Ludovico Pontecorvo INFN Roma1 Plans for the H8 system test: 2001/2002 Goals for the 2001/2002 Test beam Beam layout Chamber Supports 2001 Schedule.
G. Carboni - Muon Meeting – Muon Meeting 12/ Agenda IntroductionGiovanni (30’) GEM and TDR AddendumWalter (20’) Update on M1 ratesAlessia.
R. Boyd 1 February  Dr. M. Saleem  D. Jana  M. R. Meera Labbai  R. Boyd.
Tev4LHC Workshop 28 April th April Tev4LHC 28 th April 2005 ATLAS: detector status Test beams and Plans for Commissioning Detector status.
1 Calorimeters LED control LHCb CALO meeting Anatoli Konoplyannikov /ITEP/ Status of the calorimeters LV power supply and ECS control Status of.
Atlas Muon Spectrometer: installation and commissioning L. Pontecorvo INFN Roma.
Status of Muon Activities W.Baldini, N. Bondar, O.Maev, B. Schmidt LS1 Meeting Dec. 20-rd 2013.
14 November 08ELACCO meeting1 Alice Detector Control System EST Fellow : Lionel Wallet, CERN Supervisor : Andre Augustinus, CERN Marie Curie Early Stage.
RRB scrutiny Report: Muons. Internal scrutiny group for RRB report Internal scrutiny group composition – J. Shank, G. Mikenberg, F. Taylor, H. Kroha,
Clara Gaspar, April 2006 LHCb Experiment Control System Scope, Status & Worries.
AFP Trigger DAQ and DCS Krzysztof Korcyl Institute of Nuclear Physics - Cracow on behalf of TDAQ and DCS subsystems.
Nov. 2005Calorimeter Commissioning R. Teuscher 1 Calorimeter Commissioning in : Testbeam 2: Installation, Cosmic Ray Commissioning.
March 12 th 2013 Muon LS1 operation meeting1 Muon LS1 Status Outline Recap of last week P1 weekly schedule Muon related activities Open issues and discussions.
MUON Project Overview Action Items from September meeting New Action Items Update to the List of Worries Update of plans for the next 6 months.
GlueX Collaboration May05 C. Cuevas 1 Topics: Infrastructure Update New Developments EECAD & Modeling Tools Flash ADC VXS – Crates GlueX Electronics Workshop.
André Augustinus 18 March 2002 ALICE Detector Controls Requirements.
ATLAS The ConditionDB is accessed by the offline reconstruction framework (ATHENA). COOLCOnditions Objects for LHC The interface is provided by COOL (COnditions.
LHCb Week 27/11-01/ D.LACARRERE on behalf of Expt Area Team1 Experimental Area Latest News from IP8  Radiation Shield – Upper & Front Parts  Structures.
TDAQ and L1Calo and Chamonix (Personal Impressions) 3 Mar2010 Norman Gee.
V Thermo-siphon Workshop Test protocol Jan Godlewski PH/DT-PO On behalf of thermo-siphon working group
L1Calo DBs: Status and Plans ● Overview of L1Calo databases ● Present status ● Plans Murrough Landon 20 November 2006.
Online Database Work Overview Work needed for OKS database
The ATLAS Collaboration
Completion and Pre-Exploitation Costs for the Initial ATLAS Detector
ProtoDUNE SP DAQ assumptions, interfaces & constraints
Pierluigi Paolucci & Giovanni Polese
Racks PC Rack >> 24 mini and 12 tall PC racks Mini Racks
CSC Shift Training and Operation + B904 Status
Presentation transcript:

ATLAS Plenary, Feb. 18th, 05Commissioning1 Report on the commissioning activities G. Mornacchi, P. Perrodo and Sub-Systems Collaborators

ATLAS Plenary, Feb. 18th, 05 Commissioning 2 ATLAS components breakdown Inner Detector LARG TILES MUONS DCS

ATLAS Plenary, Feb. 18th, 05 Commissioning 3 View on the ATLAS work packages DAQ TILES LARG MUONS Cooling/ Ventilation WPs

ATLAS Plenary, Feb. 18th, 05 Commissioning 4 Concrete example: Tiles calorimeter WP1: Detector and Modules FE electronics at IP Cooling, Sniffers WP2: Cables WP4: FE Electronics on the truck WP7: BE electronics TTC DAQ DB FE-BE integration WP6: Cosmics L1 receivers Offline BE LV system WP9: HV system WP8: Cesium system WP9: Laser system WP11: TILES DCS Racks, DCS Interlocks Racks L1 receivers Laser calibration WP5: FE LVPS insertion WP3: Rack equipment Racks, DCS WP12: min Biais events Updated on 27/01/05 Active WPs

ATLAS Plenary, Feb. 18th, 05 Commissioning 5 Process Overview WP SIgn off WP Execution WP Elaboration Detail schedule and resources Well ahead of execution WP detailed System document Start end times Tests & expected results Work Package Break down System Analysis Break down in components Documents stored in EDMS Under ATC/commissioning/phase I/ Requirements WP Schedule -> ATLAS schedule WP excel sheet, PPSPS document (safety) Agree on WP outcome -> input to sign off Document results Preserve operational information We are ~ here

ATLAS Plenary, Feb. 18th, 05 Commissioning 6 Phase 1WP: next 3 months Sub-systemWPDescriptionStart date Inner DetectorCables PP3->US(A) PP2 in sector 13 ~ installation WP Pipework on cryostat ~ installation WP Lar calorimeterF/E on truck Install and commission F/E electronics with detector in “truck position” Active Racks USA15 lAr rack infrastructure in USA15 Tile calorimeterF/E on the truck Install and commission F/E electronics with detector in “truck position”. Temporary cables, mobydick, MobyDAQ March Racks USA15 Install and commission the infrastructure of the USA15 Tile racks March Cesium source Install and commission the Tile Cs source. Piping will be a subject for an intermediate sign off Active Muons systemSector Installation of MDT and RPC chambers. No real commissioning yet. Active Sector 13 Installation and commissioning of sector 13 muon chambers. Validates the full commissioning cycle. May Alignment system Install and commission alignment system. Several sub-steps, intermediate sign offs. WP document almost ready for work package analysis. March

ATLAS Plenary, Feb. 18th, 05 Commissioning 7 Phase 1WP: next 3 months Sub-systemWPDescriptionStart in DCSLocal DCS USA15 L1 Install and commission local DCS station in USA15. Includes first test with a sub-set of racks in the Tiles area. March DSS USA15 Level-1 Commission DSS system in USA15 level-1, stand alone mode. March DAQDAQ infrastructure Install and commission hardware (e.g. servers) and software (e.g. online s/w suite) infrastructure. March ROD Crate DAQ Commission RCD software. Multi-step process including one commissioning step per ROD type. Planning MagnetsMCS/MSS Install and commission Magnet Safety and control system. Multiple steps; first is related to equipment in USA15. March AllCables UX15---US(A)15 Test and commission cables upon installation. Involves all sub-systems. With cables

ATLAS Plenary, Feb. 18th, 05 Commissioning 8 Sign Off A number of infrastructure sub-systems have already been commissioned or are in the process of being so:  C&V  Cryogenics plant on surface  Cryogenics in USA15, Magnet equipment  Cranes For these we envisage a sign off procedure only  To collect the performance parameters  To understand open issues and problems  To integrate them in a uniform documentation scheme, easy to trace back

ATLAS Plenary, Feb. 18th, 05 Commissioning 9 Sign Off A formal procedure to make sure that:  Installation (if any) has been properly done: e.g. w.r.t. TC procedures (Install. DB, etc…)  Proper grounding & safety issues have been taken into account  Documentation is available: Technical and maintenance documentation for H/W and S/W User guides, operational procedures, including the test procedures  Planning for maintenance and responsibilities are defined  Performance is according to specifications Or we understand where, how, possibly why, there is a disagreement  We know what are the open problems and issues And what actions can be defined  It is clear who is authorized to use the system once commissioned: Sensitive items: ID cooling, LARG high voltage, TILES Cesium system,… The sign-off procedure may occur in several steps:  For a complex WP one may envisage intermediate milestones, hence sign offs  Associated to a repetitive aspect: E.g. ROD crates, FE electronics, muon chambers.

ATLAS Plenary, Feb. 18th, 05 Commissioning 10 Work packages tree: In the Work packages document: WP outcome: (Agreed before WP activation) Execution of the WP Follow-up during the Commissioning meetings Final sign-off procedure Installation report  Inventory, grounding, safety, … Performance specifications  Expected functionality  Quantitative performance figures Test report  Checklist of tests and results Operational documents  Indicates who is responsible, who to contact for problems  Maintenance procedures/plan  Pointers to relevant documentation Operational procedures Test procedures Component manuals  List of open issues/problems EDMS Archive documents Sign Off

ATLAS Plenary, Feb. 18th, 05 Commissioning 11 Weekly meetings at Point 1 Minutes can be found at:  Experimental Area Management (EAM):  Counting Rooms Management (CRM): ATC-C-IM-0001  Inner Detector: ATC-GE-MM-0132  Calorimeters: ATC-GE-MM-0125  Muons: ATC-GE-MM-0126 Make use of sub-system installation meetings to follow phase 1 sub-system specific commissioning  Phase 1 has too many WPs to concentrate their follow up in a single weekly meeting  Avoid proliferation of meetings  Assume that emphasis will shift from installation to commissioning Weekly meeting  The same morning as the follow-up of the management meetings for UX15 (EAM) & counting rooms (CRM)  Use for topical discussion, sign off, follow sub-systems w/o an installation meeting (e.g. DSS, DCS, DAQ, trigger)

ATLAS Plenary, Feb. 18th, 05 Commissioning 12 Monthly meetings Start discussion of phase 2 commissioning - > monthly meeting Overall status and issues to be escalated: TMB, EB

ATLAS Plenary, Feb. 18th, 05 Commissioning 13 Potential difficulties Elaborating the commissioning work to be done needs time and some distance with the daily work on site. Collaborators involved in commissioning in the sub- systems are too often overloaded by many other things (e.g. production/installation tasks). More effort needed to prepare the “functional work packages” following installation. The new installation planning is very tight (no float anymore). This can jeopardize the tests and the commissioning. Determine priorities in the tests. Test programs, software and analysis tools ready in advance is an important asset. Centralized management of the computers and network at point 1 is mandatory to avoid confusion. Need of a centralized support for the counting rooms.

ATLAS Plenary, Feb. 18th, 05 Commissioning 14 Phase II commissioning Define a reasonable “end of Phase I” for the sub-systems. We won’t go sequentially Phase 1-> Phase 2. System integration:  Partitioning the ATLAS detector: Trigger (CTP,LTP), DAQ (RCD), DCS, DB  Integration Sub-detectors + DAQ + DB + Offline data  Integration Sub-detectors + central DCS + DBs  Operations L1calo + LARG + TILES (Workshop Feb.. 1 st 2005, next in April) Functional tests:  Noise tests and Calibration Pulse tests on large scales involving sub-detectors and L1. Involves ROD crate DAQ.  Partial cosmic runs : Tiles + Muon Barrel sector 13 (+ alignment) + LARG (later). Involves ROD crate DAQ.  Toroid tests (after completion) + Sub-systems  Infrastructure (cooling, ventilation) + sub-systems (detectors, electronics, TDAQ, DCS)

ATLAS Plenary, Feb. 18th, 05 Commissioning 15 Phase II commissioning More local combinations:  LARG + cryogenics  Magnets + cryogenics  ID + gas system  Muons + gas system Work organization:  Many ideas are around and we already feel the pressure to take cosmics asap. Need a clear formulation (WP) to decide the priorities and build a planning.  Working groups being organized : “L1”, “DAQ” or “DCS” oriented Detector performances and physics coordinators: calibration data, cosmics Elaborate WPs. Monthly meetings to discuss and plan them. Role of commissioning coordination  Need a place to operate the detector being commissioned (proto Control Room). can be considered not as Phase II, but as A natural extension of Phase I

ATLAS Plenary, Feb. 18th, 05 Commissioning 16 Conclusion Continue to initiate the mechanics of WPs with the various ATLAS systems. Milestone of June, before the barrel calorimeters move to IP. The success of a well commissioned ATLAS system is the result of the sum of many detailed tasks.They have to be well thought and prepared to be meaningful for the future.This required more collaborators involved in these aspects. The acknowledgment of this work is of importance. Centralized management of the computers and network at point 1 will become soon mandatory to avoid confusion. Need of a centralized support for the counting rooms. Start thinking seriously soon to a proto control room.