MEG Review Meeting June 2006 1 Peter-Raymond Kettle Beam Line Line Status StatusBeam Line Line Status Status.

Slides:



Advertisements
Similar presentations
1 MICE Beamline: Plans for initial commissioning. Kevin Tilley, 16 th November. - 75days until commissioning Target, detectors, particle production Upstream.
Advertisements

Simona Bettoni and Remo Maccaferri, CERN Wiggler modeling Double-helix like option.
Field measurements of QEA magnets at KEK Mika Masuzawa May 30, 2006.
The Wave Nature of Light
Target Status Report Lara Howlett University of Sheffield.
P.-R. KettleMEG-Review February MEG Beam Line Studies  E5 Z-Branch NOW !!! NOW !!!
2/9/2004DC status - BVR1 1.Mechanics 2.Foil 3.Frame and Print Anode Inner cathode Hood 4.Pressure control + He bag + target 5.Electronic 6.Schedule Status.
P.-R. KettleMEG Review July MEG Beam Line Studies.
MICE Beam-line and Detectors Status Report 16 th October 2009 Chris Booth The University of Sheffield.
1 G4MICE studies of PID transverse acceptance MICE video conference Rikard Sandström.
Tagger and Vacuum Chamber Design. Outline. Design considerations. Stresses and deformations. Mechanical assembly.
MuCool RF Status MICE Collaboration Meeting June 7-10, 2006, Fermilab A. Moretti June 9, 2006.
Tagger and Vacuum Chamber Design. Outline. Design considerations. Stresses and deformations. Mechanical assembly.
D EDICATED S PECTROPHOTOMETER F OR L OCALIZED T RANSMITTANCE A ND R EFLECTANCE M EASUREMENTS Laetitia ABEL-TIBERINI, Frédéric LEMARQUIS, Michel LEQUIME.
Malte HildebrandtMEG Review Meeting, 14th February 2007 Report of Run Coordinator Run 2006 Summary Malte Hildebrandt MEG Review Meeting, 14th February.
HPS Test Run Setup Takashi Maruyama SLAC Heavy Photon Search Collaboration Meeting Thomas Jefferson National Accelerator Facility, May 26-27,
P.-R Kettle MEG Review July Beam Transport & Target Systems BTS Success Novosibirsk 24/5/ : A 300 A.
Medium heavy Λ hyper nuclear spectroscopic experiment by the (e,e’K + ) reaction Graduate school of science, Tohoku University Toshiyuki Gogami for HES-HKS.
David Urner, Oxford University, RHUL – June StaFF Stabilization of Final Focus Motion Stabilization with Nano-Meter Precision David Urner Paul Coe.
Peter-Raymond Kettle MEG Review February MEG Commissioning & Engineering Run 2007.
1 VI Single-wall Beam Pipe tests M.OlceseJ.Thadome (with the help of beam pipe group and Michel Bosteels’ cooling group) TMB July 18th 2002.
Preparation of wall position Alignment of A and C side in closed position Creation of reference system Translation of reference system to open position.
2 1/March/2015 日本物理学会大70回年次大会@早稲田大学 東大ICEPP 内山雄祐 他 MEG II collaboration.
MEG positron spectrometer Oleg Kiselev, PSI on behalf of MEG collaboration.
Timing Counter Report of Feb. 14 th, 2007 P.W. Cattaneo.
1 W.Ootani ICEPP, University of Tokyo MEG experiment review meeting Feb , PSI W.Ootani ICEPP, University of Tokyo MEG experiment review meeting.
MICE Beam-line and Detectors Status Report 16 th October 2009 Chris Booth The University of Sheffield.
M. apollonio MICE Beamline summary. - Beamline parallel session (June 1 st ): - envisaged goals (Alain) - assess readiness of the line magnet status (Ken)
1 Fulvio TESSAROTTO the new RICH beam pipe the new RICH beam pipe - pipe production, gluing and tests - measurement and removal of the old pipe - fixation.
Stabilization of Focus at ATF2 David Urner University of Oxford.
PSI July 2002MuEGamma Review Meeting1 Beam Line Status update 1.  E5 Test Beam Overview : Aims + RequirementsAims + Requirements Zone Layout + Measurement.
Plans (& ideas) for beamline commissioning The beamline Magnet field tests Source characterisation Optics (& model) commissioning K. Tilley CM18, 14/06/07.
Tokyo - Topical Meeting, March Peter-Raymond Kettle Beam Line Update End-Caps End-Caps Insertion System Insertion System Target System Target System.
COBRA Magnet Status W. Ootani June 27th, 2006 MEG Review W. Ootani June 27th, 2006 MEG Review.
S. Kahn 5 June 2003NuFact03 Tetra Cooling RingPage 1 Tetra Cooling Ring Steve Kahn For V. Balbekov, R. Fernow, S. Kahn, R. Raja, Z. Usubov.
Magnet Design & Construction for EMMA
Peter-Raymond Kettle Tokyo - Topical Meeting, March Beam Monitoring Basis for Discussion only Beam Rate Beam Rate Beam Profile Beam Profile Beam.
The Stripping Foil Test Stand in the Linac4 Transfer Line
Status of and Installation Plan for DC Gas Control System and Target Work Scheduling Meeting 4 August 2006 PSI W. Molzon, Feng Xiao.
Lecture 9: Inelastic Scattering and Excited States 2/10/2003 Inelastic scattering refers to the process in which energy is transferred to the target,
7 November 2003 Status of CNGS NBI presented by K. Elsener 1 Status of CNGS Konrad Elsener CERN – Accelerators+Beams Division.
Peter-Raymond Kettle MEG Review February BeamBeam LineLine StatusStatus.
UK Neutrino Factory Meeting Front End Test Stand (F.E.T.S.) Engineering Status by P. Savage 22nd April 2009.
Progress in the construction of the MICE cooling channel and first measurements Adam Dobbs, EPS-HEP, 23 rd July 2011.
P.-R. KettleMEG Review January MEG – Beam Line Studies Present Status & Overview since July 2002.
CLIC Stabilisation Day’08 18 th March 2008 Thomas Zickler AT/MCS/MNC/tz 1 CLIC Quadrupoles Th. Zickler CERN.
Luminosity Monitor Design MICE Collaboration Meeting 31 May 2009 Paul Soler.
T2K Status Report. The Accelerator Complex a Beamline Performance 3 First T2K run completed January to June x protons accumulated.
MEIC Detector and IR Integration Vasiliy Morozov, Charles Hyde, Pawel Nadel-Turonski MEIC Detector and IR Design Mini-Workshop, October 31, 2011.
P.-R. KettleMEG-Review July MEG Beam Line Studies  E5 Z-Branch Collaborative Effort !!! Effort !!!  E5 Z-Branch Collaborative Effort !!! Effort.
NUMI NUMI/MINOS Status J. Musser for the MINOS Collatoration 2002 FNAL Users Meeting.
Physics requirements  mapping spec’s Strategy: analyze measurements to get field Mapping plan: where/how to map Engineering design: sensor, fixtures,
Physics Requirements Sensitivity to Manufacturing Imperfections Strategy  where to map field  measure deviation from ideal model  fit to error tables.
Emulsion Test Beam first results Annarita Buonaura, Valeri Tioukov On behalf of Napoli emulsion group This activity was supported by AIDA2020.
Technical Design for the Mu3e Detector Dirk Wiedner on behalf of Mu3e February Dirk Wiedner PSI 2/15.
Status of physics analysis Fabrizio Cei On Behalf of the Physics Analysis Group PSI BVR presentation, February 9, /02/2015Fabrizio Cei1.
CERN –GSI/CEA MM preparation meeting, Magnetic Measurements WP.
DDBA magnets Chris Bailey Low emittance rings Sept Frascati.
Tagger and Vacuum Chamber Design Jim Kellie Glasgow University.
Tutorial On Fiducialization Of Accelerator Magnets And Undulators
Straw prototype test beam 2017: first glance at the data
J. Musser for the MINOS Collatoration 2002 FNAL Users Meeting
Review on collimator movement with stepping motors
Target and Horn status report
SBS Magnet, Optics, and Spin Transport
Gas Monitoring Chamber Production Status
Review on collimator movement with stepping motors
Station and Module Support Frames
Some of the Points Raised During my JLAB Visit
IR/MDI requirements for the EIC
Presentation transcript:

MEG Review Meeting June Peter-Raymond Kettle Beam Line Line Status StatusBeam Line Line Status Status

MEG Review Meeting June Peter-Raymond Kettle 1.Degrader Commissioning Run Commissioning Run Results Results 1.Degrader Commissioning Run Commissioning Run Results Results Topics to be Addressed 2. COBRA He-atmosphere He-atmosphere 3. COBRA/BTS Fringe Field Beam alignment influence influence 3. COBRA/BTS Fringe Field Beam alignment influence influence 5.  - Beam Test BTS 4. COBRA End-Cap & Insertion + Drive System Status 4. COBRA End-Cap & Insertion + Drive System Status Target System

MEG Review Meeting June Peter-Raymond Kettle Degrader Run Status Total 5 weeks planned: Many Problems encountered & several Surprises Total 5 weeks planned: Many Problems encountered & several Surprises However: some interesting facts learned !!! However: some interesting facts learned !!! Goal: Goal: first time measurement of Beam in COBRA with Degrader first time measurement of Beam in COBRA with Degrader System deployed at the centre of BTS System deployed at the centre of BTS understand misalignment problem seen Dec understand misalignment problem seen Dec. 2005Complications:  First time 6cm Target E employed during MEG Commissioning time  Lost more than 2 weeks of real beam time 11 days due to accelerator 11 days due to accelerator 2 days due to controller problems 3-D scanner 2 days due to controller problems 3-D scanner 1 day control computer problems BTS 1 day control computer problems BTS 1 day Separator vacuum interlock problems 1 day Separator vacuum interlock problems  Measurements stopped 4 last days lost due to interference COBRA stray field with other Users beam lines µSR  M3 (LTF, GPS)  E3 µCap-Expt. field with other Users beam lines µSR  M3 (LTF, GPS)  E3 µCap-Expt.  Run Programme SHORTENED Could Not Finish everything !!! Total 5 weeks planned: Many Problems encountered & several Surprises Total 5 weeks planned: Many Problems encountered & several Surprises However: some interesting facts learned !!! However: some interesting facts learned !!! Goal: Goal: first time measurement of Beam in COBRA with Degrader first time measurement of Beam in COBRA with Degrader System deployed at the centre of BTS System deployed at the centre of BTS understand misalignment problem seen Dec understand misalignment problem seen Dec. 2005Complications:  First time 6cm Target E employed during MEG Commissioning time  Lost more than 2 weeks of real beam time 11 days due to accelerator 11 days due to accelerator 2 days due to controller problems 3-D scanner 2 days due to controller problems 3-D scanner 1 day control computer problems BTS 1 day control computer problems BTS 1 day Separator vacuum interlock problems 1 day Separator vacuum interlock problems  Measurements stopped 4 last days lost due to interference COBRA stray field with other Users beam lines µSR  M3 (LTF, GPS)  E3 µCap-Expt. field with other Users beam lines µSR  M3 (LTF, GPS)  E3 µCap-Expt.  Run Programme SHORTENED Could Not Finish everything !!!

MEG Review Meeting June Peter-Raymond Kettle 1 st Surprise: Missing Rate from 6 cm Target! P µ AHW AHU AHV R 4cm =(0.55±0.05)R 6cm (1.8) R 4cm =(0.55±0.05)R 6cm (1.8) Measured  L. Simons et al (Pions!!!) Measured  L. Simons et al (Pions!!!) from geometry alone would expect ~ 0.67 (1.5) R 4cm =(0.55±0.05)R 6cm (1.8) R 4cm =(0.55±0.05)R 6cm (1.8) Measured  L. Simons et al (Pions!!!) Measured  L. Simons et al (Pions!!!) from geometry alone would expect ~ 0.67 (1.5) Very PROVISIONAL !!! Measured R 6cm ~ 1.24 R 4cm With slits open However: - at 1.8mA 6cm Target ~ 1.1 ·10 9 e + /s at 4cm Target ~ 7.7 ·10 8 e + /s at factor 1.38 factor 1.38 ** Naïve Model could explain missing µ + rate **: Surface µ +  Target Surface e+  Target Volume Very PROVISIONAL !!! Measured R 6cm ~ 1.24 R 4cm With slits open However: - at 1.8mA 6cm Target ~ 1.1 ·10 9 e + /s at 4cm Target ~ 7.7 ·10 8 e + /s at factor 1.38 factor 1.38 ** Naïve Model could explain missing µ + rate **: Surface µ +  Target Surface e+  Target Volume Low energy  -production X-sections  rel. stop density factors back face/side face/front face = 3.3/2.5/1.7 Low energy  -production X-sections  rel. stop density factors back face/side face/front face = 3.3/2.5/1.7 ProjectedIntensity dist. dist. (surface) (surface) Target E 4/6 cm If interpretation Correct  6 cm Target BAD for MEG Don’t gain µ + have ~ 1.4 more background e + If interpretation Correct  6 cm Target BAD for MEG Don’t gain µ + have ~ 1.4 more background e + EXPECTED EXPECTED

MEG Review Meeting June Peter-Raymond Kettle 2 nd Surprise: Beam Misalignment Cause! Bfield measurements with triple-axis Tesla meter & BTS showed: Bfield measurements with triple-axis Tesla meter & BTS showed: BTS Bfield asymmetry at symmetric distances from axis of max. 10G (below axis) BTS Bfield asymmetry at symmetric distances from axis of max. 10G (below axis) Equivalent to extra Dipole field Equivalent to extra Dipole field symmetry points above/below axis for equal Bfield ~ 30 cm displaced (therefore symmetry points above/below axis for equal Bfield ~ 30 cm displaced (therefore not error in measurement) not error in measurement) Area Floor exhibits Remanence & Hysterisis (remembers if BTS +ve/-ve polarity) Area Floor exhibits Remanence & Hysterisis (remembers if BTS +ve/-ve polarity) fields very reproducible, max. value on Area Floor fields very reproducible, max. value on Area Floor  Shows iron under the floor !!! which causes field lines to be diverted & alters the symmetry of the solenoidal field at a point which is important for focusing symmetry of the solenoidal field at a point which is important for focusing Further field measurements after DC-test – with COBRA & BTS ON !!! Further field measurements after DC-test – with COBRA & BTS ON !!! Enquired about Hall floor- plans should exist lay-out for 40t/m 2 40 cm thick layer of steel reinforced concrete 40 cm thick layer of steel reinforced concrete steel layer ~ 30 cm thick starts about 10 cm down steel layer ~ 30 cm thick starts about 10 cm down high-quality steel but NOT STAINLESS !!! high-quality steel but NOT STAINLESS !!! Enquired about Hall floor- plans should exist lay-out for 40t/m 2 40 cm thick layer of steel reinforced concrete 40 cm thick layer of steel reinforced concrete steel layer ~ 30 cm thick starts about 10 cm down steel layer ~ 30 cm thick starts about 10 cm down high-quality steel but NOT STAINLESS !!! high-quality steel but NOT STAINLESS !!!

MEG Review Meeting June Peter-Raymond Kettle 3 rd Surprise: Muons Prematurely Range-out! 100% 50% R~ 1460 mm He T MAT Expected: 100% transmission to centre COBRA, 100% transmission to centre COBRA, 50% to ~ end COBRA 50% to ~ end COBRA After degrader ~21 MeV/c entry to COBRA Measured: Mean Range at COBRA z= -900 mm R ~1460 mm He Equiv. R ~1460 mm He Equiv.  235 µm CH 2  235 µm CH 2 Extra Material Thickness T MAT ~ 900 mm He Equiv. or 145 µm CH 2 OR  9 % Air Contamination OR  9 % Air Contamination Know that air back diffusion Know that air back diffusion via leaks problematic as well as via leaks problematic as well as suspect “laminar flow” Mixing! suspect “laminar flow” Mixing! test measurement after DC-Test test measurement after DC-Test Measure Range Curve Measure Range Curve post BTS to test Momentum post BTS to test Momentum hypothesis hypothesis 18MeV/c  18 MeV/c in He in He

MEG Review Meeting June Peter-Raymond Kettle Beam Test Conclusions more than 2 weeks of real beam time lost mainly due to the accelerator more than 2 weeks of real beam time lost mainly due to the accelerator 6 cm target proved problematic since beam wasn’t as expected & 6 cm target proved problematic since beam wasn’t as expected & took time to investigate took time to investigate possible explanation for lack of increase in µ + rate from 6 cm Target possible explanation for lack of increase in µ + rate from 6 cm Target if true 6 cm Target No good for MEG signal/noise(e + ) bad if true 6 cm Target No good for MEG signal/noise(e + ) bad magnetic field anomaly found (Iron in floor) causes BTS field asymmetry & beam magnetic field anomaly found (Iron in floor) causes BTS field asymmetry & beam misalignment (further investigation needed) misalignment (further investigation needed) good He circulation crucial for MEG – possible cause of our muons ranging-out good He circulation crucial for MEG – possible cause of our muons ranging-out range curve post degrader & BTS should answer this range curve post degrader & BTS should answer this Need extra Beam Time (4 weeks) with 4 cm Target + Degrader Only possible after end July (4cm Target) –start 4cm Target unstable + low Only possible after end July (4cm Target) –start 4cm Target unstable + low Current MEGAPIE Current MEGAPIE Only possible after COBRA stray field influence on other beams solved Only possible after COBRA stray field influence on other beams solved To Not Delay MEG - has to be when End-Caps mounted – however problem To Not Delay MEG - has to be when End-Caps mounted – however problem no magnet measuring machine possible therefore NEW APD array Detector no magnet measuring machine possible therefore NEW APD array Detector NEEDED – (presented Tokyo Meeting) NEEDED – (presented Tokyo Meeting) Need extra Beam Time (4 weeks) with 4 cm Target + Degrader Only possible after end July (4cm Target) –start 4cm Target unstable + low Only possible after end July (4cm Target) –start 4cm Target unstable + low Current MEGAPIE Current MEGAPIE Only possible after COBRA stray field influence on other beams solved Only possible after COBRA stray field influence on other beams solved To Not Delay MEG - has to be when End-Caps mounted – however problem To Not Delay MEG - has to be when End-Caps mounted – however problem no magnet measuring machine possible therefore NEW APD array Detector no magnet measuring machine possible therefore NEW APD array Detector NEEDED – (presented Tokyo Meeting) NEEDED – (presented Tokyo Meeting)

MEG Review Meeting June Peter-Raymond Kettle Question of Muons Muons “Ranging-out” “Ranging-out” Question of Muons Muons “Ranging-out” “Ranging-out”

MEG Review Meeting June Peter-Raymond Kettle COBRA He-Atmosphere Measure Centre COBRA  X = 11.8 mm  Y = 12.0 X 0 4mm offset Y 0 on axis Rate ~ 8 ·10 7 µ + /s at 1.8mA, 6cm Target ~ 64% of muons ~ 64% of muons reach centre !!! reach centre !!! Measure Centre COBRA  X = 11.8 mm  Y = 12.0 X 0 4mm offset Y 0 on axis Rate ~ 8 ·10 7 µ + /s at 1.8mA, 6cm Target ~ 64% of muons ~ 64% of muons reach centre !!! reach centre !!! WHY?WHY? 1. Too much material in beam? Degrader too thick?Degrader too thick? New beam window >190 micronsNew beam window >190 microns Mylar Mylar Air contamination in He !!!Air contamination in He !!! 2.Momentum too low? 6cm Target (transverse offset) ???6cm Target (transverse offset) ??? AHW41 Bending magnetAHW41 Bending magnet measured momentum spectrum measured momentum spectrum 1. Too much material in beam? Degrader too thick?Degrader too thick? New beam window >190 micronsNew beam window >190 microns Mylar Mylar Air contamination in He !!!Air contamination in He !!! 2.Momentum too low? 6cm Target (transverse offset) ???6cm Target (transverse offset) ??? AHW41 Bending magnetAHW41 Bending magnet measured momentum spectrum measured momentum spectrum CheckedChecked CheckedChecked Muons Range-out prematurely

MEG Review Meeting June Peter-Raymond Kettle Beam Materials & Momentum Degrader: – 33 measurements per foil made Degrader: – 33 measurements per foil made New Mylar Window: - 16 measurements of New Mylar Window: - 16 measurements of sample of same foil made sample of same foil made Beam Momentum: - Integral & Differential Range Curve Beam Momentum: - Integral & Differential Range Curve measured post BTS using 50µm & 100 µm measured post BTS using 50µm & 100 µm Mylar foils Mylar foils Mylar foils + Holder Mylar foils + Holder APD+ Holder

MEG Review Meeting June Peter-Raymond Kettle Momentum Measurement Lowthreshold Highthreshold mm Air + 20 µm Al foil Counts µ+e Counts µ+e no threshold dependence no threshold dependence Michel MS ~ same for all Michel MS ~ same for all measurements measurements Counts µ+e Counts µ+e no threshold dependence no threshold dependence Michel MS ~ same for all Michel MS ~ same for all measurements measurements Counts µ only (Landau!) Counts µ only (Landau!) possible threshold dependence possible threshold dependence Counts µ only (Landau!) Counts µ only (Landau!) possible threshold dependence possible threshold dependence  T µ  = (2230 ± 60)keV  P µ  = (21.8 ± 0.3)MeV/c 3.8% higher than expected, Possible with 6cm Tg ! Gives lateral shift – p change  T µ  = (2230 ± 60)keV  P µ  = (21.8 ± 0.3)MeV/c 3.8% higher than expected, Possible with 6cm Tg ! Gives lateral shift – p change Mylar  R LL  = 355 µm  R UL  = 389 µm Mylar  R LL  = 355 µm  R UL  = 389 µm BEAM MOMENTUM OK !!!

MEG Review Meeting June Peter-Raymond Kettle COBRA He-atmosphere TU-1530 He-Monitor (Japan) Range 0-100% He Range 0-100% He accuracy ±1 % accuracy ±1 % Probe part magnetic Probe part magnetic TU-1530 He-Monitor (Japan) Range 0-100% He Range 0-100% He accuracy ±1 % accuracy ±1 % Probe part magnetic Probe part magnetic 2 Measurements used as cross-check Sonic Gas Monitor SGM (home-made) Calibrated Range % He Calibrated Range % He precision ±0.3 % precision ±0.3 % microphone + speaker magnetic microphone + speaker magnetic Sonic Gas Monitor SGM (home-made) Calibrated Range % He Calibrated Range % He precision ±0.3 % precision ±0.3 % microphone + speaker magnetic microphone + speaker magnetic

MEG Review Meeting June Peter-Raymond Kettle He Monitor Cross Calibration HeHe AirAir Gas Rack (mixer) True He-mixture TU-153  3.5% SGM  0.2% Measured Conc n TU-153 Monitor needs correction within % Range of  3.5% within % Range of  3.5% TU-153 Monitor needs correction within % Range of  3.5% within % Range of  3.5%

MEG Review Meeting June Peter-Raymond Kettle COBRA He-Measurements TU-153 sample He via inserted tube Sampling points: A: SGM B: z = mm C: z = mm D: z = + 45 mm E: z = mm SGM TU-153 AA BB CC DDEE Pos Comm Run DC Run B 97% 93% C 96% 92% D 90% 89% E 91% 89% Pos Comm Run DC Run B 97% 93% C 96% 92% D 90% 89% E 91% 89% He-gradient, worst US !!! He-gradient, worst US !!! explains ranging-out of Muons explains ranging-out of Muons He gas distribution too simple He gas distribution too simple Care with final gas system !!! Care with final gas system !!! He-gradient, worst US !!! He-gradient, worst US !!! explains ranging-out of Muons explains ranging-out of Muons He gas distribution too simple He gas distribution too simple Care with final gas system !!! Care with final gas system !!! P r o v i s i o n a l 7% to 11% Air 3% to 9% Air

MEG Review Meeting June Peter-Raymond Kettle Beam Misalignment & BTS + COBRA Influence BTS + COBRA Influence Beam Misalignment & BTS + COBRA Influence BTS + COBRA Influence

MEG Review Meeting June Peter-Raymond Kettle Beam Misalignment/Fringe Field Problem Initial field measurements during this run with BTS ONLY showed:  iron under the floor !!! which causes field lines to be diverted & alters the symmetry of the solenoidal field at a point which is important for focusing symmetry of the solenoidal field at a point which is important for focusing Measurements extended to Final BTS settings + COBRA Series of measurements done at US & DS faces of BTS with US & DS faces of BTS with BTS alone & BTS +COBRA: Asymmetry (beam pipe dia.) BTS alone: US ~ 6 G, C ~ 7G, DS ~ 5G BTS + COBRA: US ~ 6G, C ~ 0.6G, DS ~ 29G Series of measurements done at US & DS faces of BTS with US & DS faces of BTS with BTS alone & BTS +COBRA: Asymmetry (beam pipe dia.) BTS alone: US ~ 6 G, C ~ 7G, DS ~ 5G BTS + COBRA: US ~ 6G, C ~ 0.6G, DS ~ 29G

MEG Review Meeting June Peter-Raymond Kettle Radial BTS Symmetry (No COBRA) US DS Top Berg Aare Bot Top Berg Aare Bot BTS Measured radial Symmetry distributions US/DS at ~ beam pipe Diameter I= -200A v. Simple “c-of-g” v. Simple “c-of-g” interpretation interpretation Magnetic axis centre Magnetic axis centre US: r=2.1 mm,  =292.5° Field Asymmetry ~ 11G Field Asymmetry ~ 11G DS: r= 6.0 mm,  =247.5° Field Asymmetry ~ 33 G Field Asymmetry ~ 33 G BTS Measured radial Symmetry distributions US/DS at ~ beam pipe Diameter I= -200A v. Simple “c-of-g” v. Simple “c-of-g” interpretation interpretation Magnetic axis centre Magnetic axis centre US: r=2.1 mm,  =292.5° Field Asymmetry ~ 11G Field Asymmetry ~ 11G DS: r= 6.0 mm,  =247.5° Field Asymmetry ~ 33 G Field Asymmetry ~ 33 G

MEG Review Meeting June Peter-Raymond Kettle Radial COBRA Asymmetry BTS+COBRA TopTop Bot t COBRA Measured radial symmetry distribution US at ~ beam pipe diameter I BTS = -203A, I COBRA =360/320A I BTS = -203A, I COBRA =360/320A v. Simple “c-of-g” interpretation v. Simple “c-of-g” interpretation Magnetic axis centre Magnetic axis centre US: r=1.7 mm,  =240° US: r=1.7 mm,  =240° asymmetry ~ 55G asymmetry ~ 55G Problem to be studied by PSI Magnet Group !!! COBRA Measured radial symmetry distribution US at ~ beam pipe diameter I BTS = -203A, I COBRA =360/320A I BTS = -203A, I COBRA =360/320A v. Simple “c-of-g” interpretation v. Simple “c-of-g” interpretation Magnetic axis centre Magnetic axis centre US: r=1.7 mm,  =240° US: r=1.7 mm,  =240° asymmetry ~ 55G asymmetry ~ 55G Problem to be studied by PSI Magnet Group !!! COBRAcentre COBRAcentre Influence on µ-Beam COBRA Beam Centroid Excursion COBRA Beam Centroid Excursion

MEG Review Meeting June Peter-Raymond Kettle COBRA End-Cap + Insertion & Drive System Insertion & Drive System COBRA End-Cap + Insertion & Drive System Insertion & Drive System

MEG Review Meeting June Peter-Raymond Kettle COBRA US End-Cap System USUSDSDS US End-Cap schedule Bieri Engineering manufacture costs ~ 55 kCHf Bieri Engineering manufacture costs ~ 55 kCHf delivery to PSI – THIS WEEK (2 weeks late) delivery to PSI – THIS WEEK (2 weeks late)

MEG Review Meeting June Peter-Raymond Kettle Insertion System Connects to accelerator Beam pipe Gliding support rings NBR RETRACTED into End-Cap Replacewithwindow Gas-tight to He-side CH 2 /EVAL window Gas-tight to He-side CH 2 /EVAL window normally connected to motor-driven accelerator normally connected to motor-driven accelerator beam tube beam tube frictional hand-drive via electric drill/crank-handle frictional hand-drive via electric drill/crank-handle Detailed FEM study Electric-drill or hand drive View from Inside COBRA

MEG Review Meeting June Peter-Raymond Kettle COBRA DS End-Cap + Insertion & Drive Systems Complication encountered with DS End-Cap + Insertion & Drive System: Offer received from Bieri Engineering ~ 200kCHf !!! successful negotiations with PSI Management for extra money MEG project raised to priority 1 again – hence PSI workshops can take-over assembly & testing of complete system … Bieri price now ~ 140 kCHf Delivery schedule: End-August DS End-Cap (as planned but v. tight) Delivery schedule: End-August DS End-Cap (as planned but v. tight) Mid-September Insertion & Drive System Mid-September Insertion & Drive System

MEG Review Meeting June Peter-Raymond Kettle BTS  -Beam Test  -Beam TestBTS

MEG Review Meeting June Peter-Raymond Kettle BTS Pion Beam Test 1 st MEG  -beam Studies in 2004: part of momentum spectrum study part of momentum spectrum study MeV/c MeV/c dedicated runs at 56 MeV/c & 103 MeV/c dedicated runs at 56 MeV/c & 103 MeV/c CEX run in  E5 at 112 MeV/c Oct CEX run in  E5 at 112 MeV/c Oct ALL BEFORE BTS ARRIVED!!! ALL BEFORE BTS ARRIVED!!! Problem: BTS cannot be excited to transmit Momenta >> 70 MeV/c since maximum I BTS ~ 270 A maximum I BTS ~ 270 A exceeds allowed force on COBRA coils exceeds allowed force on COBRA coils Results Results  - Integral Spot Rates in MHz  - Integral Spot Rates in MHz for 1,8mA Proton Current & 4cm Target E Measured UPSTREAM of BTS position Normalized to Momentum Slit Settings: Normalized to Momentum Slit Settings: FS41L/R 250/280 FS43L/R 240/220 FS41L/R 250/280 FS43L/R 240/220 Results Results  - Integral Spot Rates in MHz  - Integral Spot Rates in MHz for 1,8mA Proton Current & 4cm Target E Measured UPSTREAM of BTS position Normalized to Momentum Slit Settings: Normalized to Momentum Slit Settings: FS41L/R 250/280 FS43L/R 240/220 FS41L/R 250/280 FS43L/R 240/ MeV/c R  = 7.6 ·10 6  - /s slits open R  = 7.2 ·10 5  - /s slits70/70 R  = 7.2 ·10 5  - /s slits70/70 56 MeV/c R  = 7.6 ·10 6  - /s slits open R  = 7.2 ·10 5  - /s slits70/70 R  = 7.2 ·10 5  - /s slits70/70 Solution: - should be able to transmit 56 Mev/c particles (2*28 MeV/c) with Good optics Solution: - should be able to transmit 56 Mev/c particles (2*28 MeV/c) with Good optics Single Node SNM SNM Double Node DNM DNM 56 MeV/c 28 MeV/c Measured US BTS

MEG Review Meeting June Peter-Raymond Kettle BTS  -Beam Test cont. BTS test done last week: Problem encountered – Hamamatsu APD used for µ + (no scint. but utilize “Nuclear Counter Effect”) used for µ + (no scint. but utilize “Nuclear Counter Effect”) has no pulse-ht. resolution for  - CANNOT DISTINGUISH e - &  - has no pulse-ht. resolution for  - CANNOT DISTINGUISH e - &  - measured at 56 MeV/C & 107 MeV/c with APD & Pill Counter (scintillator) measured at 56 MeV/C & 107 MeV/c with APD & Pill Counter (scintillator) see pions & electrons with pill-counter BUT CANNOT USE WITH BTS BFIELD see pions & electrons with pill-counter BUT CANNOT USE WITH BTS BFIELDHOWEVER: COULD TRANSMIT 56 MeV/c PARTICLES as expected BTS Excitation Curve For 56 MeV/c particles Question: What are expected low-energy What are expected low-energy Pion Beam Rates at centre of COBRA? Pion Beam Rates at centre of COBRA?Question: What are expected low-energy What are expected low-energy Pion Beam Rates at centre of COBRA? Pion Beam Rates at centre of COBRA?

MEG Review Meeting June Peter-Raymond Kettle BTS  -Beam Test cont. CONCLUSION: APDs with scintillators needed for Expt. APDs with scintillators needed for Expt. Cross-System of 13 APDs must be built Cross-System of 13 APDs must be built before final Commissioning with 4cm Tg before final Commissioning with 4cm Tg max.  - momentum for good optics max.  - momentum for good optics ~ 70 MeV/c !!! ~ 70 MeV/c !!! expected rate (slits open) 1.6 MHz at COBRA centre expected rate (slits open) 1.6 MHz at COBRA centreCONCLUSION: APDs with scintillators needed for Expt. APDs with scintillators needed for Expt. Cross-System of 13 APDs must be built Cross-System of 13 APDs must be built before final Commissioning with 4cm Tg before final Commissioning with 4cm Tg max.  - momentum for good optics max.  - momentum for good optics ~ 70 MeV/c !!! ~ 70 MeV/c !!! expected rate (slits open) 1.6 MHz at COBRA centre expected rate (slits open) 1.6 MHz at COBRA centre Expected low-energy Pion Beam Rates at centre COBRA for 1.8 mA Proton Beam 4 cm Tg. Taking decay-rate into account Expected low-energy Pion Beam Rates at centre COBRA for 1.8 mA Proton Beam 4 cm Tg. Taking decay-rate into account Expected Pion Beam Rates Centre COBRA 70 MeV/c  ~ 1.6MHz at 1.8mA I PROT 70 MeV/c  ~ 1.6MHz at 1.8mA I PROT

MEG Review Meeting June Peter-Raymond Kettle Target System UCI UCI Target System UCI UCI

MEG Review Meeting June Peter-Raymond Kettle Target System Mechanical Requirements Substantial Progress made with Target System since last Review !!! Supported from DC Support Structure Supported from DC Support Structure externally surveyed & introduced with DCs externally surveyed & introduced with DCs possibility to move target for End-Cap Insertion System introduction (C-W, LH 2,…) possibility to move target for End-Cap Insertion System introduction (C-W, LH 2,…)  “ target parking”  “ target parking” Mechanically stable & reproducible positioning Mechanically stable & reproducible positioning DC Support Structure InsertionBellows DC structure “Target Parking” New method of “Parking” using Translation rather than Rotation Target movement

MEG Review Meeting June Peter-Raymond Kettle Target System Characteristics Present Target Characteristics: Ellipse (210 x 70)mm Polyester foil 175 µm Ellipse (210 x 70)mm Polyester foil 175 µm freely suspended by support pins from a freely suspended by support pins from a thin Rohacell support frame at ~22° to axis thin Rohacell support frame at ~22° to axis (differential expansion) (differential expansion) frame attached by Rohacell support stems frame attached by Rohacell support stems mounted on v. thin movable rods mounted on v. thin movable rods Driven by pneumatic drive Driven by pneumatic drive Present Target Characteristics: Ellipse (210 x 70)mm Polyester foil 175 µm Ellipse (210 x 70)mm Polyester foil 175 µm freely suspended by support pins from a freely suspended by support pins from a thin Rohacell support frame at ~22° to axis thin Rohacell support frame at ~22° to axis (differential expansion) (differential expansion) frame attached by Rohacell support stems frame attached by Rohacell support stems mounted on v. thin movable rods mounted on v. thin movable rods Driven by pneumatic drive Driven by pneumatic drive polyesterpolyester Rohacell DC Support Pneumatic Drive Drive Movement Current Status UCI: prototype system prototype system successfully tested successfully tested Final System All parts machined All parts machined Assembly & testing about Assembly & testing about to start to start target foil material & angle target foil material & angle still under study still under study

MEG Review Meeting June Peter-Raymond Kettle Prototype Target & Performance Test Setup UCI Pins on which film is hung Screws for clamping frame Rohacell Frame DC Support Tube Tube Thin film (~175 micron) target – material to be determined Thin film (~175 micron) target – material to be determined “soft” polyethylene too difficult to maintain flat “soft” polyethylene too difficult to maintain flat Various polyester, polystyrene, “hard” polyethylene materials possible Various polyester, polystyrene, “hard” polyethylene materials possible Implementation Implementation Target flatness controlled by Rohacell frame – clamping two frames together allows control of flatness Target flatness controlled by Rohacell frame – clamping two frames together allows control of flatness Hanging film between frames Hanging film between frames allows for differential expansion allows for differential expansion without deformation of film without deformation of film Distance between frames controlled Distance between frames controlled by washers at screw locations by washers at screw locations Final frame cut precisely with high Final frame cut precisely with high speed CNC router speed CNC router Nylon screws/nuts used to reduce mass Nylon screws/nuts used to reduce mass

MEG Review Meeting June Peter-Raymond Kettle Prototype Target & Performance cont. Flatness measured by reflected laser off target surface and measuring reflected angle as laser spot is scanned across target. Z(x,y) = Z(0,0) + ∫ (dz/dx)dx + ∫(dz/dy)dy Flatness measured by reflected laser off target surface and measuring reflected angle as laser spot is scanned across target. Z(x,y) = Z(0,0) + ∫ (dz/dx)dx + ∫(dz/dy)dy Target measured to be flat to less than +/-100 microns Target measured to be flat to less than +/-100 microns Target Size Study Measured 45° target  88% stops Slanted target gives “leakage” due to MS Relatively insensitive to vertical size down to 5.7cm Relatively insensitive to length down to 19 cm HOWEVER Thickness of 175 microns required Final Parameters + slope sense still under study

MEG Review Meeting June Peter-Raymond Kettle Schedule US End-Cap: US End-Cap: Delivery US COBRA End-Cap: end June Delivery US COBRA End-Cap: end June US End-Cap preparations mounting PSI workshops 6WD installation after US TC US End-Cap preparations mounting PSI workshops 6WD installation after US TC US End-Cap installation 5WD Beg. Sept. US End-Cap installation 5WD Beg. Sept. Target System: Production End July Production End July Target assembly + installation 2W Target assembly + installation 2W DS End-Cap + Insertion & Drive System: Delivery DS COBRA End-Cap End Aug. – Mid Sept. Delivery DS COBRA End-Cap End Aug. – Mid Sept. Delivery Insertion + Drive System Mid Sept. Delivery Insertion + Drive System Mid Sept. DS End-Cap preparations mounting PSI workshops 6WD installation after DS TC DS End-Cap preparations mounting PSI workshops 6WD installation after DS TC Insertion & Drive System mounting + testing PSI workshops 6WD Insertion & Drive System mounting + testing PSI workshops 6WD DS End-Cap + Insertion & Drive System installation 10WD End. Sept. DS End-Cap + Insertion & Drive System installation 10WD End. Sept. Beam Commissioning (degrader + 4cm Tg.) Beam Line setup + survey 5WD post US End-Cap Beg. Sept. Beam Line setup + survey 5WD post US End-Cap Beg. Sept. BTS cryo-connections + pump & cool-down 8WD BTS cryo-connections + pump & cool-down 8WD Beam Commissioning Run 4Weeks Beg. Oct. Beam Commissioning Run 4Weeks Beg. Oct. Pion Beam Tune CEX 7D (if not during Comm. Run) before LXe Calib. Mid. Dec. Pion Beam Tune CEX 7D (if not during Comm. Run) before LXe Calib. Mid. Dec.