Machine Protection Review, Markus Zerlauth, 12 th April 2005 1 Magnet powering system and beam dump requests Markus Zerlauth, AB-CO-IN.

Slides:



Advertisements
Similar presentations
Jan Uythoven, AB/BTLHCCWG, 3 May 2006 Page GeV Commissioning Machine Protection Needs to be commissioned to: Prevent damage with the used, higher.
Advertisements

LHC Machine Protection
André Augustinus 15 March 2003 DCS Workshop Safety Interlocks.
6 th April 2010 MP3 weekly summary – issues and follow-up 0v1 M. Zerlauth for the MP3-CCC shift crew.
LHC Machine Interlocks & Beam Operation LHC Machine Interlocks & Beam Operation ARW2011Bruno PUCCIO (CERN) 13 th April v0 Thanks to Benjamin Todd.
MPS External ReviewMarkus Zerlauth September 2010 Magnet Powering System Magnet powering and Protection Commissioning of Powering Protection Systems Failures.
Elec467 Power Machines & Transformers
LHC UPS Systems and Configurations: Changes during the LS1 V. Chareyre / EN-EL LHC Beam Operation Committee 11 February 2014 EDMS No /02/2014.
PAC June LHC Machine Protection Rüdiger Schmidt R.Assmann, E.Carlier, B.Dehning, R.Denz, B.Goddard, E.B.Holzer, V.Kain, B.Puccio, B.Todd, J.Uythoven,
Concept & architecture of the machine protection systems for FCC
LECC 2006 Ewald Effinger AB-BI-BL The LHC beam loss monitoring system’s data acquisition card Ewald Effinger AB-BI-BL.
Oliver Bitterling  Introduction to the QPS  Radiation damage in electronic systems  Construction of radiation tolerant systems  Radiation test and.
TEV DUMP SWITCH FAILURES OF 2/10/09 Dan Wolff/EE Support.
Surge current protection using superconductor
1 Copper Stabilizer Continuity Measurement Project CSCM Mini Review Powering Implementation H. Thiesen 30 November 2011.
POWER SYSTEM PROTECTION
How to achieve higher redundancy of the UPS for QPS ? -The lack of redundancy concerns the supply lines from UPS to consumer but equally parts of the UPS.
Chamonix Risks due to UPS malfunctioning Impact on the Superconducting Circuit Protection System Hugues Thiesen Acknowledgments:K. Dahlerup-Petersen,
1 Second LHC Splice Review Copper Stabilizer Continuity Measurement possible QC tool for consolidated splices H. Thiesen 28 November 2011 K. Brodzinski,
CERN Rüdiger Schmidt FCC week 2015 Long Magnet Stringpage 1 Incident September 19 th Architecture of powering and protection systems for high field.
Interlock and Protection Systems for SC Accelerators: Machine Protection System for the LHC l The Risks l The Challenge l The LHC Layout l The Systems.
Etienne CARLIER, LBDS Audit, 28/01/2008 LBDS Environmental Aspects EMC, radiation, UPS… Etienne CARLIER AB/BT/EC.
Training LHC Powering R. Denz Quench Protection System R. Denz AT-MEL.
L4T Bending Power Converters: ‘ Implications of monitoring the current to 5% and 0.5%’ L4 BCC - 10 Nov 2011 David Nisbet TEEPC.
1 Will We Ever Get The Green Light For Beam Operation? J. Uythoven & R. Filippini For the Reliability Working Group Sub Working Group of the MPWG.
1 CC & MP - CC10 - CERN Crab LHC J. Wenninger CERN Beams Department for the LHC Machine Protection Panel.
Interlocks for Magnet Protection System Iván Romera Ramírez, Markus Zerlauth - CERN.
AT-MEI-PE, RD, LIUWG 31-JUL R. Denz AT-MEI-PE LHC Luminosity Upgrade Protection of the Inner Triplet, D1, Correctors and Superconducting Links/Leads.
Status of ITER collaboration for Machine Protection I. Romera On behalf of the colleagues who contribute to the project Thanks to: Sigrid, Markus, Rüdiger,
‘Review’ of the machine protection system in the SPS 1 J. Wenninger BE-OP SPS MPS - ATOP 09.
ABOC/ATC days Electrical Network: Selectivity and Protection Plan José Carlos GASCON TS–EL Group 22 January 2007.
1 Commissioning and Early Operation – View from Machine Protection Jan Uythoven (AB/BT) Thanks to the members of the MPWG.
TE/MPE activities currently planed for YETS Reiner Denz, Knud Dalherup-Petersen, Markus Zerlauth & Bruno Puccio YETS coordination meeting.
BCWG - 16/11/20102 Content WHY do we need a HW Commissioning campaign? WHAT are we going to do? HOW are we going to do it? ElQA QPS Powering Tests Planning.
A SEMINAR ON 400 KV GSS(RRVPNL) BIKANER.
AB/CO Review, Interlock team, 20 th September Interlock team – the AB/CO point of view M.Zerlauth, R.Harrison Powering Interlocks A common task.
TE-MPE -EI 23/6/2011,Antonopoulou Evangelia RQS circuit Simulation results of Quench Antonopoulou Evangelia June 2011 Thanks to E. Ravaioli.
B. Todd et al. 19 th August 2009 The Beam Interlock System Thanks to: Machine Protection Panel, R. Schmidt, B. Puccio, M. Zerlauth and many more… 0v2.
TE/MPE/MI MPE-TM30 th June 2011 FMCM sensitivity to mains perturbations 0v1 M. Zerlauth.
Conclusions on UPS powering test and procedure I. Romera Acknowledgements: V. Chareyre, M. Zerlauth 86 th MPP meeting –
Machine Protection Review, R. Denz, 11-APR Introduction to Magnet Powering and Protection R. Denz, AT-MEL-PM.
Main dipole circuit simulations Behavior and performance analysis PSpice models Simulation results Comparison with QPS data Ongoing activities Emmanuele.
LHC Machine Protection: an introduction Jörg Wenninger OP training March 2006 Acknowledgments to my colleagues of the MPWG for input and material.
Training LHC Powering - Markus Zerlauth Powering Interlocks Markus Zerlauth AB/CO/MI.
MPP Meeting 07/03/2007 MPP Main Ring Magnet Performance Panel Meeting Wednesday 7th March 2007 Agenda: 1)Matters arising 2)Recommendations for the case.
Interfacing the FMCM for additional protection in the LHC and the SPS- LHC/CNGS Transfer Lines to the CERN controls system Cristina Gabriel Casado, Interlock.
LHC machine protection close-out 1 Close-out. LHC machine protection close-out 2 Introduction The problem is obvious: –Magnetic field increase only a.
STEVE HAYS AD E/E SUPPORT E4R POWER SYSTEM for HTS MAGNET WIRE TEST.
PLCs at CERN for machine protection and access interlocks Session: Machine Protection and interlock systems at different labs I. Romera Ramírez (CERN /
LIU-PSB Working Group meeting: 25/06/2015, Markus Zerlauth Consolidation of magnet interlocks in the PS complex – Warm magnet Interlock System (WIC) R.Mompo,
Training LHC Powering – Blanca Perea Solano From Individual System Tests to Powering to Nominal Blanca Perea on behalf of Hardware Commissioning Coordination.
Inner Triplet Protection Strategy LHC & HL-LHC Daniel Wollmann with Inputs from B. Auchmann, G. Ambrosio, R. Denz, P. Fessia, E. Ravaioli, F. Rodrigues.
Main MPE Activities during YETS/EYETS/LS2 and the Provision of Resources Andrzej Siemko Andrzej Siemko TE-MPE1.
Beam Interlock System SPS CIBU Connection Review
Dependability Requirements of the LBDS and their Design Implications
Powering LHC magnets version 30/3/2007.
Superconducting Circuits, a generic view
Acknowledgements: H.Milcent, R.Denz, R.Schmidt, M.Zerlauth
Potential failure scenarios that can lead to very fast orbit changes and machine protection requirements for HL-LHC operation Daniel Wollmann with input.
LV Safe Powering from UPS to Clients
Powering the LHC Magnets
the CERN Electrical network protection system
Update on circuit protection simulations of the HL-LHC Inner Triplet circuit Matthias Mentink, Circuit specifics + STEAM simulations: Samer Yammine, LEDET.
Rüdiger Schmidt and Karl Hubert Mess
Initial Experience with the Machine Protection System for LHC
Machine Protection Xu Hongliang.
Interlocking of CNGS (and other high intensity beams) at the SPS
M. Zerlauth, I. Romera 0v1.
Machine Protection System Commissioning plans
Will We Ever Get The Green Light For Beam Operation?
Presentation transcript:

Machine Protection Review, Markus Zerlauth, 12 th April Magnet powering system and beam dump requests Markus Zerlauth, AB-CO-IN

Machine Protection Review, Markus Zerlauth, 12 th April Outline  Magnet Powering for the LHC and SPS-LHC Transfer lines –See also ‘Introduction to Magnet Powering and Protection’ by R.Denz  Powering of electrical circuits with normal conducting magnets  Powering of electrical circuits with superconducting magnets  Timescales for a beam dump by the interlock systems in case of different powering failures – Can we dump before beam losses occur?  Fast Magnet Current Change Monitors providing additional protection  Protection against combined failures

Machine Protection Review, Markus Zerlauth, 12 th April Magnet powering for superconducting and normal conducting magnets ~1600 electrical circuits with sc magnets in the LHC ~ 40 electrical circuits with 150 nc magnets in the LHC ~ 25 electrical circuits with 800 nc magnets in SPS extractions lines & CNGS  Machine protection of the LHC starts already with its pre-injectors and the transfer lines  Magnet powering and interlock systems in the SPS, transfer lines and the LHC are more or less identical see also: Talks of R. Denz and R.Schmidt

Machine Protection Review, Markus Zerlauth, 12 th April Magnet Powering and Beam Dump Requests for the LHC  Magnet powering system will account for a considerable fraction of beam dump requests due to (e.g. beam induced) magnet quenches, power converter failures, mains failures, etc..  Due to its complexity and the requirement of flexibility (not all powering failures require beam dumps), the powering interlock systems are separated from the beam interlock system SUPER- CONDUCTING MAGNETS R. Assmann J. Uythoven B.Goddard B. Todd C. Zamantzas B. Dehning V. Kain

Machine Protection Review, Markus Zerlauth, 12 th April Protection mechanisms for normal conducting magnets / circuits Magnet 1 Power Converter Magnet 2 Internal failures / Ground Fault Cooling Failures Warm Magnet Interlock Controller Network, UTC, Logging Beam Dump Normal conducting cables Several thermo- 60°C Several thermo- 60°C Power Permit

Machine Protection Review, Markus Zerlauth, 12 th April Protection mechanisms for superconducting magnets / circuits Magnet 1 Power Converter Magnet 2 HTS Current Leads sc busbar DFB Internal failures / Ground Fault Cooling Failures Network, UTC, Logging Beam Dump AUG, UPS, Mains Failures Normal conducting cables Quench Signal Superconducting Diode Energy Extraction Quench- Heater QPS Powering Interlock Controller Power Permit

Machine Protection Review, Markus Zerlauth, 12 th April Powering Interlocks for sc and nc magnets Powering Interlock Controller (PIC) Protect electrical circuits with super conducting magnets (LHC) HW Interfaces with quench protection system, converters, emergency stop, UPS PLC Siemens S7-400 Real-Time (Response time ~5 msec) Typical Powering Failures: Quenches, internal converter or cooling failures Warm Magnet Interlock Controller (WIC) Protect electrical circuits with normal conducting magnets (TI8/TI2, CNGS, LEIR, LHC, SPS, etc…) HW Interfaces with Magnets (Thermo- Switches) and power converters PLC Siemens S7-300 Real-Time (Response time ~ sec) Typical Powering Failures: Magnet overheating, internal converter failure

Machine Protection Review, Markus Zerlauth, 12 th April Requirements for the powering interlock system- Event Chain from powering failures to beam dumps  Prior task is the protection of powering equipment (magnets, busbars, current leads, cables,…) -> ms reaction time sufficient  Collect protection signals from the powering equipment and issue the beam dump requests if necessary  Up to 4 protection signals/circuit or magnet are exchanged using hardwired current loops -> No safety critical function via SW  Simple, robust, fails safe and quasi-redundant signal transmission (Safety, Reliability, Availability)  Not influenced by EMC (successfully tested to highest level of the norm)  For most failure cases, the issued beam dump request provide redundancy to BLM’s, as the fault is transmitted to the Beam Dumping System before beam losses occur  For some failure cases, the issued beam dump request will not be fast enough and other monitors (BLM etc) need to trigger the beam dump  But, for single turn failures the BLM system can not prevent damage (TT40 incident end of last year) see also: Talks of B.Todd and R. Filippini

Machine Protection Review, Markus Zerlauth, 12 th April Failure case #1: Overheating of a normal-conducting magnet Magnet 1 Power Converter Magnet 2 Internal failures / Ground Fault Beam Dump Request Normal conducting cables Several thermo- 60°C Power Permit Warm Magnet Interlock Controller  Overheating of magnet due to e.g. cooling failure  Up to 6 thermo-switches on the magnet -> Signal to the interlock controller  Controller will first switch off the beam  After an additional delay of 1 sec the converter is stopped, to avoid a decaying magnetic field as long as beam is present  One of the reasons of the beam incident in TT40 was that a PLC switched off the power converter first, and only then inhibited extraction of beam

Machine Protection Review, Markus Zerlauth, 12 th April Magnet 1 Power Converter Magnet 2 HTS Current Leads DFB Internal failures / Ground Fault Cooling Failures Beam Dump Quench- Heater QPS Powering Interlock Controller Power Permit  Power converter detects internal failure, switches immediately OFF and informs powering interlock (e.g. direct opening of the main circuit breaker )  Upon reception, the interlock controller immediately triggers a beam dump (HW Matrix in parallel to PLC process to minimize delays), but magnetic field is already decaying! Failure case #2: Internal Failures of the power converter

Machine Protection Review, Markus Zerlauth, 12 th April The Timescales T 0 Failure occurs T 2 PIC issues beam dump T 3 Beam dump is received by the BIC T 4 Completion of beam dump 400μs for HW Matrix 5 ms…for PLC < 100μs < 270μs Current in the magnet Decay starts immediately (opening of main circuit breaker of the power converter) PIC process T 1 PIC receives Failure signal Opening of the relay contact by the PC < 50 ms Failure case #2: Internal Failures of the power converter  Delay due to signal transmission via a relay contact  Τ>> (for sc magnets, but NOT for nc magnets), converter output filter and eddy currents limit the field decay and relax the detection

Machine Protection Review, Markus Zerlauth, 12 th April Magnet 1 Power Converter Magnet 2 HTS Current Leads DFB Internal failures / Ground Fault Cooling Failures Beam Dump Quench- Heater QPS Powering Interlock Controller Power Permit  Quenching of sc magnet due to e.g. beam losses  Quench detection by the QPS system  Transmission of quench signal, firing of heaters and activation of EE system  Current decay only upon complete opening of EE switch, diode will become conductive much later Failure case #3: Quench of a superconducting magnet Talk of R. Denz Diode becomes conductive

Machine Protection Review, Markus Zerlauth, 12 th April The Timescales T 0 Quench signal in local quench loop T 2 PIC reads signal T 1 Transmission time to Quench Loop Controller T 3 PIC issues beam dump T 4 Beam dump is received by the BIC T 5 Completion of beam dump 400μs of HW Matrix < 100μs < 270μs < 15 μs< 1 ms5..8 ms T 1 Transmission time to EE system T 2 Switch Opening T 3 Last branch open, arc is extinct – Current in dipole magnets decays Current in dipole circuit Diode becomes conductive > 80ms Heaters efficient >> < 15 μs< 1 ms Decay starts somewhat before the complete arc extinction due to resistive arc // resistor Mechanic opening & arc extinction PIC process state change and measurement Failure case #3: Quench of a superconducting magnet  Powering Interlock system requests a beam dump before the current in the dipole magnet starts decaying (all other magnets even less time critical)

Machine Protection Review, Markus Zerlauth, 12 th April  For superconducting magnets, the large natural time constant relaxes the required detection time  For a number of normal conducting magnets (T ~ sec) such as septas and separation dipoles, current changes of 5*10E-4 can be hazardous and beams have to be dumped in < 1ms  Very fast losses occur (due to the quickly decaying field)  Present powering interlock system provides NO redundancy to BLMs  Idea of a Fast Magnet Current Change Monitor, initially developed at DESY and recently successfully tested for the SPS extraction septa and the LHC separation dipole D1 With courtesy of M. Werner Failure case #4: Powering failure in magnets with effects on the beam very shortly after the failure

Machine Protection Review, Markus Zerlauth, 12 th April  Measurement of fast current changes (typical for powering failures), instead of absolute values  Based on measurements of the magnet voltage rather than a DCCT readout  RT calculation of the current based on a model of the circuit impedance Example of measurements during a shut down of a nc separation dipole (D1): With courtesy of M.Werner Failure case #4: Powering failure in magnets with large effects on the beam DCCT Readout Hall-Probe Readout RT current calculation Magnet Voltage Hall-Probe Readout Trip of PC Detection level 2*10E-4 of nom I Delay due to Eddy-Currents

Machine Protection Review, Markus Zerlauth, 12 th April Combined failures  Failures of the mains supply could affect not only single circuits, but a complete machine sector  Lightnings or brown outs, but also emergency stops could trip the complete powering system of a machine sector (small tolerances for thyristor converters)  No direct beam dumps are generated by the electrical distribution system for the time being  Fast Magnet Current Change Monitor would be the first device to detect such a failure  Simulations for combined failures in progress, but most insertions are covered by a FMCCM

Machine Protection Review, Markus Zerlauth, 12 th April Conclusions and Outlook  Beam dump requests from the powering interlock systems provide redundancy to e.g. BLM for most of the powering failure scenarios  Due to the limited response time of the powering interlock system, one has to rely on BLMs and collimators for some special failure cases  Whenever possible, delays are minimized (HW Matrix in parallel to the PLC, fast relays,...) to dump the beam before any beam lossess occur  Additional systems are studied for protection of critical normal conducting circuits and pulsing magnets  Combined failures as e.g. due to thunderstorms and mains losses could equally be captured using such additional protection measures