Network Regulation Rule Change Proposals AEMC Public Forum George Maltabarow Managing Director Ausgrid
2 I’ll talk about: Role of the AEMC and the National Electricity Objective Experiences under the previous framework - and how it failed Benefits of the new framework – examples of how it’s working Why Ausgrid believes the case for change has not been made.
3 National Electricity Objective & moving goal posts AEMC rightly focuses on: - efficiency - transparency - predictability - certainty Framework - Moving Goal Posts - Last two resets – two different sets of rules - Now a third set of rule changes proposed - Framework must be stable, mature, predictable
4 Previous framework – under investment Unguided Regulators: IPART kept prices artificially low at the cost of the safety & reliability Actual capex vs assumed annual average annual cost of replacing network ($M, real) Network under-investment Actual Capex Replacement cost Catch-up expenditure
5 Circuit Breaker Failures - Mason Park STSS 132kV Air Blast Circuit Breaker Failure, Mason Park STSS, 2006 Cracks in Circuit Breaker
6 Hosing down North Sydney Zone The Sunday Telegraph, 17 October 2004, page 1
7 Major failures 11kV Circuit Breaker Failure, Matraville Zone, kV Transformer Bushing Failure, Milperra Zone, 2003
8 Benefits of the framework Maintenance average unit costs reduced by approx 4% In 2005, kV feeders overloaded. Now there are % drop in no. of blackouts from equipment since 03/04. Average number of blackouts on rural power lines halved since 2003/04.
9 AER already has powers Information asymmetry - AER required more detailed information - now can’t use it - rule change not the answer Substitution Ausgrid (NSW)- AER cut: - $460M in capital funding, and - $360M in operating costs - Tribunal upheld AER’s decision
10