ATF2 Status and Plans CLIC 2016118-22 January 2016.

Slides:



Advertisements
Similar presentations
Tests of DFS and WFS at ATF2 Andrea Latina (CERN), Jochem Snuverink (RHUL), Nuria Fuster (IFIC) 18 th ATF2 Project Meeting – Feb – LAPP, Annecy.
Advertisements

Beam position monitors LCABD Plenary meeting Bristol, 24th March 2009 A. Aryshev, S. T. Boogert, G. Boorman, S. Molloy, N. Joshi JAI at Royal Holloway.
ATF Cooling Water System Toshiyuki OKUGI, KEK 2015/ 2/ 24 ATF2 Project Meeting LAPP (Annecy, France)
IPBPM piezo-mover system and plans for in situ monitoring of calibration and stability Current status and plan for ATF2 Philip Bambade Laboratoire de l’Accélérateur.
CLIC Kickers: Status and activities for 2013 in view of the budget discussions for 2013 CTC #65 M.J. Barnes CLIC Technical Committee, November M.J.
-brief report of October runs and some inputs for the Nov/Dec planning – Nobuhiro Terunuma, KEK, ATF ATF session on LCWS13, Tokyo Univ., Nov. 13, 2013.
ATF2 Progress Report For CLIC Workshop Kiyoshi KUBO.
Analysis of ATF EXT/FF Orbit Jitter and extrapolation to IP (Data of ) ATF2 Project Meeting K. Kubo.
Progress towards nanometre-level beam stabilisation at ATF2 N. Blaskovic, D. R. Bett, P. N. Burrows, G. B. Christian, C. Perry John Adams Institute, University.
ATF2 Status and Plan K. Kubo ATF2, Final Focus Test for LC Achievement of 37 nm beam size (Goal 1) – Demonstration of a compact final focus.
1.Beam Tuning Simulation 2.IP Beam Position Stability 2-1 ) Magnet Vibration 2-2 ) IP position jitter subtraction for 2 nd bunch with FONT feedback 2-3.
1 Feedback On Nanosecond Timescales (FONT): Philip Burrows Neven Blaskovic, Douglas Bett*, Talitha Bromwich, Glenn Christian, Michael Davis, Colin Perry.
High Resolution Cavity BPM for ILC final focal system (IP-BPM) ILC2007/LCWS 2007 BDS, 2007/6/1 The University of Tokyo, KEK, Tohoku Gakuin University,
Discussion on Milestone and schedule Toshiyuki Okugi ATF2 commissioning meeting 1 / 7 / 2009.
ATF2 Javier Resta Lopez (JAI, Oxford University) for the FONT project group 5th ATF2 project meeting, KEK December 19-21, 2007.
Personal strategy for ATF2 beam operation in 2009 Toshiyuki OKUGI 2009 / 7 /22 ATF2 weekly meeting.
Technical Board ATF2 GM FF progress report A.Jeremie ATF2 GM System team: K.Artoos, C.Charrondière, A.Jeremie, J.Pfingstner (a lot of figures from him),
New IP chamber for ATF2 goal 2 Philip Bambade Laboratoire de l’Accélérateur Linéaire Université Paris 11, Orsay, France ATF2 Technical Review KEK, 3-4.
Energy Spectrometer for the ILC Alexey Lyapin University College London.
ATF2 beam commissioning status and beam time request Toshiyuki Okugi 2008 / 11 / 12 ATF2 Commissioning Meeting.
ATF-II Review by GDE Marc Ross, (SLAC) For GDE Project Managers: Nick Walker and Akira Yamamoto 24 January, th ATF2 Collaboration Meeting.
ATF DR Overview Introduction Low emittance history Present status S.Kuroda ( KEK ) GDE Review 3rd Apr.2013.
Feedback On Nanosecond Timescales (FONT): Robert Apsimon, Philip Burrows, Neven Blaskovic, Douglas Bett, Glenn Christian, Michael Davis, Davide Gamba,
Commissioning Status of Shintake Monitor (IP-BSM) T. Yamanaka, M. Oroku, Y. Yamaguchi, Y. Kamiya, S. Komamiya (Univ. of Tokyo), T. Okugi, N. Terunuma,
Development of a Low-latency, High-precision, Intra-train Beam Feedback System Based on Cavity Beam Position Monitors N. Blaskovic Kraljevic, D. R. Bett,
Highlights and discussion at LAL FKPPL & FJPPL “Toshiko Yuasa” workshop Philip Bambade Laboratoire de l’Accélérateur Linéaire Université Paris 11, Orsay,
Technical Board “issues” Philip Bambade Laboratoire de l’Accélérateur Linéaire Université Paris 11, Orsay, France ATF2 Technical Review KEK, 3-4 April.
ATF2 Accelerator Status and Plans for JFY 2014 runs N. Terunuma, KEK.
ATF2 Kiyoshi KUBO Accelerator Test Facility (ATF) at KEK ATF – Designed as a prototype of damping ring and injector of LC – Achieved low vertical.
BDS Andrei Seryi, Deepa Angal-Kalinin, Emmannual Tsesmelis, Rogelio Tomas, Andrea Latina, Daniel Schulte Detectors Civil engineering.
1 FONT R&D status Philip Burrows Douglas Bett, Neven Blaskovic, Glenn Christian, Michael Davis, Young Im Kim, Colin Perry John Adams Institute Oxford University.
Results on recent technology developments at ATF - Beam extraction study by a Fast Kicker - N. Terunuma, KEK LER11, Heraklion, Crete, Greece, 2011/Oct/5.
ATF2 Commissioning Toshiyuki Okugi 2008 / 7 /9 ATF2 beam commissioning meeting, KEK.
July 2, th ATF2 Project Meeting Philip Bambade, Andrei Seryi, Toshiaki Tauchi Summary for TB.
Global Design Effort Introduction and goals of the meeting Andrei Seryi, Toshiaki Tauchi Fifth ATF2 Project Meeting December 19-21, 2007.
1 Feedback On Nanosecond Timescales (FONT): Philip Burrows Neven Blaskovic, Douglas Bett*, Talitha Bromwich, Glenn Christian, Michael Davis, Colin Perry.
1 Feedback On Nanosecond Timescales (FONT): Philip Burrows Neven Blaskovic, Douglas Bett, Glenn Christian, Michael Davis, Young Im Kim, Colin Perry John.
IP instrumentation configuration for Autumn 2010 ATF2 runs Toshiyuki OKUGI, KEK 2010 / 7/ 1 10 th ATF2 project meeting.
Prospects of the ATF operation in FY2016 N. Terunuma, KEK 19 th ATF TB/SGC meeting Jan , LAL Orsay.
Beam Dynamics WG K. Kubo, N. Solyak, D. Schulte. Presentations –N. Solyak Coupler kick simulations update –N. Solyak CLIC BPM –A. Latina: Update on the.
ATF2 Tuning Summary Nov & Dec 2010 Glen White, SLAC 11 th ATF2 Project Meeting, SLAC Jan
ATF2 Report ALCW Kiyoshi KUBO, for ATF2 Collaboration.
Low Emittance Generation and Preservation K. Yokoya, D. Schulte.
1 ATF 2 Nanobpm (Q BPM) Electronics. Mark Slater: Cambridge Yury Kolomensky, Toyoko Orimoto: UCB Stewart Boogert, Steve Malton, Alexi Liapine: UCL Mike.
ATF2 Software Review LAL June SHORT SUMMARY - Philip Bambade ATF2 weekly meeting July
ATF hardware status - Orbit Stabilization T.Naito(KEK) ATF2 Project meeting Laboratoire de l'Accélérateur Linéaire (LAL) 1.Orbit oscillation.
Task Lists of ATF2 commissioning Toshiyuki Okugi ATF2 Project Meeting 12 / 17 / 2008.
ATF2 beam operation status Toshiyuki OKUGI, KEK The 9 th TB&SGC meeting KEK, 3-gokan Seminar Hall 2009/ 12/ 16.
Simulations - Beam dynamics in low emittance transport (LET: From the exit of Damping Ring) K. Kubo
Summary of Tuning, Corrections, and Commissioning ( Short summary of ATF2 meeting at SLAC in March 2007 ) and Hardware Issues for beam Tuning Toshiyuki.
Ground motion studies at ATF2 June 11, 2014 Orbit jitter source identification via ground motion studies at ATF2 (Results of the June run) Marcin Patecki,
Tuning Techniques And Operator Diagnostics for FACET at SLAC National Accelerator Laboratory Chris Melton SLAC Accelerator Operations.
1 Feedback On Nanosecond Timescales (FONT): Philip Burrows Neven Blaskovic, Douglas Bett, Glenn Christian, Michael Davis, Young Im Kim, Colin Perry John.
CERN, 27-Mar EuCARD NCLinac Task /3/2009.
Brief review of past studies on Wakefield ATF2 Proj. Mtg K.Kubo.
1 Experiments with pulse supplies and strip-lines at ATF, Plans for fast extraction kicker for ATF2 1. Fast Kicker R&D at ATF 2. Instrumentation at ATF.
IoP HEPP/APP annual meeting 2010 Feedback on Nanosecond Timescales: maintaining luminosity at future linear colliders Ben Constance John Adams Institute,
Wakefield effect in ATF2 Kiyoshi Kubo
Technical Board Summary Preliminary Philip Bambade Laboratoire de l’Accélérateur Linéaire Université Paris 11, Orsay, France ATF2 project meeting, Technical.
ATF2 Status Background for the installation planning of Collimator
ATF2 Status N.Terunuma, KEK
Fast Beam Collision Feedbacks for luminosity optimisation at next-generation lepton colliders Philip Burrows John Adams Institute Oxford University.
Special ATF Session - ATF/ATF2 day on 28th September -
Expected hardware status and Priority of the commissioning task
For Discussion Possible Beam Dynamics Issues in ILC downstream of Damping Ring LCWS2015 K. Kubo.
Presented by Douglas BETT on behalf of the ATF2 Collaboration
CLIC-ILC BDS & MDI work.
Summary of the ATF2 project meeting at LAL (Jan.13-15, 2016)
ATF2 review R. Tomas ATF2 review web:
Towards a ground motion orbit feed-forward at ATF2
Presentation transcript:

ATF2 Status and Plans CLIC January 2016

ATF2 FY2015 operational status ATF2 FY2015 hardware status ATF2 FY2015 R&D issues and challenges Beam tuning and low-beta optics Wakefields and beam orbit stabilization. High intensities issues IP-BPMs and nanobeam stabilization Background characterization International Collaboration Status and Future ATF2 FY2016 Prospects Outline CLIC January 2016

ATF2 FY2015 operational status CLIC January 2016 Several shifts were lost by failures but quickly/successfully fixed by the maintenance team. No long failures more than a week. The startup time is shorter compare to the past years, and is used for short R&Ds. Most of the R&Ds were done at ATF2 beamline. More than 80% of shifts were for ATF2 goal-1 and 2. Non-KEK colleagues could recover a primary beam by themselves and keep R&Ds especially on owl shifts. Overview of FY2015 operations: Total 142 shits from Apr–Dec 2015

ATF2 FY2015 operational status CLIC January 2016 Budgetary issue for ATF operation in FY2015 Electricity cost (beam time) is still the higher level, ATF was maintained mainly by KEK (twice cost since 2014) Maintenance budget is very limited. Lack of spare units especially for expensive ones as: Injection/extraction Kickers (new thyratrons) soon, LINAC klystrons (highly required in 2016), Cooling facility (repair when broken basis)

ATF2 FY2015 hardware status CLIC January 2016 Orbit stabilization Orbit oscillation in the DR due to the DR Cooling water temperature change Orbit drift in FF due to the DR air-conditioner Extraction kicker trouble ( ~ ) Study of a new proposal for the pulse stabilization of the extraction kicker

ATF2 FY2015 hardware status CLIC January 2016 Orbit stabilization The orbit oscillation in the DR due to the Cooling water temperature change was fixed by stabilizing the temperature. The orbit drift in FF was due to the temperature change of the DR air- conditioner. This temperature change also should be minimized. MB68R X-pos Mag Cooling water temp DR BPMs reading Feedback Kicker Amplitude : 12/15 18:00 – 12/16 01:00 Air Temperature: 12/15 18:00 – 12/16 01:00 DR tunnel Temp (1), (2), (3), (4), (5). Temp change < 1degC Horizontal ZH4X, ZH5X Vertical ZVFB1X, ZVFB2 X The strength of the orbit feedback correlated with the DR temp.

ATF2 FY2015 hardware status CLIC January 2016 Orbit stabilization The Extraction kicker trouble( ~ ) was fixed by replacing the thyratron heater feed through (2 spares in FY2016). The extraction kicker Power Supply modification was proposed to minimize the orbit jitter and to improve the maintenance. ch1(yellow) thyratron1 current ch2(blue) thyratron2 current

ATF2 FY2015 hardware status CLIC January 2016 New hardware installation Strengthen the ATF2 skew sextupoles (KEK) -under installation for next beam runs -shorten a pole gap and widen the dynamic range for a beam tuning. φ160  φ60 Air-core dipoles in EXT/FF (KEK) -a pair of vertical dipoles were successfully functioned in December run for slow orbit feedback and jitter studies. -a pair of horizontal dipoles will be installed before April.

ATF2 FY2015 hardware status CLIC January 2016 New hardware installation OTR/ODR system (RHUL/CERN) Installation will be done in February. Collimator system (IFIC/LAL) Shipping and installation planned in March Octupoles (CERN) Shipping and installation planned in Spring

ATF2 FY2015 R&D issues and challenges CLIC January 2016 Beam tuning and low-beta optics (M. Patecki CLIC 2016) Wakefields and High intensities (K. Kubo 19 th ATF2 Project Meeting, LAL January 2016) Beam orbit stabilization (D. Bett CLIC 2016) IP-BPMs and nanobeam stabilization (T. Tauchi, N. Blascovick T. Bromwich, S.Jang, S. Wallon 19 th ATF2 Project Meeting, LAL January 2016) Background characterization (N. Fuster Martinez CLIC 2016) 19 th ATF2 Project meeting

ATF2 FY2015 R&D issues and challenges CLIC January 2016 Wakefields and High-Intensity dependence Orbit change and beam size vs. Position of Wakefield sources Experiments and calculations are (almost) consistent Beam size intensity dependence with optimized wake source (on movers) positions Still not understood It seems mostly from dynamic effect: orbit jitter + wakefield Experimental data analysis so far can not show clear results. Need more data? IPBSM with 2-bunch feedback data should give more information. Orbit change and beam size vs. Position of Wakefield sources Effects of transverse wakefield in ILC will be much smaller than in ATF2, understanding of intensity dependence is important High energy, short bunch length Beam pipe aperture will be similar, but careful design (except collimators)

ATF2 FY2015 R&D issues and challenges CLIC January 2016 IP-BPMs and nanobeam stabilization

ATF2 FY2015 R&D issues and challenges CLIC January 2016 IP-BPMs and nanobeam stabilization Present status: BPM resolution : 27nm at beam intensity IP stabilization at 67nm ( → resolution of 47nm ) What are sources of the resolution limit ? electronics noise low beam intensity, e.g. poor calibration calibration, e.g. IQ tuning static signals only seen at the low Q IPBPMs ? could be "filtered out" by the narrow band C-band pass filter may be generated in the waveguide Measures recovery of Q at IPBPM-C by re-fabrication and indium shielding to see a correlation between the Q and the static signals finer adjustment of IQ angle or detailed calibration in the nanometer range

International Collaboration Status and Future CLIC January 2016 CERN Current and Future activities: Ground Motion feed-forward Small beam tuning Ultra-low betas (topic thesis M. Patecki) Long L* (topic thesis F. Plassard) Octupoles Beam-based alignment OTR/ODR CERN group consists of 5 senior physicists (part time, R. Tomas, A. Latina, M. Modena, T. Lefevre, E. Bravin), 3 postdocs (D. Bett, S. Mazzoni, R. Kieffer) and two PhD student (M. Patecki, until end 2016, F. Plassard 3 years). The group has support from mechanical engineering at CERN.

International Collaboration Status and Future CLIC January 2016 LAPP Current and Future activities: Ground Motion studies, vibration source identification and mitigation, contribution to final doublet support mechanics LAPP group consists of 1 senior physicist (part time, A. Jeremie). The group has support from mechanical engineering at LAPP.

International Collaboration Status and Future CLIC January 2016 IFIC Current and Future activities: Halo Collimation and Collimation Wakefiels studies in ATF2 (thesis topic for N. Fuster Martinez) IFIC group consists of one senior physicist (part time, A. Faus-Golfe) and one PhD student (N. Fuster Martinez, until end 2016). The group has support from mechanical engineering at IFIC and LAL.

International Collaboration Status and Future CLIC January 2016 LAL Current and Future activities: Diamond sensor and collimation for beam halo and background control (thesis topic for Renjun Yang, also support for Nuria Fuster's thesis) Continued support for IP-BPM mechanical / mover / alignment work in the context of Goal-2 (but no new student or postdoc on this topic at the moment) General support for Goal 1 and 2 (however, also no students or postdocs on these topics at present) LAL group consists of one senior physicist (part time, P. Bambade) and one postdoc (part time, until mid 2017, Viacheslav Kubytskyi). A new PhD student has also just started his PhD at LAL on ATF2 (Renjun Yang, 3 years). The group has support from mechanical engineering at LAL, also some limited electronics support (in the context of the diamond sensor R&D).

International Collaboration Status and Future CLIC January 2016 SLAC Current and Future activities: Ongoing R&D activities (combined funding for ILC and ATF2 until end 2017) Current hardware and software maintenance of: multi-OTR, BPMs, Extraction Kicker and FFS magnets SLAC group consists of 2 senior physicist (part time, G. White, D. McCormick). The group has support from mechanical engineering and electronics at SLAC.

International Collaboration Status and Future CLIC January 2016 JAI Current and Future activities: BPMs Beam Based Feedback systems JAI group consists of 5 senior physicist (part time, P. Burrows, C. Perry, L. Nevay, G. Christian, N. Blaskovic Kraljevic) and 2 PhD students (T. Bromwich, R. Ramjiawan). The group has support from mechanical engineering and electronics at JAI.

International Collaboration Status and Future CLIC January 2016 RHUL Current and Future activities: Background studies OTR/ODR RHUL group consists of 2 senior physicist (part time, S. Boogert. P. Karataev), 3 postdoc (J. Snuverink, K. Kruchinin, M. Bergamaschi). The group has support from mechanical engineering and electronics at RHUL.

International Collaboration Status and Future CLIC January 2016 KNU Current and Future activities: IP-BPMs KNU group consists of 1 postdoc (S. Jang). The group has support from mechanical engineering and electronics at KNU.

International Collaboration Status and Future CLIC January 2016 KEK-ATF Current and Future activities: Support in all R&D activities: IP-BSM, alignment, small beam tuning, wakefields, backgrounds…… Support in all the technical and operational aspects ATF group consists of a team of seniors physicists (N. Terunuma, T. Tauchi, K. Kubo, T. Okugi, T. Naito, S. Araki, S. Kuroda…. ) and students (Y. Kano…). The group has support from KEK technical and maintenance groups

International Collaboration Status and Future CLIC January 2016 The collaborators will maintain their contribution to ATF2 collaboration at the current level. Budgets approved for the next 3 years Cooperation and sharing of resources/ skills/ synergies with other groups in the ATF collaboration is essential given the limited resources Support from EU Project E-JADE (KEK, LAL, IFIC, LAPP, CERN, JAI) funds our travel and equipment The educational aspect is crucial for all collaborators (PhDs: 4 LAL, 3 IFIC, 8 JAI, 1 LAPP, 3 CERN, ?? KEK, 1 KNU)

ATF2 FY2016 Prospects CLIC January 2016 Background of budget decision for ATF2 FY2016 KEK will receive a little bit more than 2015 but will not be sufficient for the commissioning of SuperKEKB; i.e., highly prioritized on-going project. Electricity cost is still higher level (twice since 2014). KEK DG wish to slim down the projects because KEK has a lot of satellite projects. Of course, KEK has been leading the promotion of ILC but this promotion activity and R&D activity should be separately managed because of the budget. KEK DG request ATF/STF to focus on the R&D for ILC. It means we may face very little room for general accelerator R&D. We can/should show all of the plan at ATF are needed for ILC.

ATF2 FY2016 Prospects CLIC January 2016 Budgetary issue for ATF2 FY2016 Operational budget: Electricity charge + Maintenance We submitted estimation of the electricity in FY2016 to KEK about 21 weeks operation, same as the past standard. Assignment of the electricity charge for ATF will be fixed in early March. Spares of the key components should be prepared (LINAC Klystron, Kicker Thyratrons) We expect severe budget assignment then we should consider the trade off between a beam time and maintenance.

ATF2 FY2016 Prospects CLIC January 2016 Budgetary issue for ATF2 FY2016 Operational budget: Electricity charge + Maintenance We submitted estimation of the electricity in FY2016 to KEK about 21 weeks operation, same as the past standard. Assignment of the electricity charge for ATF will be fixed in early March. Spares of the key components should be prepared (LINAC Klystron, Kicker Thyratrons) We expect severe budget assignment then we should consider the trade off between a beam time and maintenance. Prospection

ATF2 FY2016 Prospects CLIC January 2016 History of ATF Beam Weeks Electricity cost became twice. CERN/CLIC supported 2 weeks. No beam for Jan-Mar. Apr-Dec: 11 weeks, Jan-Mar: 7 weeks are scheduled. 2016/Feb-Mar, evaluation and decision by KEK.

CLIC January 2016 Thanks for all the help and material