Status & schedule of ladder parts production Oct. 2, 2014 Koji Hara (KEK)

Slides:



Advertisements
Similar presentations
Seog Oh/ Duke University/June, 2003 TRT/ ATLAS week at CERN Duke Production Status.
Advertisements

A Low Mass On-chip Readout Scheme for Double-sided Silicon Strip Detectors 13th February 2013 C. Irmler, T. Bergauer, A. Frankenberger, M. Friedl, I. Gfall,
Belle-II Meeting Nov Nov Thomas Bergauer (HEPHY Vienna) Status of DSSD Sensors.
Milestones and Schedule of SVD Construction Markus Friedl (HEPHY Vienna) on behalf of the Belle II SVD Collaboration BPAC October 2012.
Summary of the SVD session 19 March 2009 T. Tsuboyama (KEK)
Construction and Status of the Origami Module Prototype C. Irmler HEPHY Vienna.
5. July 2010 Christian Irmler (HEPHY Vienna), Yoshiyuki Onuki (Tohoku University) 6” Origami Module and Front End Electronics 6 th Open Meeting of the.
US Tracker Group Status Sep. 1, 2005 J. Incandela For the US CMS Tracker Group.
M.Friedl, C.Irmler, M.Pernicka HEPHY Vienna
SVD Mechanics 21th B2GM Florian Buchsteiner (HEPHY Vienna)
18 November 2010 Immanuel Gfall (HEPHY Vienna) SVD Mechanics IDM.
26 April 2013 Immanuel Gfall (HEPHY Vienna) Belle II SVD Overview.
Noise and Capacitor M.Friedl, R.Thalmeier, H.Yin (HEPHY Vienna) 24 September 2015.
L. Greiner 1IPHC meeting – May 7, 2012 STAR HFT Plans for the next year A short report on HFT/PXL plans for post May 2012 TPC – Time Projection Chamber.
Origami Chip-on-Sensor Design: Progress and New Developments 19th September 2012 TWEPP 2012, C. Irmler (HEPHY Vienna) TWEPP 2012, Oxford University.
Concluding Summary WBS1.1.2 SCT Subsystem A. Seiden BNL March 2001.
Jigs and procedure for ladder assembly BelleIInote #8 6 th Feb 2012 Yoshiyuki Onuki University of Tokyo 1.
Construction and Test of the First Belle II SVD Ladder Implementing the Origami Chip-on-Sensor Design 29 Sept TWEPP 2015, C. Irmler (HEPHY Vienna)
18 July 2006A.Ciocio -SCTSG1 SCT Services Installation ID week full report (July 4) SCT Cables Web page
The Belle II Silicon Vertex Detector Florian Buchsteiner (HEPHY Vienna)
16/04/20031PNPI / LHCb Muon EDR Wire Pad Chambers PNPI design for regions R4 in Stations M2,M3,M4  4 gas gaps of 5mm±70µm;  Active area: 1224x252.8 mm².
1 DT critical items status: HVBoards Control and Trigger Boards Assembly in Torino fgasparini june 2004.
LNF activities on WPC Panels Construction of prototypes and layout Status of tooling Proto 0, open items, plan,...
Thermo-mechanical petal status Sergio Díez Cornell 23Jan 2015.
SVD Mechanics Markus Friedl (HEPHY Vienna) BPAC, 26 October 2015.
CDF Japan Meeting, Dec 13-14, Run2b Silicon Detector - Overview K. Hara U of Tsukuba Project Status Sensor Prototype: Delivery Testing at U Tsukuba.
18 March 2009 Thomas Bergauer Prototype batch of DSSD from commercial vendors & Proposal for SVD Layout HEPHY Vienna.
11 June 2015 Thomas Bergauer (HEPHY Vienna) Belle II SVD beam Test SPS 2015 SPS users meeting.
Construction and Status of the Origami Module Prototype C. Irmler, M. Friedl HEPHY Vienna.
DSSD update. 2Manfred Valentan, 3 rd Open Meeting of Belle27-9 July 2009 Outline DSSD design in Vienna: How it is done First test batch of SVD DSSDs Status.
PS Module Ron Lipton, Feb A bit of History During much of the conceptual design phase of the outer tracker we had focused on the “long barrel”
A.Cheremukhin (JINR, Dubna) CMS Preshower PRR, July 5-6, 2001, CERN1 Micro-module assembly -  -module elements - alignment of the silicon sensors to the.
Trigger efficicency on double tracks Trigger efficiency on isolated tracks Final results of the Trigger Test on the 25ns beam Bx NUMBER Fraction of Triggers.
Hybrid and Module Status 1. Hybrid Delivery First hybrids over-etched and shrunk due to changes in design and mistakes in manufacturing – Shrinkage for.
Origami and PA design 6 February 2012 Christian Irmler (HEPHY Vienna) 1 Common SVD-PXD Meeting.
Comments on ladder structure 5 Feb Toru Tsuboyama.
Shipping/Receiving concerning the BW/FW assemblies S.Bettarini/F. Forti.
2 Oct C. Irmler (HEPHY Vienna) BPAC Preparation and SVD Schedule 6 th Belle II VXD workshop.
Overview SVD 21 Jan C. Irmler (HEPHY Vienna) 7 th Belle II VXD Workshop, Prague.
PA and Origami Status and Plan Koji Hara (KEK) Jan. 21, 2015 (updated on Jan. 23) 7th Belle II VXD Workshop and 18th International Workshop on DEPFET Detectors.
Steinar Stapnes, LHCC June The ATLAS inner detector TRT endcap A+B TRT endcap C TRT barrel SCT barrel SCT endcap Pixels uWhole ID sits inside bore.
Ladder Mount R&D T. Tsuboyama (KEK) 2 Oct T. Tsuboyama (KEK) 2 Oct
Origami and Cooling 24th September 2012 C. Irmler (HEPHY Vienna) Joint PXD and SVD Meeting Göttingen.
Location of SVD Temperature and Humidity Monitors L.Vitale & L.Lanceri INFN & Univ. Trieste 6 th VXD Workshop, 02/10/2014 SVD parallel for discussion Sep.
1 Class-X BW/FW Subassemblies S. Bettarini for the Pisa Belle2-SVD group SVD Parallel Session VXD-Workshop Praga, 22 nd January 2015 OUTLINE Status/numbers.
PA and Origami Status and Plan Koji Hara (KEK) Jan. 21, th Belle II VXD Workshop and 18th International Workshop on DEPFET Detectors and Applications.
SVD QCG Report F.Forti. Outline Sep 09, 2015QCG Report, F.Forti2 view/Detector/SVD/SvdQCQAGrou p.
25th April 2013 C. Irmler (HEPHY), Y. Onuki (IPMU) Ladder Assembly Procedure Belle II – New Collaborators Meeting.
25 April 2013 Thomas Bergauer (HEPHY Vienna) Components and ladder quality control and testing procedures Belle II Vienna-Pisa meeting.
L5 Assembly 10 Sept C. Irmler (HEPHY Vienna) 8 th Belle II VXD Workshop OS5.905.
L5 Assembly Plans in Vienna 5 February 2013 Christian Irmler (HEPHY Vienna) 3 rd PXD/SVD Workshop Wetzlar, Germany.
SVD Status Markus Friedl (HEPHY Vienna) SVD-PXD Göttingen, 25 September 2012.
QCG Report Francesco Forti University and INFN, Pisa.
Electrical Tests of Modules and Ladders Markus Friedl (HEPHY Vienna) 2 October 2014.
24 September 2012 Immanuel Gfall (HEPHY Vienna) SVD Status of Mechanics PXD-SVD Meeting Göttingen.
24 September 2012 Immanuel Gfall (HEPHY Vienna) Annekathrin Frankenberger (HEPHY Vienna) SVD Status of Mechanics PXD-SVD Meeting Göttingen.
Schedule 24 September 2012 Christian Irmler (HEPHY Vienna) Joint PXD and SVD Meeting Göttingen.
Mechanical robustness & associated tension at the DSSD slant part connection Mar-5 th 2013 B2GM KEK S. Uozumi (KNU), T. Tsuboyama, N. Sato (KEK)
Silicon Vertex Detector Schedule 23 July 2012 Christian Irmler (HEPHY Vienna) 12 th Open Meeting of the Belle II Collaboration.
FADC/Hybrid cable production 21 Jan 2015 T. Tsuboyama.
Florian Buchsteiner (HEPHY Vienna)
9 September 2015 VXD Mechanics Summary Markus Friedl (HEPHY Vienna)
SVD Overview Christoph Schwanda Institute of High Energy Physics Austrian Academy of Sciences 8th Belle II VXD Workshop September 9-11, 2015 Trieste, ITALY.
Update on the SVD construction
7th Belle II VXD Workshop, Prague
Christoph Schwanda (HEPHY Vienna) For the Belle II SVD group
Katsuro Nakamura Sep. 10, 2015 VXD meeting
Origami, PA 2015 Sep. 10 Koji Hara (KEK).
Radiation Laboratory Meeting
Class B Ladder assembly
Presentation transcript:

Status & schedule of ladder parts production Oct. 2, 2014 Koji Hara (KEK)

Ladder Parts Ribs (L3-L6) Airex sheets L3 mount bridges BWD End mounts, APV covers, Kokeshi pins FWD end mounts (incl. SLM), APV covers, Kokeshi pins L4-L6 Hybrids L3 Hybrids Origame CE, -Z, +Z Pitch adapters Pipe clamps (already delivered) Sensors

Ribs (L3): already delivered to Melbourne Ribs (L4, L5, L6): re-production of CF sheets ongoing  followed by micro-waterjet-cutting  Already delivered to assembly sites Airex sheets (L4, L5, L6): Already delivered to IPMU

L3 mount bridges and spacers – 12 sets have been produced for Melbourne 8 BW, 11 FW are at Melbourne (4 BW, 1 FW are at KEK) – 8 sets (BW are mechanical sample) for DESY thermal mockup  brought from KEK in this workshop

BW End mounts, APV covers, Kokeshi-pins – 75 sets are produced 5 sets are sent to HEPHY for mockup study – 70 sets are at IPMU for L4,5,6 Ready to use for mockups Need to add an additional screw hole for grounding – New position given by Florian in this workshop – Additional 40 sets have been produced for DESY thermal mockup 10 sets brought in this workshop

FW dummy end mounts without SLM for mockup study – 30 sets of end mounts and Kokeshi-pins produced – 5 sets are sent to HEPHY – 10 L6 APV covers available, but no L4-5 APV cover FW end mounts with SLM – 120 sets have been produced including those for thermal mockup 70 sets with L4-5 APV guard 50 sets with L6 APV guard – 5 sets brought for HEPHY – 5 L L6 sets brought for thermal mockup

L3, L4-L6 FR4 Hybrid boards – 44% of L4/5/6 hybrids completed – 31% of L3 hybrids bonded, 12% tested and shipped

Pitch adapters 1-layer 3-row – All 10 types have been produced Class B samples also delivered – 10 /type/site good samples – Issues : Short found in “good” samples Pad widths of P3B1 pieces of sheet 1 is smaller than others – Final production will take 1.5 months + contract delay Verify the final specification Start making contract in Oct.-Nov. in the order of – 1. PF1,2/PB1,2 – 2. PA1,2 – 3. P3F1,2/P3B1,2

P3B1-3r.03-XX Other P3F/P3B

Short on P3F2-3r We have also found other suspicious samples

The short in P3F/B samples found last week end.  All P3F1,2 /P3B1,2 good samples have been returned to Tokai Denshi Answer received in Oct. 2 morning – “it is found short circuit test actually was not performed (!) because of the bad communication between Tokai Denshi and the company performing the test” In the previous production >1 year ago, it was. – Confirming if it is only P3F/B but also in all others Also asking possibility to reproduce other 8 types by their responsibility if the test has not been performed

Pitch adapter 2-layer – Samples of the initial production has been delivered 10 / type / site B-class samples are also delivered Delivery will be finished by June 23 – No plan to produce more

HPK L3 sensors – 24 good sensors produced, 21 at KEK 3 have been sent to Torieste and HEPHY for beam test and checks – 11 mechanical samples sent to Melbourne HPK large – 167 good sensors produced, 160 at KEK 7 sensors brought to Italy / HEPHY for check – mechanical samples 20 at HEPHY 1 at Pisa (+ 8 early test production sensors) at IPMU/KEK for L4, L6 and spares for L5 and FW/BW

Explanation of the excel file Column H: Assignment. Priority is determined with the radiation level. Better DSSDs should go to inner layers. Priorityposition Assignments TIFR/HEPHY/IPMU/Pisa Cumulative sum 1L4 barrel12+2/0/0/014 2L4 Backward0/0/0/ L5 Barrel0/28+4/0/060 4L6 barrel0/0/57+6/0123 5L5 backward0/0/0/ L6 backward0/0/0/ Total14/32/63/51160 Proposal 29 Sept Tsuboyama-san

Status of Trapezoidal sensors produced by Micron Micron Delivery Micron delivered 83 pcs in total –56 sensors (until summer) –3 mechanical samples –24 sensors on 15 th of September 2014 Sensors from all but last shipment have been fully tested (59 pcs.) and qualified –Stripscan either by Trieste of Vienna –Longterm stability tests performed on all Micron sensors using Vienna climate chamber 15Thomas Bergauer (HEPHY Vienna)19 June 2014 Thomas

Status of Trapezoidal sensors produced by Micron Delivery Status by now Thomas Bergauer (HEPHY Vienna)19 June 2014 ShipmentDelivered to CERN Number of sensors Strip scan done by Current location 12 Aug 132Micron & ViennaVienna (IPR) 24 Oct 134Micron & ViennaVienna (IPR) 39 Oct 137TriesteVienna 422 Oct 134TriesteVienna Vienna TriesteVienna Vienna (including replacements for rejects) to be doneTrieste Sum:80 (delivered)(ordered 60)13 rejected so far 16 Thomas

Status of Trapezoidal sensors produced by Micron Quality Sensors have been qualified in three Classes: –Class A: perfectly working: 30 pcs. –Class B: (working with some minor problems): –Class C: not working -> mechanical samples Summary of available sensors: –Class A: 30 pcs –Class B: 19 pcs (mostly due to scratches caused by testing in Vienna) –Class C: 10 pcs (including 3 mechanical samples delivered by Micron) –Not yet classified: 24 pcs. 17Thomas Bergauer (HEPHY Vienna)19 June 2014 Thomas

L3 parts availability 11 mechanical sensors at Melbourne Ribs delivered 8 sets of FW/BW bridges + spacers at Melbourne – More 4 sets are at KEK 3-PF1,PF2,PB1,PB2 – 3-row PAs mechanical samples at Melbourne – “good samples” returned to the company because of short problem – Final mass production to be completed in 2014 JFY Hybrid – Hybrid samples at Melbourne

FW/BW, L4-6 parts availability HPK mechanical sensors available at each site Micron mechanical samples available Ribs delivered BW end mounts available FW end mounts available Origami – Mechanical samples available (15 / type / site ) – 100% APV equipped, 70% wire-bonded – Crack problems PAs – 1-layer 3-row PF/PB/PA delivered – “good samples” returned to the company because of short problem – Final mass production to be completed in 2014 JFY Hybrid delivered Need to define # of parts for each site

Status of Produced Origami Assembled Origami : wire-bonded/APV glued/Produced at Taiyo total (141 ordered) 102/141/151 +Z (27 ordered) 24/27/31 CE(48 ordered) 33/48/51 -Z (66 ordered) 45/66/69 (assembly is suspended now) crack scan by CMM microscope – So far 22 Origamis checked  cracks found in all of them – Photographs of 512 pads are taken for each Origami PA0  damaged pads counted by eye-scan of them for 19 Origamis Electrical probe test of assembled Origami PA0, PA0 to be produced for repair Discussing Taiyo The company used by Tokai Denshi answers us they can do the test of PA0.

PA0 history and crack Cracks have been overlooked in Taiyo’s check (visual inspection) We have checked Origami samples we have Pre-production before 2013 Oct. – No cracks found Modification of glue between PA0 layers in 2013 oct. – Acrylic glue -> epoxy glue For radiation tolerance and to reduce curvature around PA0 Accompanying cover sheet under the glue was also changed – Cracks observed Final production in late 2013 – Found cracks in all samples we have checked so far 6th Belle II PXD/SVD workshop21

Fraction of pads with crack (crack on the pad itself excluded) Pad position

Improved PA0 production Taiyo is trying to improve the production process – New blanking mold – Different glue between PA0 and Origami Accompanied with different cover sheet on the glue Glue between PA0 top and bottom layer is kept same Taiyo made repaired Origami sample with new PA0 glued on existing PA0  Quality checked on Sep. 29 at KEK

Still find many cracks on both layers Also in the APV-side

Before After The cracks after the modification are small but still there  Sample returned to taiyo  Taiyo is checking  Need more iteration

Solution for PA0 problem Need to produce crack-free PA0 – Must be electrically tested Two possible (not impossible) ways a) Gluing new PA0 without cracks on existing Orgami PA0 b) Full reproduction of Origami 6th Belle II PXD/SVD workshop26

Crack-free PA0 production First trial at Taiyo was not successful – Smaller but many cracks – Taiyo is investigating the sample Need more iteration – 1 st trial done in a month  another trials  expect to 3 months for 3 trials 2 weeks for the final production Electrical test – The company used by the tokai denshi can do the test of PA0 – Cost is about 550 Yen/piece  ~90,000 pieces – < 2 weeks (machine program and test of 150 pieces)

Gluing option Gluing on existing PA0 – Precise positioning is doable with existing alignment holes – Gluing without bubble is the key issue Step between top and bottom layer – Selection of glue Two options – Gluing by Taiyo Acrylic-type glue sheet, hot pressed by small bars, avoiding touching APV and wires 1 month – Gluing by REPIC Using araldite, cured in room temperature for one day REPIC has experience of the similar situation 2 months – Gluing by REPIC is better

Taiyo glued sample Bubbles between pads but not under the pads

Full reproduction Need to procure parts  basically available – APV chips  available at CERN (diced), thinning possible (need to test to get the yield) – Connectors  500 connectors already bought by HEPHY Origami + PA0 full production at Taiyo Reflow soldering, APV gluing, APV wire bonding (control lines) at REPIC

Rough Cost and Delay Estimation Crack-free PA0 production 4 months Gluing option : 2 months – Expect Taiyo + REPIC to pay by themselves Taiyo already showed their will do so, for gluing option at Taiyo Additional electrical test ~ 90,000 yen  payable Full reproduction option : 6 months – Origami + PA0 production + assembling parts + bonding – Origami assembly : 25 M JPY Some of them must be paied by Taiyo + REPIC – APV cost (2500 chips) : 5 M JPY (chip 4.3M, thinning 0.7M)

The quality of DSSD is evaluated (i) Bias current at 200 V ( for the long-term stability and radiation tolerance) (ii) Number of AC-coupling and aluminum-trace failures (Preventing the punch-through current flowing into APV25, especially after installation) (iii) Number of implant errors on the p side (DC measurement) The formula is shown below 29 Sept. 2014

The quality of DSSD is evaluated e) Then I assigned which DSSD goes to each site. Better DSSDs are assigned in the inner layers because of the higher radiation level. f) In order to distribute enough numbers of DSSDs to each site, I included the DSSDs diced with saw, not with laser. g) DSSDs with serial number less than 64 and are treated as R&D DSSD. 29 Sept. 2014

Explanation of the excel file Column A-E: Bar code, batch, delivery date. Column F: The present site where the DSSD is stocked. Column G: Quality index – Q=(10-Ib(200V))*(60-P_badstrips)*(10-P_couplingerror)(10- Ncouplingerror) – Q>0: The quality is acceptable. – Q==0: The quality is quite poor or the DSSD has been used or lost already. – 0>Q>-100 (Calculation: Q=Q-100 for ID<64.) These DSSDs have been distributed already for tests and R&D. The DSSDs with 0>Q>-50 are good sensors. though they were produced in the early stage. – Q=-100: quite poor quality or unusable DSSD with ID<64 29 Sept. 2014