25 June 2015 1 EHN1 civil engineering project status (MAY) Summary: Updating of the activities carried out on-site (Done) in MAY List activities on going.

Slides:



Advertisements
Similar presentations
Cairo Metro Line3 / Medinah Car Park II
Advertisements

Bridge over BNSF Railroad 7 km East of Windham - East Bridge Replacement Project Using Accelerated Bridge Construction.
Michael Swinford Bechtel International Project Director, Autostrada Transilvania Friday 22 nd October 2010 Albanian Motorway Project A New Direction.
CONSTRUCTION OF SOIL NAILING WALLS
Project Managers Update Roy Preece Particle Physics Department, STFC MICE Video Conference, 18 th September 2014.
Update of Downtown Rail Improvements DFWI & Chamber Stakeholders February 26, 2014 Alonzo Liñán, PE, PTOE City of Fort Worth.
1 BROOKHAVEN SCIENCE ASSOCIATES Central Chilled Water Facility – Phase II Alan Raphael MPO Project Manager CFAC Committee Review November 9, 2009 Sub-basement/Pipe.
CENF – Civil Engineering Extension B887 CERN: An accelerator complex unique in the world -Prevessin site complex- -EHN1 Extension Area- EHN1 Extension.
Industry information day INDUSTRY INFORMATION DAY Assembly & Installation Laurent Schmieder Buildings Infrastructure and Power Supplies Project.
VRVS, Jan. 2006CERN AB-ATB1 Safety Review Solenoid & Cryogenics CERN AB-ATB VRVS session, Jan
Engineering H193 - Team Project Spring Quarter 2003 P. 1 Laboratory Quiz, Guidelines for Final Report Draft, Performance Test on Friday Week 5 Day 2.
Jess Albino FAC CF April 16, 2007 Meeting of the LCLS Facilities Advisory Committee LCLS Conventional Facilities Jess.
Jess Albino Facility Advisory October 29, 2007 FACILITY ADVISORY COMMITTEE PLENARY CONVENTIONAL FACILITIES UPDATE October.
Status of IPBSM Improvement N. Terunuma, KEK 2012/July/13 ATF2 Weekly Meeting.
John Osborne GS/SE March 2013
DELIVERY PROGRAMME Ian Hardwick Head of Engineering - Gallagher 28th January 2015.
Broadway Street Viaduct Improvement, Pre-Load Testing and Geotech Report Workshop Consultant Presentation Iowa DOT 2 nd April 2007.
Activities Status and Plan for the week D. Giugni / INFN Milano D. Giugni Monday Meeting
Latest Advancements in Instrumentation, Monitoring and QA/QC Techniques for Deep Excavation Support Systems: Al Hilal Project, Abu Dhabi – A Case History.
19 February Summary: Updating on the activities completed (Done) since the last meeting List activities on going (Next steps) and related Actions.
EN-CV status EHN1 Extension Project Jérôme Rodary EN-CV-PJ 2015/08/06.
09 July EHN1 civil engineering project status (JUNE) Summary: Updating of the activities carried out on-site (Done) in JUNE List activities on going.
06 August EHN1 civil engineering project status (JULY) Summary: Updating of the activities carried out on-site (Done) in JULY List activities on.
GIF in EHN1- layout, construction and schedule Adrian Fabich, EN-MEF-LE GIF users meeting, 12 th February 2014.
Status of Radiation Protection studies in support of ELENA R. Froeschl and J. Vollaire DGS-RP-AS.
CNGS PROJECT STATUS D.Autiero 21/5/2003 General status 2003 Project review CNGS upgrade.
Progress report Collaboration meeting 23-SEP-2009
CENF – Civil Engineering Extension B887 Status – 02 October 2014 Done: (1/2) Preliminary civil engineering drawing and Functional specification approved.
MWSS Diatomite 21S Weekly Update Chevron Reporting Period: 6/29/2015 – 7/5/2015.
R2E Mitigation Project P5 Relocation Options - Discussion R2E Mitigation Project CMS Relocation Options Towards An R2E Baseline 1 M. Brugger for the R2E.
22 October Summary: Updating of the activities carried out on-site (Done) in SEPTEMBER List activities on going (Next steps) and scheduled for OCTOBER.
15 January Extension of Building Neutrino Platform General Meetings N.Lopez – M.Manfredi EHN1 civil engineering project status Summary: Updating.
CENF – Civil Engineering Extension B887 Status – 18 September 2014 Done: (1/2) Preliminary civil engineering drawing and Functional specification approved.
General Infrastructures Services Department Civil Engineering planning for LSS4 Option, presented at review workshop 30/7/ months Planning and Resources:
February 14, Comprehensive Review B. Schmidt Outline: Status and overview of activities: –Platforms and staircases –Muon Filters and beam plugs.
MDI 9 th Meeting - 22 nd January 2016 FCC Experimental Caverns - Feasibility and Excavation C. Cook (GS), J. Osborne (GS),
CENF meeting 5 th February STATUS CE engineering contract running : – phase 1 : tender drawings – phase 2 : execution drawings – Phase 3 (option)
Survey Meeting John Osborne, CERN 8 February 2016
R2E Mitigation Project Status Report 2 nd R2E Committee Meeting R2E Project Report.
EN-CV Progress EHN1 Extension Project Jérôme Rodary EN-CV-PJ 2016/01/21.
EHN1 – EN/EL Progress update J. Devine G. Gross 11/02/16.
HiRadMat : Coordination meeting 02 October S. Evrard 1 News from project team General information : access,... PR532 repair : plans Existing services.
19 February Extension of Building Neutrino Platform General Meetings N.Lopez – M.Manfredi EHN1 civil engineering project status Summary: Updating.
Town of East Greenbush Waste Water Treatment Plant Project Monthly Update – September 2014.
SANKALCHAND PATEL COLLEGE OF ENGINEERING,
WP 17.1 Civil Engineering Platform height / vs option Status on M. Manfredi on behalf of WP17.1 team.
Infrastructure EHN1 extension Lau Gatignon, 7 March 2016.
21 January Summary: Updating of the activities carried out on-site (Done) in DEC + ½JAN List activities on going (Next steps) and scheduled till.
10 December Summary: Updating of the activities carried out on-site (Done) in NOVEMBER List activities on going (Next steps) and scheduled for DECEMBER.
WP 17.1 Civil Engineering Point 1 - Networks LS2 COMMITTEE – CERN – Pieter Mattelaer (SMB-DI)
EN-CV Progress EHN1 Extension Project Jérôme Rodary EN-CV-PJ 2016/01/14.
FCC Underground Infrastructure
Special Mention: Main Gymnasium Second Floor East: Technically Inaccessible Entrance Problems
Tunnel Cross Section Studies
CRG-TM: LS1 projects review
CE Status: Activities executed until 03/08 and ongoing
EHN1: CE Integration process updating
Special LS1 day on 12 June 2012, EDMS:
CLIC Civil Engineering Update
Minuteman Vocational Technical Regional High School Progress
US 50 SLOPE STABILIZATION PROJECT
اصول گودبرداری و ایمن سازی
Wellborn Underpass Update
API 16TR2 now 16TR1 June 2017 Shear Ram Performance Test Protocol
Reedy River Basin Sewer Tunnel Project Update
Experimental Areas – LS2 planning
Construction Considerations
A133 IPSWICH ROAD SCHEME COMMUNICATION UPDATE ( )
FCC Week 2019 Civil Engineering Summary
eSPS 2nd CDR meeting – 17th June 2019
Presentation transcript:

25 June EHN1 civil engineering project status (MAY) Summary: Updating of the activities carried out on-site (Done) in MAY List activities on going (Next steps) and scheduled for JUNE Final consideration Extension of Building th EHN1 Extension Integration Meeting N.Lopez – M.Manfredi

(1) MICRO PILES Vertical & inclined drilling along TT85: (100% completed) EHN1 civil engineering project status (MAY) Crown beam execution: (50% completed). Remains Type 3 to be done Done (1/3): 25 June Extension of Building th EHN1 Extension Integration Meeting N.Lopez – M.Manfredi

(2) DIAPHRAGM WALLS -73 panels- Execution EAST side: (88% completed) EHN1 civil engineering project status (MAY) Execution SOUTH/WEST side: (0% completed) Done (2/3): 25 June Guide walls allowing DW excavation: (100% completed) Execution NORTH/WEST side: (20% completed) ~46% TOTAL PANELS EAST N/W S/W Extension of Building th EHN1 Extension Integration Meeting N.Lopez – M.Manfredi

Done (3/3): (3) TECHNICAL GALLERY -70 meters- EHN1 civil engineering project status (MAY) Earthworks: (50% completed). Remains Type 3 to be done Execution TG: (25% completed). Type 2, facing TT85 enlargement Backfilling: (0% completed) 25 June Extension of Building th EHN1 Extension Integration Meeting N.Lopez – M.Manfredi

Next Steps: Activities scheduled for June (1) MP: Crown beam completion in Type 3 part (2) DW: Advancement on panels execution side S/W+N/W. Excavation up to crown beam level EAST side. Ties test and tensioning (3) TG: Type 3 part. Earthworks and execution of the slab system EHN1 civil engineering project status (MAY) 25 June /06/2015 Extension of Building th EHN1 Extension Integration Meeting N.Lopez – M.Manfredi

Final Consideration: -Approx. 2 weeks of delay for the DWs execution from the latest long-term schedule given -New contractual frozen-long-term schedule will be prepared by Contractor. -Execution of TG-Type 2, in time. Backfilling foreseen during 1 st week of June. -Beam operation in TT85 can restart. RP safety separation (5.5m) respected. -CE Handover unchanged for the moment (Jul-2016) -Next status of the works end-June. EHN1 civil engineering project status (MAY) 25 June Extension of Building th EHN1 Extension Integration Meeting N.Lopez – M.Manfredi