1 PFP IPDR 2010/6/14 - 16 Particles and Fields Package (PFP) Instrument Preliminary Design Review Integration & Test David Curtis, PF Package Manager.

Slides:



Advertisements
Similar presentations
GLAST LAT ProjectLAT Engineering Meeting, April 1, 2003 GLAST Large Area Telescope: Performance & Safety Assurance Darren S. Marsh Stanford Linear Accelerator.
Advertisements

STEREO IMPACT Preliminary Design Review 2001-September 11,12 David Curtis1 IMPACT Project Overview.
1 PFP MSR, 8/21/2012 Particles and Fields Package Monthly Status Review (MSR) August 21, 2012 Dave Curtis, PFP PM.
MAVEN CDR May 23-25, 2011 Particles and Fields Package Pre-Environmental Review May , 2012 Flight Software Peter R. Harvey Mars Atmosphere and Volatile.
THEMIS INSTRUMENT PER 1 UCB, May, 2005 EMC / Mag Instrument Test Plan & Results Michael Ludlam University of California - Berkeley.
GoetzFIELDS iPDR – I&T SPP/FIELDS Integration and Test Preliminary Design Review Keith Goetz University of Minnesota 1.
THEMIS Mission CDRInstrument I&T 1 UCB, June , 2004 Instrument Integration and Test Rick Sterling / Sharon Jelinsky University of California – Berkeley.
THEMIS Instrument CDR 1 UCB, April 19-20, 2004 Integration and Test Critical Design Review Rick Sterling University of California – Berkeley Thm_CDR_IT_Revc.
NASA’s Goddard Space Flight Center LRO Integration and Test Joanne Baker GSFC Code 568 August 16-17, 2005.
THEMIS-SCM THM – SCM – CDR – 08-April-2004 in Velizy
18-1 MAVEN IPER May 22-23, 2012 Particles and Fields Package Pre-Environmental Review May , Package Dave Curtis, PFP Package Manager Mars.
1 PFP MSR, 11/17/2009 Particles and Fields Package Monthly Status Review (MSR) November 17, 2009 Dave Curtis, PFP PM.
THEMIS Instrument Suite PERSuite T-V- 1 UCB, May 2, 2005 THEMIS Instrument Suite Thermal Vac Test Rick Sterling University of California, Berkeley.
25-1 MAVEN IPSR October 30,31, 2012 Particles and Fields Package Pre-Ship Review October 30,31, : SMA Jorg Fischer, MAM Mars Atmosphere and Volatile.
RBSP Radiation Belt Storm Probes RBSP Radiation Belt Storm Probes RBSP/EFW I-PER 21 January EFW Test Plan Michael Ludlam Space Sciences Laboratory.
THEMIS Instrument CDR 1 UCB, April 19-20, 2004 THEMIS Electric Field Instrument Fabrication, Integration, and Testing.
THEMIS Instrument CDR(1) UCB, April 19 & 20, 2004 Mission Assurance Critical Design Review Ron Jackson University of California - Berkeley.
GLAST LAT ProjectI&T&C Pre PDR Presentation– Oct. 2, I&T&C Organization Chart I&T&C Manager Elliott Bloom WBS I&T Engineer B. Grist WBS
GoetzFIELDS iCDR – I&T Solar Probe Plus – FIELDS Integration and Testing Instrument CDR Keith Goetz University of Minnesota 1.
1 PFP IPDR 2010/6/ Particles and Fields Package (PFP) Instrument Preliminary Design Review Safety and Mission Assurance Jorg Fischer, PFP SMA Manager.
RBSP Radiation Belt Storm Probes RBSP Radiation Belt Storm Probes RBSP/EFW Boom PER 30 June RBSP EFW Spin Plane Booms Greg Dalton Space Sciences.
24-1 MAVEN IPSR October 30,31, 2012 Particles and Fields Package Pre-Ship Review October 30,31, : ATLO Support Dave Curtis Mars Atmosphere and Volatile.
1 PFP IPDR 2010/6/ Particles and Fields Package (PFP) Instrument Preliminary Design Review System Engineering David Curtis, PF Package Manager.
THEMIS Mission PDR/CAR 1 UCB, November 12-14, 2003 Instrument Integration & Test Dr. Ellen Taylor University of California - Berkeley.
THEMIS Instrument FM2/FM3 PERSystems- 1 Teleconference 8/30/2005 THEMIS Instrument FM2/3 Pre-Environmental Review System Overview Ellen Taylor University.
MAVEN CDR May 23-25, 2011 Particles and Fields Package Critical Design Review May , 2011 Integration and Test Dave Curtis PFP Package Manager Mars.
PFP Instrument Status All PFP Instruments Except SWEA have been delivered, integrated, and tested; supporting environmental tests Issues: –EUV alignment.
RBSP Radiation Belt Storm Probes RBSP Radiation Belt Storm Probes RBSP/EFW I-PER 21 January EFW Overview and Status Keith Goetz University of Minnesota.
THEMIS Instrument FM2/FM3 PEREnvironments- 1 Teleconference 8/30/2005 THEMIS Instrument FM2/3 Pre-Environmental Review Environments Jeremy McCauley University.
1 SWEA pre-CDR Peer Review Particles and Fields Package (PFP) SWEA pre-CDR Peer Review Integration and Test 2011 March 29 Dave Mitchell.
STEREO IMPACT Critical Design Review 2002 November 20,21,22 Acuña1 MAGNETOMETER (MAG) M. H. Acuña NASA/GSFC Laboratory for Extraterrestrial Physics.
Solar Probe Plus A NASA Mission to Touch the Sun March 2015 Instrument Suite Name Presenter's Name.
Solar Probe Plus Fluxgate Magnetometer QSR – Oct SPF MAG Quarterly Report – Oct 2014 The MAG EM1 (EQM) (board and frame at right) was successfully.
Monthly Status Review Wednesday, January 18, 2012 LPW/EUV Jim Westfall PM & Will Thompson SE Laboratory for Atmospheric and Space Physics University of.
THEMIS INSTRUMENT CDR Peer ReviewSYSTEM- 1 UCB, April 19, 2004 TITLE: Test Flow RFA CODE: UCB-10 REQUESTED BY: Preble SPECIFIC REQUEST: We recommend that.
RBSP Radiation Belt Storm Probes RBSP Radiation Belt Storm Probes RBSP-EFW SMA I-CDR RBSP EFW SMA Safety and Mission Assurance Instrument -
FM1 Instrument Suite Pre-Ship Review (PSR)INT- 1 UCB September 21, 2005 THEMIS FM1 INSTRUMENT SUITE PRE-SHIP REVIEW (PSR) INTEGRATION AND TEST PLANS Jeremy.
June 16, 2015SPP/FIELDS SOC CDR: Integration & Test SPP/FIELDS Integration and Test SOC Critical Design Review Keith Goetz University of Minnesota
10-1 MAVEN IPSR October 30,31, 2012 Particles and Fields Package Pre-Ship Review October 30,31, : EMC Dave Curtis Mars Atmosphere and Volatile EvolutioN.
FM2/FM3 PSR FM4/FM5 PERSCM - 1UCB, November 10, 2005 THEMIS FM2/FM3 INSTRUMENT SUITE PRE-SHIP REVIEW (PSR) THEMIS FM4/FM5 INSTRUMENT SUITE PRE- ENVIRONMENTAL.
15-1 MAVEN IPER May 22-23, 2012 Particles and Fields Package Pre-Environmental Review May , SWIA (Solar Wind Ion Analyzer) J.S. Halekas.
TRIO-CINEMA 1 UCB, 2/08/2010 Integration and Test Program Dave Curtis UCB/SSL Space Sciences Laboratory University of California, Berkeley.
13-1 MAVEN PFP ICDR, May 23 – 25, 2011 Particles and Fields Package Critical Design Review May , 2011 GSE Timothy Quinn.
THEMIS Instrument CDR 1 UCB, April 19-20, 2004 EFI Preamp Sensor G.T. Delory, A. Hull, D. Schickele, J. Bonnell & The EFI Team University of California.
4-1 MAVEN IPER May 22-23, 2012 Particles and Fields Package Pre-Environmental Review May , Verification Dave Curtis, PFP Package Manager.
March 28, 2011 MAVEN SWEA instrument Pre-CDR Peer IRAP March 28-29, IRAP Management MAVEN SWEA Instrument Pre-CDR Peer Review IRAP, March.
1 PFP Team Meeting Particles and Fields Package Weekly Team Meeting, SSL April Dave Curtis, PFP PM.
RBSP Radiation Belt Storm Probes RBSP Radiation Belt Storm Probes RBSP/EFW I-PER 21 January EFW Systems Engineering Michael Ludlam Space Sciences.
FM4/FM5 IPSRSYS - 1 UCB, May 5, 2006 THEMIS INSTRUMENT SUITE FM4/FM5 PRE-SHIP REVIEW SYSTEM OVERVIEW Ellen Taylor University of California - Berkeley.
20-1 MAVEN iPSR Oct 30-31, 2012 Particles and Fields Package Pre-Ship Review October 30-31, PFDPU D. Gordon, W. Donakowski & PFDPU Team Mars.
1 SWEA pre-CDR Peer Review Particles and Fields Package (PFP) SWEA pre-CDR Peer Review Integration with PFP, Qualification, ATLO 2011 March 28 Dave Curtis.
RBSP Radiation Belt Storm Probes RBSP Radiation Belt Storm Probes Sept 30 – Oct RBSP EFW ICDR1 Integration and Test Michael Ludlam (EFW Systems Engineer)
MAVEN-SWEA Assembly, Integration & Test (AIT) Contents AIT: CESR Team Facilities Main subcontractors Applicable documents AIT documentation Cleanliness.
THEMIS-SCM SCM – OVERALL RESSOURCES – STATUS versus REQUIREMENTS ItemSpecificationStatus Sensor Bandwith Sensor Sensitivity Up to 4 kHz 1 pT/√Hz at 10.
FIELDS MEP Thermal Vacuum Cycling iPER
Particles and Fields Package (PFP) SWEA Pre-CDR Peer Review
Gayle K. Martin November 14, 2016
(EFW Systems Engineer) University of California, Berkeley
Agenda. Solar Probe Plus FIELDS Main Electronics Package iPER Agenda Feb 2, 2017.
Solar Probe Plus – FIELDS Main Electronics Package
Mars Atmosphere and Volatile EvolutioN (MAVEN) Mission
Solar Probe Plus – FIELDS Verification Instrument mini-PER (V5)
THEMIS INSTRUMENT SUITE
FIELDS SCM Thermal iPER
Solar Probe Plus FIELDS Main Electronics Package iPER EMC Feb 2, 2017
Mars Atmosphere and Volatile EvolutioN (MAVEN) Mission
Particles and Fields Package Quarterly Status Review (QSR)
0.0 Instrument Suite Name Presenter’s name
Integration and Test Organization Chart
GLAST Large Area Telescope
Presentation transcript:

1 PFP IPDR 2010/6/ Particles and Fields Package (PFP) Instrument Preliminary Design Review Integration & Test David Curtis, PF Package Manager

2 PFP IPDR 2010/6/ PFP Block Diagram 10cm

3 PFP IPDR 2010/6/ Integration and Test Plan MAVEN_PF_SYS_0022 I&T Plan submitted to Project –Matches up with PFP Verification & Validation Plan Philosophy: –Requirements are verified as early as possible at a low level Verifies subsystems, Retires risk –Requirements are verified at the highest level of assembly possible –Identify requirements which cannot be verified at a system level and ensure they are verified at the lower level before integrating –Maintain flexibility in test sequencing to maintain schedule Full set of Protoflight level tests on FM Typical Test Levels: –Subassembly (circuit board, mechanism): functional –Component: functional, mass properties, vibration, TV, magnetics, deployments –Instrument: functional, calibration, interface –Package: functional, EMC, Package Self-compatibility, interface

4 PFP IPDR 2010/6/ Integration and Test Flow

5 PFP IPDR 2010/6/ Environmental Test Flow

6 PFP IPDR 2010/6/ Environmental Verification Matrix

7 PFP IPDR 2010/6/ MAG I&T MAG is fabricated at GSFC MAG will be functionally tested, calibrated, and the sensor vibrated at GSFC –Using SSL-provided PFDPU simulator EGSE MAG will be delivered to SSL and the electronics will be integrated into the PFDPU –Followed by functional testing to verify performance not degraded Following Suite I&T and EMC tests, MAG sensor Thermal Vac will take place at SSL –With PFDPU outside the chamber

8 PFP IPDR 2010/6/ SEP I&T Instrument fabricated at SSL –Board level functional testing –Attenuator functional testing –SSD test, Select –Magnets test, select –Instrument integration Instrument bench CPT –Uses radiation source –Uses PFDPU Simulator EGSE Collimator scattered light test Instrument Calibrated –Existing automated calibration facility –End-to-End test SEP electronics integrated into the PFDPU –Followed by functional testing to verify performance not degraded Following Suite I&T and EMC tests: –Magnetics Screening –Vibration (near by subcontractor facility) –Thermal Vac

9 PFP IPDR 2010/6/ LPW / EUV I&T LPW Booms and Preamps fabricated at SSL –Preamps will be thermal vac tested separately before integration due to the extended temperature range EUV sensor and LPW electronics fabricated at LASP –Board level functional using SSL-provided PFDPU simulator EGSE –EUV calibration testing LPW electronics integrated into the PFDPU –Followed by functional testing to verify performance not degraded Following Suite I&T and EMC tests: –LPW boom & EUV Magnetics Screening –LPW Boom & EUV Vibration (near by subcontractor facility) –LPW Boom & EUV Thermal Vac –EUV environments at LASP, LPW Boom at SSL

10 PFP IPDR 2010/6/ LPW Boom Deployments Boom deployment testing takes place at the component level (LPW). A minimum of 2 full deployments will take place on each unit prior to the start of the environmental test program. In addition, during component level thermal vacuum tests, there will be one deployment at hot and one at cold. –whip deployment must be tested in a subsystem-level thermal vac Prior to LPW component integration Chamber and GSE cannot support both whip and stacer deployment at the same time LPW Boom cannot be deployed at the Spacecraft level –Difficulty G-negating deployment safely –During functional tests at the spacecraft level, actuator simulators can be used to verify the ability of the system to run the deployment.

11 PFP IPDR 2010/6/ STATIC, SWIA I&T Instrument fabricated at SSL –Board level functional testing –MCP test –Instrument integration Instrument bench CPT –No high voltage –Uses internal test pulser –Uses PFDPU Simulator EGSE Instrument calibrated at SSL –New SWIA/STATIC automated calibration facility –End-to-End test Following Suite I&T and EMC tests: –Magnetics Screening –Vibration (near by subcontractor facility) –Thermal Vac

12 PFP IPDR 2010/6/ SWEA I&T SWEA Analyzer if fabricated in CESR (France) –Board level functional testing –MCP test –Instrument integration Instrument calibrated at CESR –Existing calibration facility –End-to-End test Analyzer delivered to SSL Digital Electronics & LVPS fabricated at SSL –Board level functional tests Instrument is integrated at SSL –Bench CPT using PFDPU Simulator EGSE Instrument calibrations at SSL –Existing calibration facility –Subset of CESR tests to ensure system functionality Following Suite I&T and EMC tests: –Magnetics Screening –Vibration (near by subcontractor facility) –Thermal Vac

13 PFP IPDR 2010/6/ PFDPU I&T PFDPU electronics (excluding instrument electronics) fabricated at SSL –Board level functional tests –Uses Instrument Simulator GSE, Spacecraft Simulator GSE PFDPU integrated & tested –Install Acceptance-tested Flight Software Integrate Instrument Electronics –Integrated PFDPU CPT Following Suite I&T and EMC tests: –Magnetics Screening –Vibration (near by subcontractor facility) –Thermal Vac

14 PFP IPDR 2010/6/ Package I&T The PFDPU is integrated (DCB, REG, IIB, MAG, SEP, LPW electronics) –Functional test to verify interfaces and compatibility The remaining instruments are integrated –SWEA, SWIA, STATIC A baseline CPT test is performed A self-compatibility test is performed –Verify instruments don’t interfere with each other Pre Environmental Review EMC testing is completed at the Package level –RE, RS, CE, CS, Transients, Inrush –Flight or flight like harnesses –Near-by subcontractor facility –Instruments bagged and purged Remaining environments are done at the Component level Final pre-delivery package CPT –STATIC may be tested and delivered separately as it is needed first at LM

15 PFP IPDR 2010/6/ Component Environmental Tests Magnetics Screening –Simple SSL facility – measures dipole magnitude, AC & DC Vibration –Nearby subcontractor –Sine, Random per ERD levels –Structural Loads (Sine Burst) – TBR pending analysis –Instruments bagged Thermal Balance / Thermal Vac –SSL Facilities (5 chambers available with various configurations) –Thermal Balance depending on results of thermal analysis –8 cycles per ERD and GEVS to predicts/AFT +/-10C –Nominally separate due to different environments But may consider combining some tests if ranges compatible –Last cycle followed by bakeout with TQCM

16 PFP IPDR 2010/6/ Thermal Test Profile

17 PFP IPDR 2010/6/ SSL Integration and Test Facilities ‘Snout’ TVac Chamber (LPW deploy) Cleanroom (with 5 THEMIS probes) Magnetics Screening StationCalibration Chamber

18 PFP IPDR 2010/6/ Contamination Control PFP instruments shall be assembled in clean room facilities –Sensitive detectors (SWEA, SWIA, STATIC, SEP, EUV) shall be assembled on flow benches –Components will be bagged when not in clean room facilities LN2 boil-off shall be used to purge the instruments –SWEA, SWIA, STATIC, SEP, EUV –Limited times off purge Instruments shall be maintained at VC-HS levels –cleaned with IPA by PFP personnel

19 PFP IPDR 2010/6/ Performance Tests Comprehensive Performance Test (CPT) covers all functions and modes of operation to the extent possible Limited Performance Test (LPT) is a subset of CPT covering representative modes and functions in a limited time –No external stimulus Provides repeatable functional tests for use throughout I&T and ATLO –Some adaptation required at different levels of assembly; instrument, package, spacecraft Provides data for performance trending

20 PFP IPDR 2010/6/ Integration and Test Procedures Each test shall be documented by a Test Procedure –Test procedure shall identify L3 requirements to be verified by the test –Test procedure shall include pass/fail criteria –System Engineer, QA, Subsystem lead to sign off on proc before use –System Engineer, QA to sign off on completed as-run proc –QA to ensure Red-lines to be transferred into proc before next use Each completed test to be documented by a Test Report –EM and subassembly test reports may be a combination of the as-run proc and lab notebook –System Engineer to sign off on test reports, and determine if test adequately verifies associated requirements Discrepancies found during tests to be documented in a Problem Failure Report (PFR) –Starting with first functional tests at flight subassembly level –Includes any problem (including software) not immediately identified as a test setup or operator problem which cannot stress the flight article –QA will track PFRs to closure with concurrence of the Failure Review Board –Waivers by Project CCR process System Engineer to track Completed Verifications on a Verification Matrix

21 PFP IPDR 2010/6/ ATLO Issues Contamination Control –Dust Covers –Purge Magnetics –Keep high fields away from sensors (tools, equipment) Stimulus for CPT –LPW function generator EGSE –SEP radiation source LPW Boom Deployment –Cannot deploy booms at system level due to G-negation issues –Use simulators to verify ability to fire actuators High Voltage –SWEA, SWIA, STATIC HV cannot be operated in air –Limits ability to do end-to-end tests –Green-tag enable plugs protect against accidental operation –Can operate in thermal vac, but not a complete test –Need a post-environments test at SSL to fully verify functionality These issues are covered in the PFP to Spacecraft ICD.

22 PFP IPDR 2010/6/ I&T Schedule Milestones LPW DFB, BEB from LASP10/24/2011 EUV from LASP 12/1/2011 SWEA Analyzer from CESR 12/1/2011 MAG from GSFC 4/16/2012 SEP, LPW, PFDPU to PFP I&T 4/16/2012 SWEA, SWIA, STATIC to PFP I&T 4/30/2012 PFP PER 5/22/2012 PFP EMC6/6/2012 Component Qualification Start6/19/2012 PFP PSR8/23/2012 PFP due at LM10/1/2012