WRUC – Long Lead Time Commitments QSE Manager’s Working Group ERCOT Operations March 23, 2016.

Slides:



Advertisements
Similar presentations
INSULATING PRICE RESPONSIVE LOAD FROM RUC CAPACITY SHORT CHARGE Mark W. Smith J. Kay Trostle August 2008 DSWG.
Advertisements

IMPACT TO FREQUENCY CONTROL DURING STARTUP AND SHUT DOWN OF UNITS
Concerns with RUC Capacity Short Charge and Energy Trades.
NPRR605 Ancillary Service Make-Whole Payments Under a Watch.
NPRR 336, Authorize ERCOT to Procure Additional RRS During Severe Cold Weather Consideration of Tenaska and Luminant Comments.
1 Market Trials Open Market Participant Call Weekly Kick Off Aug 16, 2010.
1 Generator Telemetry and Market Prices WebEx Training July 28 th, 2015.
ERCOT RMR Deployment and Cost Proposals By: Matt Mereness and Ino Gonzalez.
NPRRs NPRR680 Allow QSEs to Self-Arrange AS Quantities Greater Than Their AS Obligation. This Nodal Protocol Revision Request (NPRR) proposes to allow.
Lead from the front Texas Nodal 1 Texas Nodal Market Management System Requirement Documents November 7, 2006 Sai Moorty MMS Project.
PRR 568 – Settlement Timeline PRR 638 – Invoice Timeline PRR 599 – Mismatch Notification COPS January 2006 Updates.
Demand Side Working Group Load Resource Performance Subgroup April 9, 2010 Mary Anne Brelinsky EDF Trading North America.
1 Settlement Changes R5 (SEP 2015) and R5.5 (OCT 2015) Blake Holt ERCOT COPS 9/14/2015.
Settlement of Mothballed RMR Resources for System Capacity November 15, 2011 RDTF Meeting Ino González ERCOT November 14, 2011.
July QMWG Update (WMS). GREDP Discussion GREDP is currently used as a compliance tool ERCOT is considering now just using it as an investigative tool.
Lead from the front Texas Nodal 1 Texas Nodal Load Frequency Control (LFC) EDS 3 Release 6 - Handbook EDS 3 Release 6 MP Planning.
1Texas Nodal Market Trials Update. 2Texas Nodal Full System Market and Reliability Test 24-Hour Test Observations Duration of Test for Week of 8/ Hour.
E x p e r i e n c e C o m m i t m e n t SM ERCOT Nodal – Fuel Cost Analysis Verifiable Cost Working Group October 6, 2008.
QMWG – Feb. 26, 2014 Discussion topic: NPRR585 Clarification of Administrative Pricing Requirements for Self-Committed Combined Cycle Combustion Turbines.
Protocol Revision Subcommittee Sandy Morris November 3, 2011.
Quick Start Resource – Payment for Start-Up at less than LSL Current NPRR language: ( 8) If a QSGR comes On-Line as a result of a Base Point less than.
1 Market Trials Update NATF June 1, 2010.
Nodal ATF 1 Nodal Advisory Task Force Update for TAC September 2 nd, 2010.
1 Cutover Market Call November 29, :00 AM.
RCWG Update to WMS July 11, Alternatives to Address Negative Prices At its June meeting, WMS directed RCWG to bring back something to vote on. RCWG.
Lead from the front Texas Nodal 1 Texas Nodal Startup Eligibility Day-Ahead and RUC Make-Whole Settlements ERCOT Settlements & Billing.
7 August, 2006 TPTF MMS Issues Review Brandon Whittle Lead, Real-Time Market Operations.
COPS – ERCOT PROJECTS UPDATE WHOLESALE MARKET DEVELOPMENT Paula Feuerbacher February 22, 2005.
Texas Nodal © Electric Reliability Council of Texas, Inc. All rights reserved. 1 Nodal Verifiable Costs Process WMS Meeting May 15, 2007 Ino.
NPRRs 663NPRR Ancillary Service Insufficiency Actions. This Nodal Protocol Revision Request (NPRR) specifies the actions ERCOT will take to ensure sufficient.
N ODAL P ROGRAM U PDATE TO C OPS Jim Galvin.
March 13, 2007 – Slide 1 ERCOT Nodal 101 COPS Market Guide Commercial Operations Market Guide Section 5 a. Overview of ERCOT ERCOT Overview Market Overview.
Small Resettlements A Proposal to Reduce Impact on ERCOT and Market Participants.
1 Market Trials Update NATF May 4, 2010.
Scheduling and Operating Transmission Devices in the Nodal Environment.
QSE Managers Working Group Report to WMS, April 8, 2011 S. Looney, Luminant.
Settlement Update Blake Holt ERCOT 2/15/2016. Agenda NPRR689 – R1 – 02/10/16 NPRR744 – Buy-Back notification NPRR746 – Negative load impacts 2016 Settlement.
RPRS Settlement Examples Market Support Services March 30, 2005 March 14, 2006 Presented by ERCOT Art Deller Bill Kettlewell.
1 Nodal Stabilization Market Call December 27, 2010.
1/07/2014 QMWG – RUC and AS update QMWG – ERCOT Update ERCOT Market Analysis.
Texas Nodal © Electric Reliability Council of Texas, Inc. All rights reserved. 1 Verifiable Costs for Nodal WMS Meeting.
© ERCOT and 2004 Fleet Deployment and Settlements WMS Meeting August 19, 2004 Ino Gonzalez ERCOT Settlements
1 Market Trials DAM/RUC/SASM Weekly Update March 19, 2010.
1 Market Trials Open Market Participant Call Weekly Kick Off Aug 09, 2010.
1 Market Trials Open Market Participant Call Weekly Kick Off May 10, 2010.
Real Time Balancing (RTB) & Resource Plan Statuses Change to the QSE practice of showing offline units as online and available ERCOT Presentation to ROS.
Retail Workshop ERCOT Nodal Update October 06, 2010.
Text reason for Deviation from Defined High Sustained Limit/Low Sustained Limit John Adams January 5, 2010 Nodal Advisory Task Force.
Day-Ahead Market Discussion/Clarification TPTF April 24, 2006.
07/27/2006 Overview of Replacement Reserve Procurement ERCOT Staff PRS RPRS Task Force.
July 15, 2011 Reliability Deployments Task Force Meeting ERCOT Studies and Proposal on Reliability Energy Pricing John Dumas Director Wholesale Market.
Lead from the front Texas Nodal 1 Texas Nodal Market Management System Update on TPTF Comments on MMS Clarification Notes May 21,
NPRRs 705NPRR Provides Consistency for References to the End Date of the Generation Interconnection Process. In the Resource Interconnection Handbook,
Settlement of Ancillary Service Infeasibility ERCOT QMWG April 15, 2016.
1 February, 2012 QMWG S&B Protocol Clarifications QSE-Requested Decommitment of a DAM Commitment ERCOT Mandy Bauld.
IMM alternate framework for Look-Ahead SCED November 21, 2011.
Lead from the front Texas Nodal 1 Texas Nodal EDS4 - Approach 11/28/2007.
Reliability Must Run Resources for Summer Slide 2 RMR for Summer 2011 RMR Contracts for Mothballed Units ERCOT has signed RMR Agreements with two.
Texas Nodal Program ERCOT Readiness & Transition (ERT) Supplemental Information TPTF January 12, 2009 Kevin Frankeny.
Non-Spin Deployment Resmi Surendran. RUC Awarded Ancillary Service Bring Resources On-Line if awarding REG or RRS When awarding Non-Spin – First award.
Use of ONTEST Resource Status over Telemetry: – ERCOT protocol permits the use of telemetered Resource Status code “ONTEST” during periods of start-up.
ERCOT Market Education Market Role in Emergency Operations OTS 2016.
Market Trials Update NATF March 2,
Settlement Update Austin Rosel ERCOT February 27, 2017.
Nodal Program Update to Cops
Cutover Market Call November 29, :30 PM
ERCOT Market Design & Operations
Current FRRS Language & Explanation of Posted Data
Market Trials Open Market Participant Call
Market Trials Open Market Participant Call
Presentation transcript:

WRUC – Long Lead Time Commitments QSE Manager’s Working Group ERCOT Operations March 23, 2016

PUBLIC Long Lead Time Resources To ensure that we have the long lead time resources online, we will notify participants when we initiate a WATCH due to inclement weather conditions and inform that we will be running SASM for an increase in AS for the inclement weather day. WRUC relies upon accurate COP data. The lack of accurate COPs data makes if very difficult for the Operator to review and act upon the results. ERCOT has recently seen changes in the behavioral pattern of coal units specifically. 2

PUBLIC Operator actions – Long Lead Time Resource Example Operator runs WRUC after 1:00am Jan. 9 th and confirms a resource is needed to solve congestion starting Jan.11 at 4:00am. Resource is off and available with a 36hr startup time for an Outage scheduled to last 4 days. Jan. 9 th, Issue an Electronic Dispatch Instruction (EDI), this data is also sent to S&B Jan. 10 th Unit1 is committed in DRUC for Jan. 11 th Jan 11 th Unit 1 is committed in HRUC for Jan. 12 th Jan 12 th Unit 1 is committed in HRUC for Jan. 13 th Jan 13 th Unit 1 is committed in HRUC for Jan. 14 th HRUC will monitor to extend commitment if resource is needed for additional time. 3

PUBLIC Settlement action – Long Lead Time Resource Unit1 was not eligible for Start Up in the previous example RUC Startup Cost Eligibility (c) The generation breakers must have been open, as indicated by a telemetered Resource status of Off-Line, for at least five minutes during the six hours preceding the first RUC-Committed Hour; and (d) The generation breakers must have been closed, as indicated by a telemetered Resource status of On-Line, for at least one minute during the RUC commitment period or after the determined five- minute open breaker, as indicated by a telemetered Resource status of Off-Line, in the six hours preceding the first RUC-Committed Hour. Unit1 was eligible for Minimum Energy and received a Make Whole payment for each day. The QSEs that were short at the DRUC/HRUC each day were charged for the next day’s RUC Make Whole. 4

PUBLIC Long Lead Time Resources – Changes needed for S&B Startup eligibility? 1.One suggestion has been to have QSE dispute and put in a settlement adjustment to pay start up. Would require Protocol language change but no system impacts. 2.Are there concerns with this? 3.Other ideas? 5

PUBLIC Questions? 6