DOE Review, 6/2/2011Answers to Committee Questions – Magnet Systems Answers to committee questions - magnets.

Slides:



Advertisements
Similar presentations
Superconducting Magnet Program S. Gourlay CERN March 11-12, Lawrence Berkeley National Laboratory IR Quad R&D Program LHC IR Upgrade Stephen A.
Advertisements

September 2007 FP7-IA HFM JRA proposal G. de Rijk (CERN)1 FP7-IA HFM JRA proposal   The proposal is under discussion: we welcome input from potential.
11 September 2007 FP7-IA HFM JRA proposal G. de Rijk (CERN)1 FP7-IA HFM JRA proposal   Outline Motivation General description Proposed Work Packages.
1 Letter of Rossi to Peggs (agred with Schmickler and Devred) April 2005  We strongly believe that the major steps in the near term are: 1)Construction.
Superconducting Large Bore Sextupole for ILC
Oct , 2013, CDP D.R. Dietderich LARP Conductor & Cable Review 1 Conductor Development Program Support for LARP and HiLumi LARP- HiLumi Conductor.
Nb3Sn Cable and Insulation for LARP High-Gradient Quadrupole Magnets
11 Oct , 2013 by Video LBNL Cable Experience for HiLumi HiLumi LARP/LHC Strand and Cable Internal Review Oct , 2013 by Video D.R. Dietderich,
LARP review, Fermilab, 6/10/2013Magnet Project Overview – G. Sabbi 1 HL-LHC IR Quadrupole Magnet Project Overview GianLuca Sabbi Internal Review of proposed.
E. Todesco PROPOSAL OF APERTURE FOR THE INNER TRIPLET E. Todesco CERN, Geneva Switzerland With relevant inputs from colleagues F. Cerutti, S. Fartoukh,
AARD Sub-panel at Fermilab Feb , 2006 LARP Magnet R&D Program - S. Gourlay1 BNL -FNAL - LBNL - SLAC LARP Magnet R&D Program Steve Gourlay AARD Sub-Panel.
LQ status and plans – G. Ambrosio 1 LARP Collaboration Meeting - LBNL, April , 2006 BNL - FNAL - LBNL - SLAC OUTLINE: Goals, Input and Output Sub-tasks.
11 T Nb3Sn Demonstrator Dipole R&D Strategy and Status
Plans and schedule for QXF Giorgio Ambrosio and Paolo Ferracin Joint LARP/CM20 HiLumi meeting Napa Valley, CA, USA 8-10 April, 2013 The HiLumi LHC Design.
ASC 2012Nb 3 Sn IR Quadrupoles for HL-LHC – G. Sabbi 1 Nb 3 Sn IR Quadrupoles for HL-LHC BNL - FNAL - LBNL - SLAC GianLuca Sabbi for the US LHC Accelerator.
Lab Coordination Meeting 9/25/13Introduction – G. Sabbi 1 Magnet Development Plan Update Overview GianLuca Sabbi LARP Lab Coordination Meeting September.
Title – xxxx 1 LARP & US-HiLumi Contribution to the Inner Triplet Quadrupoles G. Ambrosio Cost and Schedule Review CERN, March 9 th -11 th 2015.
Lab Coordination Meeting 3/21/13LHC IR Quadrupole Plan – G. Sabbi 1 LARP Magnet Systems Plan GianLuca Sabbi Lab Coordination Meeting March 21, 2013.
HL-LHC Annual Meeting, November 2013HQ Planning – G. Sabbi 1 HQ Status and Plans G. Sabbi High Luminosity LHC Annual Meeting Daresbury, UK, November 11-14,
ASC 2014Nb 3 Sn Block Coil Dipoles for a 100 TeV Hadron Collider – G. Sabbi 1 Performance characteristics of Nb 3 Sn block-coil dipoles for a 100 TeV hadron.
11 T Dipole Informal Coil and Assembly Readiness Review CERN September 2013 Review committee: Herman Ten Kate CERN (Chair) Fred Nobrega FNAL Davide.
S. Caspi, LBNL HQ Progress and Schedule Shlomo Caspi LBNL LARP Collaboration Meeting – CM13 Port Jefferson November 4-6, 2009.
Helene Felice 11/16/2011 LARP Collaboration Meeting 17 1 st HiLumi Collaboration Meeting CERN Status on HQ Coil Design and Fabrication.
Review of Quench Limits FermilabAccelerator Physics Center Nikolai Mokhov Fermilab 1 st HiLumi LHC / LARP Collaboration Meeting CERN November 16-18, 2011.
LARP DOE Review, 7/9/2012Magnet Systems Introduction – G. Sabbi 1 Magnet Systems Overview and HQ Program GianLuca Sabbi 2012 DOE Review of LARP SLAC, July.
MQXF support structure An extension of LARP experience Helene Felice MQXF Design Review December 10 th to 12 th, 2014 CERN.
LARP Magnets FNAL contribution to LARP (LHC Accelerator Research Program) FNAL core-program support to LARP DOE Annual Program Review - May 16-18, 2006.
J. Strait Fermilab 16 October 2006 Consideration on LHC upgrade from A US perspective.
LARP Magnet Progress Michael Lamm For the LARP Collaboration bnl - fnal - lbnl - slac US LHC Accelerator Research Program All Experimenters’ Meeting Monday,
Subscale quadrupole (SQ) series Paolo Ferracin LARP DoE Review FNAL June 12-14, 2006.
LARP Collaboration Meeting, April 26-28, 2006Gian Luca Sabbi HQ Design Study (WBS ) LARP Collaboration Meeting April 26-28, 2006 N. Andreev, E.
F. Savary Question 1 A. Magnet design criteria for the prototype and production magnet to be tested before the installation into the tunnel.
Joint IR Studies: Operating Margins Nikolai Mokhov Fermilab bnl - fnal- lbnl - slac US LHC Accelerator Research Program LARP Collaboration Meeting SLAC.
16 T Dipole Design Options: Input Parameters and Evaluation Criteria F. Toral - CIEMAT CIEMAT-VC, Sept. 4th, 2015.
Long Quadrupole – G. Ambrosio 1 LARP Collaboration Meeting – FNAL, Oct , 2008 BNL - FNAL - LBNL - SLAC Long Quadrupole Giorgio Ambrosio LARP Collaboration.
HE-LHC, 10/14/2010GianLuca SabbiUS LARP Magnet Development LHC Accelerator Research Program Magnet Development GianLuca Sabbi for the US LARP collaboration.
E. Todesco OUTPUT OF THE CABLE REVIEW E. Todesco and the QXF team CERN, Geneva Switzerland CERN, 10 th December 2014 QXF design review, CERN.
LARP CM17, 11/16/2011Magnet Systems Overview – G. Sabbi 1 Magnet Systems Overview GianLuca Sabbi LARP Collaboration Meeting 17 November 16, 2011 BNL -
Helene Felice HQ Test Results Review Thursday December 16 th Overview of HQ coils and Magnet.
HTS for Upgrades: overview of test requirements Amalia Ballarino, CERN Review of superconductors and magnet laboratories, A. Ballarino.
U.S. Activities on the High-Luminosity LHC: LARP Sustainability & Evolution as a Construction Project HiLumi-LARP Collaboration Meeting October 26, 2015.
11 T Dipole Project CERN Status M. Karppinen 11 T Management meeting 1 July 2013.
E. Todesco INTERACTION REGION MAGNETS E. Todesco On behalf of the WP3 collaboration CERN, Geneva, Switzerland CERN, 27 th October 2015.
FCC EuroCirCol kick-off,CERN, 3 rd June 2015.
1 BNL -FNAL - LBNL - SLAC P. Wanderer IR’07 - Frascati 7 November 2007 U.S. LARP Magnet Programme.
Report from Session 2 Main Dipoles. P. McIntyre 2005 – 24T ss Tripler, a lot of Bi-2212, Je = 800 A/mm2 E. Todesco T, 80% ss 30% NbTi 55 %NbSn.
Long Quad (LQ) & High Gradient (HQ) Series Alexander Zlobin bnl - fnal- lbnl - slac US LHC Accelerator Research Program DOE LARP review Fermilab, June.
LARP review, Fermilab, 6/10/2013Magnet Project Overview – G. Sabbi 1 HL-LHC IR Quadrupole Magnet Project Overview GianLuca Sabbi Internal Review of proposed.
MQXFS1 Test Results G. Chlachidze, J. DiMarco, S. Izquierdo-Bermudez, E. Ravaioli, S. Stoynev, T. Strauss et al. Joint LARP CM26/Hi-Lumi Meeting SLAC May.
Answers to the review committee G. Ambrosio, B.Bordini, P. Ferracin MQXF Conductor Review November 5-6, 2014 CERN.
LARP Collaboration Meeting 15 Nov 1-3, 2010 A2C- Materials Working Group Arup Ghosh (coordinator), Emanuela Barzi, Dan Cheng, Dan Dietderich, Soren Prestemon,
LHQ Coil Design and Features Miao Yu Fermilab May 09, 2012.
LARP CM15, SLAC, 11/3/2010GianLuca SabbiSummary of MS Parallel Sessions Summary of Magnet Systems Parallel Sessions GianLuca Sabbi LARP Collaboration Meeting.
LHC Performance Workshop 2012Nb 3 Sn IR Magnets – G. Sabbi 1 New Magnets for the IR How far are we from the HL-LHC Target? BNL - FNAL - LBNL - SLAC GianLuca.
2 nd LARP / HiLumi Collaboration Mtg, May 9, 2012LHQ Goals and Status – G. Ambrosio 11 LHQ Goals and Status Giorgio Ambrosio Fermilab 2 nd LARP / HiLumi.
LARP Collaboration Meeting 15 Nov 1-3, 2010 Conductor Procurement and Qualification Arup K. Ghosh (BNL) bnl - fnal- lbnl - slac US LHC Accelerator Research.
CERN QXF Conductor Procurement and Cable R&D A.Ballarino, B. Bordini and L. Oberli CERN, TE-MSC-SCD LARP Meeting, Napa, 9 April 2013.
DOE Review, 7/15/2010GianLuca SabbiMagnet Systems - Progress and Plans Magnet Systems Summary Progress and Plans GianLuca Sabbi DOE Review of the LHC Accelerator.
QXF Coil Fabrication & Tooling Reaction / Impregnation
TQ Program and Review Charge
Model magnet test results at FNAL
MQXF Goals & Plans G. Ambrosio MQXF Conductor Review
Nb3Sn IR Quadrupole Program
MQXF Planning Paolo Fessia, Frederic Savary, Ezio Todesco, Lucio Rossi - CERN Mike Anerella, Peter Wanderer - BNL Giorgio Ambrosio, Mark Kaducak - FNAL.
MQXF Short Models Status and Plans
Introduction to the technical content The Q4 magnet (MQYY) for HL-LHC
New Magnets for the IR How far are we from the HL-LHC Target?
HL LHC WP3 (magnets) TASK 2 ADVANCEMENT
Design of Nb3Sn IR quadrupoles with apertures larger than 120 mm
Design of Nb3Sn IR quadrupoles with apertures larger than 120 mm
Presentation transcript:

DOE Review, 6/2/2011Answers to Committee Questions – Magnet Systems Answers to committee questions - magnets

DOE Review, 6/2/2011Answers to Committee Questions – Magnet Systems Q1: Please clarify the definition of success for the operating point vs. short sample limit 1) Background: Last year following a review recommendation we established a CERN-US working group to discuss requirements and development plans for Nb 3 Sn and present recommendations to LARP, DOE, and CERN management One of the goals was to articulate a set of “success criteria” for magnet quench performance since it was felt that simply defining a target gradient as it was done for TQ/LQ (200 T/m) would not capture some of the key metrics such as fast training and no retraining after a thermal cycle Also, in order to apply to any magnet they were formulated relative to a maximum theoretical performance given the magnet design and conductor properties The committee expressed concern about the statement that Target operational quench level will be defined as 80% of SSL A wording issue? “Operating point” suggests operation in the machine; “short sample limit” does not have a unique definition

DOE Review, 6/2/2011Answers to Committee Questions – Magnet Systems Q1: Please clarify the definition of success for the operating point vs. short sample limit (slide 2/3) 2) Clarification attempt: This definition of success only applies to quench performance in R&D models – not to the design/expectations for HL-LHC We define the theoretical performance limit as the intersection of the magnet load line (peak field in the conductor as a function of current) and the cable critical current as function of field The conductor peak field is derived from calculations and the cable critical current is derived from extracted strand measurements using the ITER Ic measurement method The performance limit as defined above provides a maximum current that the magnet can sustain without quench. We take 80% of this value as a reference point in evaluating the magnet quench performance The 80% criteria will provide a reference gradient and peak field. The goals for training/retraining stay the same We will review with CERN to make sure we are on the same page

DOE Review, 6/2/2011Answers to Committee Questions – Magnet Systems Q2: HQ – Please list issues to be addressed and the focused remediation steps The causes of observed performance limitations: Coils under excessive compaction during curing and reaction Insufficient insulation between coil and ground Remediation: Reduce strand and cable size Room for 4.5% of azimuthal coil expansion Room for 2.3% of radial coil expansion Room of 4 mm/m (Island gap size) for coil axial contraction Thicker insulation between layers Improved electrical QA - Impulse test

DOE Review, 6/2/2011Answers to Committee Questions – Magnet Systems Practice coils Spare coil test Structure develop. & test LHQ01 coils LHQ01 assembly & test LHQ01b assembly & test LHQ02 coils, assembly & test LQS03 test HQ coil w new cable tested w mirror HQ02 w new cable Q3: How are the HQ and LHQ schedules integrated? (slide 1/2)

DOE Review, 6/2/2011Answers to Committee Questions – Magnet Systems Practice coils Spare coil test LHQ01 coils LQS03 test HQ coil w new cable tested w mirror HQ02 w new cable Q3: How are the HQ and LHQ schedules integrated? (slide 2/2)

DOE Review, 6/2/2011Answers to Committee Questions – Magnet Systems Q4: What are the deliverable goals of the magnet program and how are you going to measure them? Goal of LARP is to demonstrate Nb 3 Sn technology for use in the upgraded IR quads. Therefore LARP will have achieved its goal if the HL-LHC TDR will specify a Nb 3 Sn IR Quad  Clearly we are on the right track since Nb 3 Sn is now recognized as the primary candidate technology for the upgrade We agreed with CERN that a successful LHQ with 120 mm aperture and ~4 m length will be sufficient to complete this demonstration We agreed on a set of success criteria for LHQ quench performance However other key performance indicators/targets are not yet defined: field quality, thermal margin, radiation resistance etc.  Defining these targets for LHQ is not a goal of the design study, but the design study will help understand what is needed  Direct comparison between Nb 3 Sn and NbTi models with 120 mm aperture will also be an important decision criteria

DOE Review, 6/2/2011Answers to Committee Questions – Magnet Systems Q4 follow up: so why do we discuss infrastructure needs, construction schedules etc? There seems to be an implicit mandate or expectation that LARP will facilitate the construction planning until it is handed off to a project Last year’s review contained many recommendations pushing us in this direction. A legitimate question is whether some of these preparation steps would then become LARP tasks or not Examples: long infrastructure for the prototype, early conductor procurements, short model of the final design, the prototype itself Some guidance from the APUL (then LAUC) experience: LARP developed the proposal, but the 2008 DOE review of LARP strongly recommended to form a separate organization asap. However, there are some important differences in this case since HL- LHC IR Quads are fully aligned with LARP while the “Phase 1” scope was not, especially for magnets