SC Project Review of NCSX, April 8-10, 2008 C. A. Gentile NCSX Startup (WBS 85) C.A.Gentile NCSX CD-4 Startup.

Slides:



Advertisements
Similar presentations
August NSTX-U Team Meeting. Engineering Operations August 15, 2014 NSTX-U In-Vessel installations and calibrations have concluded, and activities have.
Advertisements

2013 NASA Safety and OH Directors’ Meeting Kennedy Space Center, FL 2013 NASA Safety and OH Directors’ Meeting Kennedy Space Center, FL “Moving Forward.
Effective Methods for Software and Systems Integration
Linac Front-End R&D --- Systems Integration and Meson Lab Setup
March 14, 2002GJG NCSX CRYOGENICS DESIGN DEVELOPMENT STATUS WBS-63.
NCSX May 12, 2005 ACC Review- Station 5 J.H. Chrzanowski - 1 ACC Review Of Modular Coil Manufacturing Facility Station No. 5 [VPI] the NCSX Manufacturing.
NCSX NCSX CDR May 21-23, 2002 Larry Dudek Slide 1 Facility Systems (WBS 62-65) L. Dudek, G. Gettelfinger, M. Kalish.
Standard WBS Version 1.0 WBS2-3.pptPage 1 Standard Work Breakdown Structure Legend = Decomposes to lower level WBS elements 4.0 Implementation 4.0 Implementation.
1 BROOKHAVEN SCIENCE ASSOCIATES Authorization Basis Plan Steven Hoey, ESH Manager NSLS-II Project Advisory Committee Meeting December 10 – 11, 2009.
1/18/2005Module 41 How the NCSX Project Does Business Work Planning & Design Review Processes.
I&T and Operating and Support Hazards Martin Nordby Chief Mechanical Engineer LSST Camera Safety Review August 18, 2015 R1.
NCSX Management Overview Hutch Neilson, NCSX Project Manager NCSX Conceptual Design Review Princeton, NJ May 23, 2002.
SC Project Review of NCSX, April 8-10, 2008 NSCX Poloidal Field Coils Michael Kalish.
NCSX NCSX Preliminary Design Review ‒ October 7-9, 2003 G. Oliaro 1 G. Oliaro - WBS 5 Central Instrumentation/Data Acquisition and Controls Princeton Plasma.
The NSTX-U Electric Arc Introductory comments on the process of recovery Stewart Prager May, 2015.
1 BROOKHAVEN SCIENCE ASSOCIATES CFAC Review Marty Fallier Director for Conventional Facilities CD-2 Planning May 8, 2007.
NCSX NCSX CDR May S. Ramakrishnan Slide 1 Electrical Power Systems (WBS 4) S. Ramakrishnan NCSX CDR May
NCSX 1 NCSX Engineering Overview Wayne Reiersen NCSX Engineering Manager On behalf of the NCSX Team.
Activity Certification Committee Charles Gentile On behalf of the NSTX-U ACC Princeton Plasma Physics Laboratory NSTX Upgrade Project Readiness for Operations.
1 Kenneth Osborne, 9/14/07 Inter Group communications at the Advanced Light Source. Overview of the different methods of communication between different.
SC Project Review of NCSX, April 8-10, 2008 Central Controls and Computing WBS51 & 52 P. Sichta WBS5 Work Package Manager.
February NSTX-U Team Meeting. Engineering Operations Feb. 11, 2014 NSTX-U In-Vessel installations and Calibrations to conclude in late March (3/28/2014)
July LEReC Review July 2014 Low Energy RHIC electron Cooling Edward T. Lessard ESHQ.
NCSX NCSX Design Review Guide May 27, 2005 Wayne Reiersen NCSX.
CLIC Implementation Studies Ph. Lebrun & J. Osborne CERN CLIC Collaboration Meeting addressing the Work Packages CERN, 3-4 November 2011.
1 NSTX Upgrade Progress Report May 7 th, 2013 Ron Strykowsky, Erik Perry, Tim Stevenson, Larry Dudek, Steve Langish, Tom Egebo, Mike Williams and the NSTXU.
April NSTX-U Team Meeting. Engineering Operations April 25, 2014 NSTX-U In-Vessel installations and Calibrations to conclude in mid-June to shift activities.
Main Requirements on Different Stages of the Licensing Process for New Nuclear Facilities Module 4.5/1 Design Geoff Vaughan University of Central Lancashire,
12/2/04Module 2D1 The NCSX Engineering Web – An Overview Part IV Engineering Management & Systems Engineering and Other.
SC Project Review of NCSX, April 8-10, 2008 NCSX Coil Services P.L. Goranson Work Package 161.
SC Project Review of NCSX, April 8-10, 2008 NCSX Cryogenics Systems WBS-62 Steve Raftopoulos NCSX Cryogenic Systems WBS(62)
Progress to Date PPPL Advisory Board Meeting May 20101NSTX Upgrade – R. L. Strykowsky CD-0 Approved February 2009 The NSTX Upgrade Project organization.
SC Project Review of NCSX, April 8-10, 2008 NCSX Fueling and Vacuum Pumping Systems W. Blanchard WBS 21 and 22 Manager.
Anthony Indelicato DOE-Princeton Site Office May 2012 Construction Progress Review for the NSTX Upgrade Project Construction Progress Review for the NSTX.
PU-PPPL Earned Value Management System Overview Thomas Egebo October 4-6, 2011 Princeton University Plasma Physics Laboratory EVMS Certification Review.
NCSX NCSX TF Coil Procurement 1 February 3, 2006 Michael Kalish NCSX TF Coil Procurement.
Conceptual Design Requirements for FIRE John A. Schmidt FIRE PVR March 31, 2004.
SC Project Review of NCSX, April 8-10, 2008 S. Ramakrishnan - 1 Electrical Power Systems (WBS 4) S. Ramakrishnan NCSX PWR System April
NCSX Systems Engineering Management Plan Peer Review Bob Simmons May 15, 2003.
1Page # Machine Assembly WBS 700 By: James H. Chrzanowski January 24, 2001.
NCSX Field Period Assembly (FPA) Operations, Cost and Schedule, Staffing, and Metrology Utilization Mike Viola Field Period Assembly Manager NCSX FPA Peer.
NCSX Project Overview Hutch Neilson, NCSX Project Manager For the NCSX Team NCSX Conceptual Design Review Princeton, NJ May 21, 2002.
F. Dahlgren -SC Project Review of NCSX, April 8-10, 2008 PF, TF, & Trim Coil Supports (WBS-15) Core Base Support Structure (WBS-17) F. Dahlgren NCSX Coil.
Solar Probe Plus A NASA Mission to Touch the Sun March 2015 Instrument Suite Name Presenter's Name.
NCSX NCSX Project Meeting March 21, 2003 G. E. Oliaro Slide 1 WBS5 Central Instrumentation/Data Acquisition and Controls G. E. Oliaro Computer I&C, Network.
U.S. Department of Energy’s Office of Science National Compact Stellarator Experiment (NCSX) Princeton Plasma Physics Laboratory (PPPL) CLOSEOUT PRESENTATION.
NCSX Field Period Assembly (FPA) Operations, Cost and schedule, staffing, and metrology utilization Mike Viola Field Period Assembly Manager NCSX FPA Peer.
NCSX NCSX CDR May 21-23, 2002 H.W. Kugel Slide 1 Conceptual Design for NCSX Auxiliary Systems Heating, Fueling,Wall Conditioning and Vacuum Systems.
SC Project Review of NCSX, April 8-10, 2008 NCSX Cryogenics Systems WBS-62 Steve Raftopoulos NCSX Cryogenic Systems WBS(62) Manager.
SC Project Review of NCSX, April 8-10, 2008 NCSX Machine Assembly E. D. Perry.
PPPL is Committed to the Success of NCSX Rob Goldston, Director Princeton Plasma Physics Laboratory August 15, 2007.
Strykowsky 1Project Review November 2, 2005 NCSX Project Review November 2, 2005 Cost and Schedule Ron Strykowsky.
Field Period Assembly Wayne Reiersen SC Project Review PPPL May 2006.
NCSX Hutch Neilson NCSX Project Manager NCSX Team Meeting January 20, 2005 Meeting Our Safety Management Responsibilities.
Engineering Operations Outage Status: Tile cleaning is complete Tentatively planning on 2 LITER operation. Design Review upcoming Shielding of HHFW/in-vessel.
EDM Fast Start Presentation WBS 11 – Assembly and Commissioning Vince Cianciolo, Paul Huffman May 23, 2006.
Engineering Operations Outage Status: New shielding of HHFW/in-vessel components has been completed. Fit-ups of OH bus lead upgrades to reduce error fields.
Preparations for working on Station 1 November 22, 2005.
NCSX Strykowsky 1Cost and Schedule Rebaseline April 25, 2005 NCSX Project Re-baseline Review April 25, 2005 Cost and Schedule Ron Strykowsky.
Business Continuity Disaster Planning
NCSX VVSA / MCWF FDR A Systems Engineering Perspective Wayne Reiersen Bob Simmons NCSX VVSA / MCWF FDR May 19-20, 2004 PPPL.
PPPL Stellarator Program Overview Hutch Neilson NCSX Project Manager NCSX Program Advisory Committee Meeting #6 Princeton, NJ December 9, 2002.
Engineering Operations TF Commissioning Mechanical testing of TF flag/box assemblies complete, inner bundle installed, and all joints made up. Joint resistance.
Failure Modes, Effects and Criticality Analysis
NCSX Strykowsky 1Independent Project Review (IPR) June 8-9, 2004 NCSX Project Review June 8-9, 2004 Cost, Schedule, and Project Controls Ron Strykowsky.
Instrumentation for status monitoring of SST-1 superconducting magnets
Turbomachinery Flow Visualization P08453
Experimental equipment Edgar L. Black February 17, 2019
Implementation of DOE O 420.2C at PPPL for NSTX-U
ESHAC #8 Safety Readiness Review Thomas Hansson, ESH
Presentation transcript:

SC Project Review of NCSX, April 8-10, 2008 C. A. Gentile NCSX Startup (WBS 85) C.A.Gentile NCSX CD-4 Startup

SC Project Review of NCSX, April 8-10, 2008 C. A. Gentile 2 NCSX Startup WBS 85 Objective = Safely bring NCSX on-line Concerns = People Safety, Environmental Safety, Machine Safety WBS 85 has two main components = Documentation + Safe Startup Startup Strategy = 10 week Startup Plan w/ First week 7 Startup Documentation = Slides 7 & 8 Startup Staffing and Positions = Slide 9 Basis of Startup cost & staffing requirements = TFTR (during D-T transition), NSTX Risks and Mitigation = Slide 10 Strong emphasis on pre-operational system testing and Activity Certification Committee (ACC) reviews. ACC is an independent cognizant group made up of PPPL and PSO membership. ACC performs detailed technical reviews including physical walk-down of reviewed system(s). Successfully implemented during NSTX startup.

SC Project Review of NCSX, April 8-10, 2008 C. A. Gentile 3 What Startup Will Demonstrate * Ohmically heated (first) plasma m major radius - > 0.5 T magnetic field - > 25 kA plasma current - coils operated at cryogenic temperatures - modular coils operated at 12 kA - TF coils operated at 2 kA - PF coils operated at 3 kA - PF5 & PF6 operated at 2 kA - central solenoid operated at 12 kA - ability to maintain high vacuum in vv - ability to bake at 150 C - ability to perform (multiple) e-beam (surface) mapping * see Hutch Neilson presentation for additional startup parameters

SC Project Review of NCSX, April 8-10, 2008 C. A. Gentile 4 WBS 85 Schedule - 1 ISTP

SC Project Review of NCSX, April 8-10, 2008 C. A. Gentile 5 WBS 85 Schedule - 2 ISTP

SC Project Review of NCSX, April 8-10, 2008 C. A. Gentile 6 Startup Flow Chart Subsystem PTPs

SC Project Review of NCSX, April 8-10, 2008 C. A. Gentile 7 Documentation needed for Startup NCSX Safety Assessment Document ( SAD) NCSX Integrated System Test Procedure (ISTP) Completed (sub-system) Pre-operational Test Procedures (PTP) NCSX Configuration and Interface Control Procedures NCSX Training Matrix First Plasma sub-system support procedures Torus VV pumpdown, cryo operations, search & secure procedures, power system procedures, coil operating procedures, bakeout procedures, control system procedures.

SC Project Review of NCSX, April 8-10, 2008 C. A. Gentile 8 Startup Documentation Effort Documentation Costs = $345 K - Documentation Development Team 28.5 weeks ( 1140 hours ) -Senior Lab & 28.5 week ( 1140 hours ) -Total for documentation development = 2280 hours -Equivalent ~ 1.10 person years of effort

SC Project Review of NCSX, April 8-10, 2008 C. A. Gentile 9 Startup Staffing and Positions Startup Team costs = $ 450 K - (1) Test Director = % FTE - (1) Chief Operations Engineer = % FTE - (1) Project Engineer = % FTE - (2) Machine Technicians = % FTE - (1) FCPC Technician = % FTE - (1) Cryo System Technician = % FTE - (1) AC Power Engineer = % FTE - (1) Computer Engineer = % FTE -Total Startup hours = 2720 hours -Equivalent ~ 1.3 person years of effort to safely startup NCSX

SC Project Review of NCSX, April 8-10, 2008 C. A. Gentile 10 Risks & Mitigation Incorrectly connecting power supply to coil leads - Coil leads to be clearly designated prior to startup, low power compass test. Ground Faults - Check for ground fault conditions during assembly (pre-startup) to mitigate impact on startup. Loop Faults - Check for loop faults during assembly (pre-startup). Control System - Pre-test wave forms and clock cycles to ensure control system operation. Loss of sub-system components (i.e., pumps ) - repair / replace.

SC Project Review of NCSX, April 8-10, 2008 C. A. Gentile 11 Conclusion Based on the startup of similar machines at PPPL NCSX startup requirements are understood. Good experience base and support for e-beam mapping from colleagues at ORNL, UW, Auburn. NCSX startup concerns are mostly about safety (people, environment, machine). Success of startup the result of prerequisite PTP’s, ACC reviews, ES&H Executive Safety Board review, safety certificate issuance, closing out post construction punch list items. Completion of NCSX ISTP will transition the machine from startup to operational.