Schedule Status Reporting Using MS Project Presented by: Ric Albani, PMP, PMI-SP PMI Scheduling Forum May 4, 2010
Purpose Demonstrate techniques for reporting schedule information using MS Project.
Background Common shortfalls with reporting schedule information include: -Too much text/narrative -Difficulty associating the information being reported against the schedule -WBS is not conducive to reporting -Lack of credible critical path/chain -Lack of baseline and/or variance analysis and corrective action
Sample Schedule Status Report MS Word document containing extracts from MS Project including: -Accomplishments Last Week -Work in Progress -Two-week Look Ahead -Variance Summary -Variance Detail -Corrective Action -Critical Path
Sample Schedule Status Report Accomplishments Last Week Tasks Started and/or Finished last week (4/19/10 – 4/23/10):
Sample Schedule Status Report Work In Progress
Sample Schedule Status Report Two-Week Look Ahead Tasks Scheduled to Start and/or Finish in next two weeks (4/26/10 – 5/7/10):
Sample Schedule Status Report Variance Summary Variance Report Summary (Finish Variance: Green = 0 days; Yellow = 1-5 days; Red = >5 days):
Sample Schedule Status Report Variance Detail Variance Report Summary (Finish Variance: Green = 0 days; Yellow = 1-5 days; Red = >5 days): The ‘Yellow’ one-day finish variances were a result of the cutover dates for all four Phase 1 terminals being rescheduled from Monday to Tuesday. The ‘Red’ finish variances were primarily caused by rescheduling the start of MPLS Readiness (Phase 1, Part 4) from 6/28/10 to 8/2/10. This rescheduling was a result of the three-week IOS-XR feature upgrade to v3.9.1 which needs to occur prior to MPLS. Variance Report Detail (Yellow/Red): No detail is provided since the cause for the ‘Yellow’ and ‘Red’ variances are described in the above section. Corrective Action (Yellow/Red): Two options exist for correcting the ‘Red’ variances, as described above, include: 1) reset the baseline for the Deployment Phase 2 milestones since the rescheduling was a result of a management decision to implement the three-week IOS-XR feature upgrade prior to MPLS Readiness; or 2) leave ‘as is’ for now, and defer the decision to re-baseline, or not, pending the results of Deployment Phase 1.
Sample Schedule Status Report Critical Path
Sample Schedule Status Report Construction Demonstration of the views, tables, filters, custom fields, and ‘copy picture’ function used to create the following items: -Accomplishments Last Week -Work in Progress -Two-week Look Ahead -Variance Summary -Critical Path
Sample Schedule Status Report Construction Accomplishments Last Week
Sample Schedule Status Report Construction Work in Progress -Use the ‘In Progress Tasks’ standard filter Critical Path -Use the ‘Critical Path’ standard filter
Sample Schedule Status Report Construction Two-week Look Ahead
Sample Schedule Status Report Construction ‘Copy Picture’ Function -Report (Menu)/Copy Picture…
Sample Schedule Status Report Construction Variance Summary -Requires creation of custom number (VarSum, Number1) and duration (Finish Var Ind, Duration1) fields
Sample Schedule Status Report Construction Variance Summary -Finish Variance Indicator (Duration1)
Sample Schedule Status Report Construction Variance Summary -Finish Variance Indicator (Duration1)
Summary Enhance schedule status reporting by using: -More graphics, less text/narrative -Status report information that is easily associated with the project schedule -A WBS that is well-organized and conducive to status reporting -A credible critical path/chain -A baseline to perform variance analysis and corrective action (as needed)
Ric Albani ric@rmaconsultinggroup.com 916.425.7724 www.rmaconsultinggroup.com