Jan , 2008 LCLS Undulator Week Dean R. Walters 1 Vacuum Components Undulator System SH Lee, J Morgan, and D Walters
Jan , 2008 LCLS Undulator Week Dean R. Walters 2 Major Components Vacuum Chamber Support Bellows Quadrupole Spool BFW Support RFBPM Support Long Break Spool Chambers Girder Extensions
Jan , 2008 LCLS Undulator Week Dean R. Walters 3 Vacuum Chamber Support
Jan , 2008 LCLS Undulator Week Dean R. Walters 4 Vacuum Chamber Support
Jan , 2008 LCLS Undulator Week Dean R. Walters 5 Adjustment Mechanism
Jan , 2008 LCLS Undulator Week Dean R. Walters 6 Vacuum Chamber Support Tubular Chamber Support First Article shipped from ANL 1/13/08, expect arrival at SLAC on 1/23/08 Expect balance to ship 2/16/08 Adjustment Mechanism Expect First Article to ship1/24/08 Expect final group 1 (35) to ship 2/22/08
Jan , 2008 LCLS Undulator Week Dean R. Walters 7 Bellows
Jan , 2008 LCLS Undulator Week Dean R. Walters 8 Bellows E Flange and Bellows Assy. Award No: 8A Award Date: 01/11/2008 Supplier: APPLIED ENERGY SYSTEMS INC Delivery Date: 05/11/2008 Based on the vendor's delivery schedule in the quote, It is expected on 02/16 for 1st article and completion 03/16 E for Beam Tube Award No: 8A Award Date: 01/16/2008 Supplier: WALCO TOOL & ENGINEERING CORP Delivery Date: 03/16/2008 It is expected on 02/16 for 1st article and completion 03/16 Cleaning, baking, and assemble at the APS before sending to SLAC Best estimate for the completed units 2/25/08 for the First Articles and the balance by 3/25/08
Jan , 2008 LCLS Undulator Week Dean R. Walters 9 Quadrupole Spools First Articles are at ANL Aluminum was plated onto parts
Jan , 2008 LCLS Undulator Week Dean R. Walters 10 Quadrupole Spools Best estimate of shipping (3) First Articles is 1/28/08 Balance to ship 2/21/08
Jan , 2008 LCLS Undulator Week Dean R. Walters 11 BFW & RFBPM Support BFW Support First Article planned to ship on 1/24/08
Jan , 2008 LCLS Undulator Week Dean R. Walters 12 Long Break Chambers The requisition for this has just recently been written. Seeking delivery of this to be 8 weeks. Chambers will have to come to ANL for leak check, clean, and bake.
Jan , 2008 LCLS Undulator Week Dean R. Walters 13 Girder Extension The requisition for this has just recently been written. Seeking delivery of this to be 8 weeks.